Case No.25 of 1999
Present : Shri S.C. Mahalik, Chairman
Shri D.K. Roy, Member
Date of Argument : 30.11.1999
Date of Order : 30.12.1999
IN THE MATTER OF : Revenue requirement and determination of
tariff for retail supply for CESCO.
O R D E R |
|
Central Electricity Supply
Company of Orissa Ltd. (CESCO, for short) 18, Forest Park, Bhubaneswar, the holder of
licence for carrying on the business of Distribution & Retail Supply of electricity in
its licensed area of supply namely Electrical Circles of Bhubaneswar, Cuttack, Dhenkanal
and Paradeep, submitted an application on 30.09.99 u/s
26 of the Orissa Electricity Reform Act, 1995 (Reform Act, 1995, for short) in respect
of tariff for retail supply of electricity to different categories of consumers.
|
2.0
|
The application of CESCO is in two volumes
(Vol.1 containing the main text & annexures and Vol. 2 containing evidential
documents). The Commissions staff, after preliminary scrutiny of the application,
raised a number of comments/queries thereon. The Commission forwarded the comments/queries
to CESCO and asked for additional information from CESCO in order to enable the Commission
to decide whether the filing would be treated as complete for the purpose of proceeding u/s 26 of the Reform Act, 1995.
|
2.1
|
CESCO provided clarifications
to the comments/queries in a bound volume on 5th October, 1999. In the light of
the clarifications to the comments/queries and additional information received from it,
the filing appeared to be generally in order. Accordingly the filing was treated as
complete and by Order No.2 dt.06.10.99, the application in question was admitted and issue
of public notice inviting objections to CESCOs application was ordered. |
2.1.1
|
Notice was published, as
approved by the Commission, in several local newspapers on two consecutive days in terms
of Clause 39 r/w sub-clause
(1) of Clause-126 of the Orissa Electricity Regulatory Commission (Conduct of Business)
Regulations, 1996 (Regulations, 1996, for short) outlining the broad features of the
Distribution & Retail Supply Licensees proposed tariff and the rates &
charges in a Schedule appended to the notice and inviting objections from interested
persons. The public notice required the interested persons to file their objections and
such documents as they seek to rely upon, supported by an affidavit, in six copies and to
indicate also if they would like to be heard in person by the Commission in terms of Clause 43 of the Regulations, 1996. The notice further
required the interested persons to serve a copy of the reply/objection alongwith the
documents relied upon on the petitioner/applicant and to file proof of such service before
the Commission at the time of filing of the reply/objection in terms of Clause 44 of the Regulations, 1996. |
2.1.2
|
The above public notice also called upon the
interested persons/objectors to inspect/peruse CESCOs application and take note
thereof during office hours within 15 days of the publication of the notice. The public
notice also permitted the interested persons to obtain the salient features of the
application on payment of Rs.20/- towards photocopying charges from the Managing Director,
CESCO, Bhubaneswar and all Executive Engineers in charge of Distribution Divisions such as
Bhubaneswar City Distribution Division, Bhubaneswar, Bhubaneswar Electrical Division,
Bhubaneswar, Cuttack City Distribution Division, Cuttack, Cuttack Electrical Division,
Cuttack, Puri Electrical Division, Puri, Khurda Electrical Division, Khurda, Nayagarh
Electrical Division, Nayagarh, Kendrapara Electrical Division No.I, Kendrapara, Kendrapara
Electrical Division No.-II, Marsaghai, Jagatsinghpur Electrical Division, Jagatsinghpur,
Athagarh Electrical Division, Athagarh, Salipur Electrical Division, Salipur, Talcher
Electrical Division, Chainpal, Dhenkanal Electrial Division, Dhenkanal and Angul
Electrical Division, Angul. They were also permitted to obtain a full set of the
application together with supporting materials on payment of Rs.100/- towards photocopying
charges.
|
2.1.3
|
The last date of filing of objection complying
with the terms & conditions of the public notice was initially fixed as 31.10.99. The
date fixed for filing of objection was extended to 15.11.99 because of the super cyclone
which hit Orissa on 29th and 30th October, 1999. A notice in print
media such as "Samaya" (dt.05.11.99) and "New Indian Express"
(dt.3.11.99) was published extending the date of filing of objection with regard to the
Retail Supply Tariff (RST) applications of the Distribution and Retail Supply Licensees
for the information of the general public and interested persons. The notice regarding
extension of the date of filing of the objection was also displayed on the office Notice
Board.
|
2.2
|
The Commission received 33 objections against
CESCOs application out of which twelve were rejected for non-compliance of the terms
& conditions as laid down in the public notice while 21 objections were admitted
according permission to the objectors for participating in the hearing. The objectors
whose objections were admitted for hearing are (1) M/s Shakti Sugars Cane Growers Rural
Development & Water Users Society, At Haripur, P.O. Korian, Dist. Dhenkanal. (2) M/s
Shakti Sugars Cane Growers Rural Development & Water Users Society, At/P.O. Baramba,
Dist. Cuttack. (3) M/s Nava Bharat Ferro Alloys Ltd., At/P.O. Khadgaprasad (Near
Meramundali Rly. Station), Dist. Dhenkanal. (4) M/s Utkal Chamber of Commerce &
Industry Ltd., Barabati Stadium, Cuttack. (5) M/s IPISTEEL Ltd., At/P.O. Buxi Bazar, Dist.
Cuttack. (6) General Secretary, Orissa Young Entrepreneurs Association, Industrial Estate,
Cuttack. (7) Shri P.N. Agarwal, Director, M/s Globe Aluminium Industries (P) Ltd., New
Industrial Estate, Jagatpur, Dist. Cuttack. (8) M/s Shakti Rural Development & Water
Users Society, 1412, Aurobindo Nagar, Madhupatana, Cuttack. (9) Shri K.N. Jena, General
Secretary, Orissa Consumers Association, Biswanath lane, Cuttack. (10) Shri K.
Acharya, President, Orissa Grahak Mohasangha, B-4, Pallaspali, Bhubaneswar. (11) Jt.
Secretary, Federation of Consumer Organisation, Orissa, Plot No.39, Budha Nagar,
Bhubaneswar (12) Shri Ramachandra Mohapatra, 550, Rameswarpatana, Bhubaneswar. (13) Shri
N. Jena, Secretary, Nayapalli Community Care Association, N-2/100, IRC Village, BBSR. (14)
Shri J. Mohapatra, M.D., M/s Ananda Industrial Gases Ltd., 239, Kharabela Nagar,
Bhubaneswar (15) Dr. S.K. Tamotia, President, Aditya Aluminium, 9th Floor, IDCO
Towers, Bhubaneswar. (16) M/s Senior Consultant and Advisor Group, N-2/95, Nayapalli,
Bhubaneswar. (17) M/s NALCO, P/1, Nayapalli, Bhubaneswar. (18) Shri R.C. Padhi, Retd.
Chief Engineer, MIG A/24, Brit Colony, Nayapalli, Bhubaneswar. (19) Executive Officer,
Bhubaneswar Municipal Corporation, Bhubaneswar. (20) Shri S.K. Nanda, Convenor, Energy
Panel, Confederation of Indian Industry, Eastern Region, 8, Forest Park, Bhubaneswar. (21)
Shri Dhaneswar Dhal, A-39, Sahid Nagar, Bhubaneswar.
|
2.3
|
After receipt of the objections and scrutiny
thereof, the Commission published a notice in two Oriya dailies and one English daily on
17th & 18th November99 whereunder the list of valid
objections with regard to CESCOs application and the date of hearing (30.11.99 and
if required, on the day following) were notified for the information of the general
public.
|
2.3.1
|
In terms of Clause-45
of the Regulations, 1996, the Commission permitted the applicant to file a rejoinder
to all the objections/reply filed by the objectors.
|
2.4
|
As notified, the hearing of
the RST application commenced on 30.11.99. None of the parties present made any prayer to
adduce oral or documentary evidence in course of the proceedings except those that were
filed supported by affidavit, in response to the public notice. |
2.5
|
Apart from the substantive objections, the
following legal objections were raised by different objectors as preliminary objections on
the maintainability of the tariff proceeding. The Commission heard the views of CESCO on
such objections. While one of the preliminary objections was disposed of by Order
dt.30.11.99, it was decided with the consent of the respective objectors that all other
preliminary objections would be dealt with by the Commission in the final order.
|
2.5.1
|
The preliminary objections are as follows :- |
2.5.1.1
|
Miscellaneous Appeal No.41 of
99 has been filed in the Honble High Court of Orissa being aggrieved with the
decision of the Commission in Case Nos.18/98 (BST) and 19/98 (RST) and therefore the present RST application should be
rejected by the Commission as an appeal is pending against the RST determined by the
Commission in its Order dt.21.11.98.
(Orissa Grahak Mohasangha Para-1) |
2.5.1.2
|
The RST application is
neither a new tariff nor an amendment to the existing tariff. It is only a revision of the
existing tariff. Therefore it is not permitted under law.
(Orissa Grahak Mohasangha Para-1) |
2.5.1.3
|
The RST determined by the
Commission by its Order dt.21.11.98 in Case No.19/98 which has
come into force from 01.12.98 cannot be revised or amended within a period of 3 years as
envisaged u/s 57-A (1)(e) of the Electricity (Supply) Act, 1948 (the Act, 1948, for short)
and therefore the present application for RST is not maintainable and liable to be
rejected outright.
(O.C.A. Para-1& 28) |
2.5.1.4
|
The RST determined by the
Commission (in Case No.19/98) cannot be amended within one financial year unless warranted
for adjustment of Fuel Surcharge.
(O.C.A. Para-2) |
2.5.1.5
|
OERC has not framed any
regulation by notification in official gazette for determination of tariff u/s 29 of the
Electricity Regulatory Commission Act, 1998 (the Commission Act, 1998, for short) and sub-section (2) of Section 26 of the Reform Act, 1995
and as such it lacks authority and power to consider the application of the licensee, be
it for determining a new tariff or revising or amending the existing one.
(O.C.A. Para-2&4) |
2.5.1.6
|
OERC has not yet specified
the methodology and procedure for calculating expected revenue from the charges and
therefore, it cannot consider the application of the licensee which is based on imaginary,
vague, and manipulated statement of facts and accounts in the absence of statutory audit
reports for the years 1997-98 and 1998-99.
(O.C.A. Para-5,6,&7) |
2.5.1.7
|
Licensee has failed to comply
with the conditions of the Licence to improve its efficiency, standard of service and
reduce its losses and as such, it should not be allowed to make good the losses
attributable to mal-administration, inefficiency, corruption, mismanagement, and
unwarranted expenses by way of penalising the consumers in the form of a tariff hike.
(O.C.A. Para-8&13) |
2.5.1.8
|
Since the application for RST
has not been filed prior to the commencement of the FY 1999-00 and has been filed in the
middle of the aforesaid FY, it cannot be entertained for setting a tariff for the balance
or remaining part of the FY.
(O.C.A. Para-9) |
2.5.1.9
|
As the OERC has not consulted
Commission Advisory Committee (CAC, for short) prior to the admission of the tariff
application and issue of public notice, it would not be legal and proper to proceed with
the case.
(O.C.A. Para-16) |
2.5.1.10
|
As the Commission, at present, is only a two
member Commission instead of three and the member of the Commission who shall be an
electrical engineer having experience of generation, transmission & distribution or
supply of electricity in terms of Section- 5 (1)(a) of the
Reform Act, 1995 having not been appointed as yet, the Commission now comprising two
members lacks quorum to undertake and dispose of the tariff proceeding because of the bar
created u/s 9(4) of the Reform Act, 1995.
|
2.6
|
We now deal with the first objection raised by
Orissa Grahak Mohasangha. Though M.A. No.41/99 has been filed in the Honble High
Court of Orissa against the final order in BST (Case No.18/98)
and RST (Case No.19/98), it is not the case of the objector that
the orders of the Commission in those two cases have been stayed by the Honble
Court. As the final orders in Case No.18/98 and 19/98 have not been stayed by the Honble Court, the plea of
the objector that the present application for RST should be rejected out of hand because
of the pendency of the M.A. bearing No.41/99 cannot be considered as a valid objection.
|
2.7
|
Regarding the second objection raised by Orissa
Grahak Mohasangha, it may be mentioned that nowhere in the RST application, the applicant
has sought for revision. On the other hand, the applicant has described the RST
application as one for amendment of Distribution & Retail Supply Tariff u/s 26 of the Reform Act, 1995. Similarly, in para-B at
page 5 of the RST application, it has been described as an application u/s 26 of the Reform Act, 1995 r/w Condition 21.3 of the Orissa Distribution & Retail Supply
Licence for amendment of the Retail Supply Tariff approved by the Commission vide its
Order dtd. November 21, 1998 in Case No.19/98.
|
2.7.1
|
Apparently there is some misunderstanding about Section 26 of the Reform Act, 1995 which is relevant to
the determination of tariff by the Commission. We would like to clarify that in this
section of the Reform Act, 1995, the procedure for determination of
a fresh tariff or amendment of tariff is the same. There is no vaccum or even interregnum
in operation of a tariff which has been defined as a schedule of standard prices or
charges. This has been amply made clear in Clause 116 of
Regulation, 1996. Depending on the gap between estimated revenue requirement and the
aggregate revenue which a licensee is permitted to recover by the tariff in operation, the
Commission may approve modification to the tariff or any part of tariff. Whether the
resultant determination is called a tariff or an amendment of tariff is not of any
consequence. The Commission cannot refuse to entertain an application if the Commission
finds that the licensees filing of revenue requirement and expected revenue from
charges is reasonably complete. It has to process it and take a decision within ninety
days of the complete filing. Sub-sec. (6) of Section
26 of the Reform Act, 1995 lays down that except in terms of fuel surcharge formula,
no tariff or part of tariff can be amended more than once in any financial year. The
natural corollary is that tariff or part of any tariff can be legitimately amended once in
a financial year. The current RST was set in November98 within the financial year
1998-99. Therefore an amendment to RST during financial year 1999-00, if found justified,
cannot be termed as illegal.
|
2.8
|
The third objection raised by Orissa
Consumers Association in paras 1 & 28 of its written objection is that when the
provisions of Sec.57-A of the Act, 1948 r/w the provisions of the Reform
Act, 1995 contemplate that charges for the supply of electricity, once fixed, shall be
in operation for three years, revision of tariff within one year would be without the
authority of law.
|
2.8.1
|
The objection is purportedly based on Section
57-A of the Act, 1948. We have considered the provision of Section 57-A of the Act, 1948
and particularly sub-clauses (c) and (e) of sub-section (1) of Section 57-A quoted by Shri
Jena. We find that these provisions are applicable to charges for electricity recommended
by a Rating Committee and approved by the State Govt. and stipulate that such charges
recommended by a Rating Committee for supply of electricity shall be in operation for such
period not exceeding three years as the State Govt. may specify in the order. Sub-section (7) of Section 26 of the Reform Act, 1995
repeals the constitution of a Rating Committee making the provisions of the Act, 1948
quoted by Shri Jena inapplicable in this case. We hold that the preliminary objection by
the learned counsel citing the provisions of Section 57-A of the Act, 1948 is without
merit as the said provision is inapplicable in tariff proceeding under Section 26 of the Reform Act, 1995.
|
2.9
|
The fourth objection that the RST determined in
Commissions Order dated 21.11.98 (in Case No.19/98) cannot
be amended within one financial year unless warranted for adjustment of fuel surcharge is
already dealt with by us in para 8 above.
|
2.10
|
The fifth objection of the Orissa
Consumers Association relates to lack of authority and power of the Commission to
consider the present application of the Licensee, be it for fixing a new tariff or
revising or amending an existing one on the ground that the Commission has not framed any
regulation for fixation of tariff u/s 29 of the Commission Act, 1998 and under sub-sec. (2) of Sec. 26 of the Reform Act, 1995, by
notification in the official gazette.
|
2.10.1
|
In fact, this objection of the Orissa
Consumers Association has two parts. The first part of the objection is that OERC
has not framed any regulation for determination of tariff u/s 29 of the Commission Act,
1998 and as such, it lacks authority and power to consider the application of the
licensee. In view of the above objection, the point for consideration is if Sec. 29 of the
Commission Act, 1998 is applicable to determination of tariff in the State of Orissa.
|
2.10.2
|
We understand that Shri K.N.
Jena, General Secretary of the Orissa Consumers Association has, in OJC No.6999/99,
challenged the procedure adopted by the State Govt. for appointment of a member of the
Commission which has fallen vacant on the ground that the State Govt. has not followed
procedure provided under the Commission Act, 1998 for such purpose. The aforesaid writ
application is yet to be disposed of laying down the law on the issues involved. |
2.10.3
|
Meanwhile, we are of the opinion that the Reform Act, 1995 holds good in all matters provided therein for OERC
including determination of tariff by the Commission in view of the special provision
relating to the Orissa Electricity Reform Act, 1995 and Haryana Electricity Reform Act,
1997 contemplated u/s 41 of the Commission Act, 1998. Sec. 41 of the Commission Act, 1998
clearly provides that the provisions of the said Act, in so far they relate to the State
Commissions, shall not apply to the Commissions established under the Orissa
Electricity Reform Act, 1995 or the Haryana State Electricity Reform Act, 1997.
|
2.10.4
|
The subject "electricity" is in the
Concurrent List of the Constitution of India. Therefore, the State of Orissa has a right
to enact law on electricity as it did in the Reform Act, 1995. The
Reform Act, 1995 has been assented to by the President of India on the 3rd
January, 1996. Further, Sec.41 of the Commission Act, 1998 is in the nature of a built-in
provision to safeguard the State Acts enacted earlier from the overriding effect of a
Central Act enacted later than the State Acts on the same subject of
"Electricity" and in the same field of establishing Electricity Regulatory
Commission. To sum up, we hold that the Commission Act, 1998 in so far as it relates to
State Commissions is not applicable to OERC.
|
2.10.5
|
The second part of the objection is that the
OERC has not framed any Regulation by notification in the official gazette for
determination of tariff under sub-section (2) of
Sec.26 of the Reform Act, 1995 and therefore it has no authority or power to consider
the application of the Licensee whether it is for a new tariff or revision or amendment of
the existing one. Before we deal with the factual aspect of this objection, we may point
out that while Shri Jena has stated in the first part of his objection that tariff should
be determined by OERC in accordance with the provisions of Sec. 29 of the Commission Act,
1998, he has also contended in the second part of his objection that OERC has not framed
regulations for fixation of tariff u/s 26(2) of the
Reform Act, 1995 and, therefore, OERC has no authority or power to consider the said
application of the Licensee. It appears to us that Shri Jena is challenging the Reform
Act, 1995 in so far as it relates to the OERC and at the same time relying on the same Reform Act, 1995 to challenge the alleged omission on the part of OERC.
|
2.10.6
|
The plea taken by Shri Jena that OERC has not
framed any regulation to determine tariff u/s 26(2)
of the Reform Act, 1995 has no basis in fact. Chapter-V of the Regulations,
1996 deals with regulations on tariff as envisaged in Chapter-VIII
of the Reform Act, 1995. The provisions contained in Chapter-V of the Regulations,
1996 has conferred upon the Commission a measure of discretion in the matter of
evolving its working procedure so long as these procedures conform to the principles of
natural justice. Accordingly, we are of the opinion that there is no merit in this
objection.
|
2.11
|
With regard to the sixth objection of the Orissa
Consumers Association, it may be pointed out that upon filing of the application for
RST by CESCO on September 30, 1999, the Commission in its letter No.2532 dt.01.10.99
pointed out certain omissions to be supplied by the applicant and raised certain queries
for clarification. The applicant supplied the omissions and filed clarification to the
queries on 5.10.99. After scrutiny of all the filings including a large number of
documentary evidence, the Commission treated the filings to be generally in order and the
tariff application in question was treated as complete.
|
2.11.1
|
It may be stated here that regulatory proceeding
cannot be treated at par with proceedings before common law courts. The Commission is
empowered under Clause-111
(Chapter-V) of the Regulations, 1996 to lay down methodologies and procedures for
calculating the expected revenue from charges and for determining the tariffs from time to
time with the further enabling provisions to add, amend, alter, revise, substitute or
otherwise change such methodologies and procedures at any time the Commission desires. Clause 113 of the said Regulation further provides that the
Commission may issue orders from time to time giving details of the manner in which
licensees revenue and tariff will be determined consistent with the provisions of
the Act and Regulations framed for the purpose. Even, where no Regulation has been framed
to deal with any matter or exercise any power under this Act, the Commission is free to
deal with such matters, powers and functions in the manner it thinks fit.
|
2.11.2
|
We would also like to emphasise that in
accordance with Section 10(5) of the Reform Act, 1995,
this Commission, in discharge of its function, shall be entitled to and may consult to the
extent it considers appropriate from time to time such persons or group of persons who may
be affected or likely to be affected by the decisions of the Commission. This provision
read with Sec. 26 of the Reform Act makes it clear
that the Commission has wide discretion to evolve its own methodology, procedures and
mechanism, subject, however, to the fact that they are just and reasonable and to carry on
its activities in cases where there is no provision in the Reform Act,
1995 or Regulations framed thereunder.
|
2.11.3
|
We have examined the objection that the filing
should not have been admitted in the absence of audited accounts for 1998-99. It may be
mentioned that the licensee has filed audited accounts for the year 1997-98 alongwith the
application. The audited accounts for the year 1998-99 have not been filed. In the normal
course, the revenue requirement for 1999-2000 alongwith request for amendment of tariff if
any should have been filed in December, 1998. If the application would have been filed by
the prescribed date, the licensee was in a position to file only the audited account for
1997-98. It appears that in view of the unsettling effects of transition involving
formation of new distribution companies, disinvestment of government shares and issue of
fresh license etc. the revenue requirements were not filed in December, 1998 which ought
to have been the case. This was filed in August99 when audited accounts for 1998-99
were not yet due.
|
2.12
|
Therefore, we are unable to agree with Shri Jena
that the tariff application of the Distribution & Retail Supply Licensee is defective,
incomplete and not maintainable.
|
2.13
|
The seventh preliminary objection raised by Shri
Jena relates to debarring the licensee from revising the tariff until and unless it
fulfilled the conditions of Distribution & Retail Supply Licence as amended from time
to time and complied with the order of the Commission.
|
2.13.1
|
Non compliance or inadequate compliance of the
licence conditions, if any, is a separate issue which cannot hold up the process of
determination of tariff. The Commission is bound by law as in Section 26 (6) of the Reform Act, 1995 to determine
the tariff within 90 days from the date the application was treated by the Commission as
complete. Elaborate provisions exist in the Reform Act, 1995 to deal with non-compliance
or violations of licence conditions. Filing of the revenue requirement and expected
revenue from charges is a statutory duty of the licensee as provided in s/s (4) of Sec.26 of the Reform Act, 1995 and
therefore this function must not be mixed up with other issues like non-compliance or
inadequate compliance of the licence conditions. The Commission is, therefore, of the
opinion that this objection has no merit and is accordingly overruled.
|
2.14
|
The eighth objection raised by Shri Jena for
Orissa Consumers Association that the application cannot be entertained in the
middle of the financial year 1999-00 has no basis in law. The Commission would have liked
strict adherence to the due date of filing of the revenue requirement i.e. by 31st
December, 1998 but the Commission is persuaded to accept the delay caused due to the
transitional problems. The Commission has also noted that there is no statutory time
schedule for application for tariff and hence the Commission cannot refuse to consider the
application if it is otherwise in order.
|
2.15
|
The ninth objection raised by Shri Jena, General
Secretary of the Orissa Consumers Association is that the Commission Advisory
Committee was not consulted by the Commission before admitting the application. Sub-section (6) of Sec.26 prescribes; "If the
Commission considers that the proposed tariff or amended tariff of a licensee does not
satisfy any of the provisions of sub-section (5),
it shall, within 90 days of the date of receipt of all information which it required, and
after consultation with the Commission Advisory Committee constituted u/s 32 and the
licensee, notify the licensee the proposed tariff or amended tariff." It is clear
from the language employed in sub-sec. (6) that
the question of consultation arises only before the Commission actually seeks to notify
the licensee the proposed tariff or amended tariff. Consultation with the Commission
Advisory Committee, therefore, is not a pre-requisite for admission of the licensees
application. It may be further mentioned that the Commission had already scheduled the
meeting of the CAC by the time the public hearing was taken up.
|
2.16
|
In order to dispose of the last objection, we
may point out that Sec.9(4) of the Reform Act, 1995
stipulates a quorum for review of any previous decision taken by the Commission. This
stipulation for quorum is applicable only if there is an explicit prayer for review of any
previous decision of the Commission. We have already stated while dealing with second
objection that the present application is not a prayer for review of the RST. It is an
application u/s 26(6) of the Act. We therefore
hold that there is no bar to or infirmity in the Commission proceeding to determine the
RST as prayed for by the applicant.
|
2.17
|
In the light of our observations in the above
paragraphs, we have to hold that there is no validity in any of the preliminary
objections, most of which were due to inadequate appreciation of regulatory procedure. We,
therefore, proceed to examine CESCOs proposal and give our findings on the same.
|
3.0
|
CESCOS PROPOSAL |
3.1
|
CESCO, which was initially incorporated as a
wholly-owned subsidiary company of GRIDCO, obtained licence from Orissa Electricity
Regulatory Commission for distribution and retail supply of electricity in Bhubaneswar,
Cuttack and Dhenkanal Electrical Circles with effect from April 1, 1999. With the sale of
51% of equity holding to a strategic investor i.e. a consortium of AES and Jyoti
Structures, CESCO became a joint sector company with effect from 01.09.99. Subsequent to
this restructuring and operation as a licenced utility, CESCO filed its calculation of
aggregate revenue for FY 1999-00 along with a proposal for tariff to meet the shortfall
between the revenue requirement and the expected revenue from charges.
|
3.2
|
CESCO estimates that it would draw around 3883
MU of power from GRIDCO with an average monthly maximum demand of 689.3 MVA. It estimates
sale of 2058.67 MU, an increase of 13.13% over the billed units for the year 1998-99.
|
3.3
|
CESCOs estimate of power purchase for the
year 1999-00 is Rs.497.44 crores comprising Rs.165.44 crores on account of demand charge
and Rs.332.00 crores on account of energy charge. The average cost per unit is estimated
at Rs.1.28 paise/unit.
|
3.4
|
The cost of distribution and sale of energy for
the year 1999-00 is estimated at Rs.196.40 crores which comprises employees cost, cost of
materials, administrative and general expenses, interest on loans borrowed from
organisations, bad debts and depreciation (less capitalisation on account of interest) and
legal expenses. There is a proposal for special appropriation of Rs.1.32 crores to cover
contribution to contingency reserve. CESCO estimates to earn a reasonable return of
Rs.17.14 crores on its capital base of Rs.100.28 crores.
|
3.5
|
The revenue requirement for Financial Year
1999-00 estimated by CESCO is at Table : 1.
Table : 1
Revenue Requirement for 1999-00 (Rs. in crores)
Purchase of energy |
497.44 |
Distribution & sale of energy |
196.40 |
Special appropriation |
1.32 |
Reasonable return |
17.14 |
Total |
712.30 |
|
3.6
|
CESCO has stated that the existing tariff and
charges are inadequate to meet the estimated revenue requirement of Rs.712.30 crores for
the FY 2000 and it would face a deficit of Rs.200.03 crores in the year 1999-00. It has
further stated that in view of the anticipated large deficit there is an urgent need to
develop a strategy to preserve the financial viability of CESCO. The revenue projection
made by CESCO for 1999-00 is given in Table : 2.
Table : 2
Estimated Revenue from charges for 1999-00 (Rs. in crores)
|
Revenue |
Deficit |
For FY 00 based on existing tariff |
512.27 |
200.03 |
For FY 00 based on tariff proposed in the application
for full year |
637.56 |
74.74 |
For FY 00 based on tariff proposed in the Application
for 4 months |
554.03 |
158.27 |
|
3.7
|
CESCO has stated that the system suffers from
high energy loss, inadequate customer service and inadequate overall system performance
which it intends to improve through corrective measures. CESCO has further stated that the
current tariff determined by the Commission is based on the application filed by GRIDCO
and does not fully meet the requirements of CESCO. The energy sales mix, losses, costs and
revenue requirement of CESCO are different from the erstwhile aggregated GRIDCO for which
the existing tariff needs to be modified in line with CESCOs operating environment
and constraints.
|
3.8
|
Main Features of
CESCOs Proposal |
3.8.1
|
CESCO has proposed a tariff to reduce the gap
between revenue requirement and expected revenue from existing tariff and charges for the
FY 1999-00. Based on the concept of rationalisation of tariff structure of the previous
years, it proposes to continue with the existing tariff structure to minimise variations
across separate zones for reasons of consumer acceptability. It intends to minimise
increase in demand and energy charges for both EHT and HT categories of consumers while
proposing enhancement of charges for LT category of consumers to reduce cross
subsidisation. CESCO has further stated that it needs to raise tariff by 39.05% across all
categories to reduce cross subsidisation. In its opinion, the tariff for EHT and HT
consumers has already reached a level that could force these consumers to set up their own
captive power plants. Therefore, tariff increase in LT category should be quite large i.e.
around 61.35%.
|
3.8.2
|
Main features of tariff proposal of CESCO are as
follows :-
|
3.8.2.1
|
Increase in monthly minimum
fixed charges for LT category consumers |
3.8.2.2
|
Introduction of demand charge for emergency
supply to captive power plants
|
3.8.2.3
|
Increase in energy charges at least by the rate
of inflation across all consumer subclasses for HT, LT, EHT categories
|
3.8.2.4
|
Increase in energy charges for irrigation to at
least 50% of cost of supply
|
3.8.2.5
|
Decrease in tariff and charges for power
intensive industries in EHT/HT categories. Consequently to do away with optional incentive
tariff applicable to these consumers
|
3.8.2.6
|
Incentive tariff for EHT and HT consumers except
for the Public Institution category. It proposes to maintain the difference between normal
tariff and incentive tariff by 60 paise/unit for EHT and by 70 paise/unit for HT
|
3.8.2.7
|
In addition to above, CESCO
has proposed two changes :-
|
3.9
|
Uncovered deficit
proposed in tariff |
3.9.1
|
CESCO has stated that the uncovered deficit from
expected revenue for the FY 1999-00 at proposed tariff and charges for the full year is
estimated as Rs.74.74 crores. If the proposed tariff is made applicable for part of the
year i.e. from December 1, 1999, the estimated uncovered deficit will be Rs.158.27 crores
(Table-2 refers). For maintaining the financial viability of the company and for rendering
effective service to the consumers, CESCO proposes to defer the uncovered deficit for the
year 1999-00 for the next three years i.e. till 2003, when it becomes recoverable with
interest.
|
3.10
|
Institution of purchased power price
adjustment clause (PPPAC)
|
3.10.1
|
CESCO has stated that its power purchase costs
are directly affected by GRIDCOs proposed bulk supply tariff as approved by OERC.
Since these costs are beyond the control of CESCO, the proposal is to insulate CESCO from
such risk through institution of a Purchased Power Price Adjustment Clause (PPPAC).
Further, this PPPAC should be regarded as a generic term to cover all increase in power
purchase cost which are beyond the control of CESCO.
|
3.11
|
Automatic pass through of change in Bulk
Supply Tariff to the Consumers
|
3.11.1
|
CESCO has stated that incremental changes in BST
if approved by the Commission will affect its power purchase cost. CESCO has proposed that
whenever a change in any of the components of the BST like demand charge, energy charge,
and fuel price adjustment rate is approved by the Commission, corresponding change in RST
should automatically be made as a pass through to the consumers without the need for any
further approval of the Commission.
|
3.12
|
CESCOs Prayer
|
3.12.1
|
CESCO has made the following
prayers to,
-
Approve the Retail Supply Tariff and Charges as proposed
-
Confirm revenue requirements, calculation of capital base and
calculation of clear profits for the year 1999-00
-
Allow deferment of all uncovered deficit for FY 00 and recovery with
interest after three years starting from FY 2003
-
Institute PPPAC to cover all changes in the cost of purchase of power
-
Automatic pass through of cost impact of change in Bulk Supply Tariff
to the consumers
-
Approve the proposed tariff to be effective from December 1, 1999
|
4.0
|
Objections
during hearingTwenty
one objections were admitted for personal hearing. The main issues of objections are
outlined below : |
4.1
|
SAKTHI SUGARS CANE
GROWERS RURAL DEVELOPMENT AND WATER USERS SOCIETY, DHENKANAL
|
4.2
|
SAKTHI RURAL DEVELOPMENT
& WATER USERS SOCIETY, BARAMBA
|
4.3
|
SAKTHI SUGARS CANE
GROWERS RURAL DEVELOPMENT AND WATER USERS SOCIETY, MADHUPATNA, CUTTACK
|
4.3.1
|
The three cooperative societies
mentioned above were represented through Mr. Satish Kumar, Secretary, Shakti Rural
Development & Water Users Society. He contended that the increase in tariff seems to
have necessiated due to increase in overhead cost, transmission loss, non-recovery of
energy dues, theft of electricity which are occurring due to mis management of the
licensee. Poor control over unauthorised consumers and mismanagement by the licensee
should not be transferred to the genuine retail consumers.
|
4.3.2
|
It was further submitted that with the proposed
tariff increase from Rs.0.80 to Rs.1.80 paise/unit for Irrigation the profitability per
acre will be reduced drastically and this will discourage sugar cane cultivation.
|
4.4
|
NAVA BHARAT FERRO ALLOYS LTD
|
4.4.1
|
Nava Bharat was represented through its
representative Shri A.K. Parida, Liaison Officer. He submitted that uniform special tariff
should be available for 24 hrs to all export oriented power intensive industries of the
state.
|
4.4.2
|
With the high percentage of hydro power (more
than 45 %), thermal stations of the state at pit heads and sale of more than 50% of power
in HT & EHT, the tariff of Orissa should have been much less.
|
4.4.3
|
A lot of money has been invested by CESCO after
reforms for system improvement while energy demand has not increased during last 3 years.
|
4.4.4
|
Consumers should not be penalised for bad debts
of CESCO which is due to its own inefficiency. OERC should not allow bad debts in the
revenue requirement.
|
4.5
|
THE UTKAL CHAMBER OF COMMERCE AND
INDUSTRY LTD., CUTTACK.
|
4.5.1
|
Shri M.V. Rao representing Utkal Chamber of
Commerce and Industries strongly objected to tariff increase on various grounds. He
submitted that retail tariff application of DISTCOs may be taken up after finalizing BST.
|
4.5.2
|
He argued that there is scope to reduce the BST
and hence the retail applications of DISTCOS should be rejected and that yearly tariff
revision harms industrial planning.
|
4.5.3
|
Tariff for all categories of consumers should be
related to the cost of supply so that the industrial consumers are attracted to install
industry in Orissa.
|
4.5.4
|
As promised by the Commission earlier, there
should have been perceptible reduction in T&D loss as the reform process has been in
operation for more than three years. For the purpose of tariff, distribution loss should
be considered at 28% and EHT loss as 3.5%.
|
4.5.5
|
Shri M.V. Rao objected to increased claims under
employee expenses, A&G expenses, interests , bad debts, He suggested that
depreciation, R&M expenses, and contribution to contingency reserves may be taken as
proposed by CESCO. According to him the revenue requirement of CESCO works out to
Rs.617.84 crores as against the proposed figure of Rs.712.30 crores. Since the total
expected revenue with existing tariff with 28% distribution loss comes to Rs.657.53
crores, no tariff hike is necessary for CESCO.
|
4.6
|
IPISTEEL LIMITED.
|
4.6.1
|
Shri K. Panigrahi, Advocate appeared on behalf
of M/s. IPI Steel Limited and raised following points against tariff filing.
|
4.6.2
|
The deficit seems to have been shown on higher
side by projecting higher expenses and higher T & D loss. The system loss can be
reduced in a phased manner at least by 10% during financial year 2000 which alone is
sufficient to make up the entire deficit.
|
4.6.3
|
The rate for mini steel plant has been proposed
to be Rs.4.03/Kwh which is equivalent to 218% of cost of supply whereas the tariff for
Kutirjyoti or Domestic category has been proposed to be Rs.100/Kwh and Rs.1.62/Kwh which
are equivalent to 24% and 38% of the cost of supply respectively.
|
4.6.4
|
IPISTEEL Limited is under rehabilitation
programme of BIFR and as per the directive of the State Govt, the company shall be
provided with power at concessional rate. BIFR Act has overriding effect on all other Acts
including OER Act and any deviation from the directives of BIFR will be ultravires.
|
4.7
|
ORISSA YOUNG ENTREPRENEURS ASSOCIATION,
INDUSTRIAL ESTATE, CUTTACK
|
4.7.1
|
Orissa Young Entrepreneurs Association,
Industrial Estate, Cuttack was represented through its General Secretary, Shri B.N. Mishra
who raised following objections:
|
4.7.2
|
The proposed rates of electricity tariff for the
year 1999-2000 is excessive, arbitrary, unjustified, lacks transparency and is liable to
be quashed.
|
4.7.3
|
Energy charges are increased every year without
corresponding increase in performance, efficiency and economic use of resources.
|
4.7.4
|
Employees cost should not be projected more than
1% than the earlier year.
|
4.7.5
|
Interest payment against non-payment of dues
should not be allowed to be shifted to consumers as it has occurred due to inefficiency
and bad management.
|
4.7.6
|
Expenses claimed by the licensee need to be
reviewed by the Hon'ble Commission.
|
4.7.7
|
There is no rationale for the levy of monthly
minimum fixed charge and demand charges upto a contract demand of 100 KW.
|
4.8
|
GLOBE ALUMINIUM INDUSTRIES PVT. LTD.
|
4.8.1
|
Shri Pavan Kumar Agarwal, Director representing
M/s. Globe Aluminum Industries(P) Ltd. submitted the following objections before the
Commission against tariff application :
|
4.8.2
|
T & D loss is over-estimated.
|
4.8.3
|
Interest payment on overdue should not be
allowed.
|
4.8.4
|
Expenditures projected need to be reviewed by
the Hon'ble Commission.
|
4.9
|
ORISSA CONSUMERS ASSOCIATION,
BHUBANESWAR
|
4.9.1
|
Shri K.N. Jena represented Orissa
Consumers Association. He objected on a variety of grounds as below :
|
4.9.2
|
This Commission cannot proceed and has no
authority and power to consider the application of the licensee either for revising or
fixing or amending the tariff which is in force.
|
4.9.3
|
The Commission has not yet specified the
methodology and procedure for calculating the expected revenue from the charges.
|
4.9.4
|
The licensee has not completed its functioning
even for a year and therefore it has no accounts statement of its own for even one
complete year. To make matters worse, the inherited account of latest complete year namely
98-99 has not been audited. The licensee be directed to produce their annual accounts and
serve copies thereof to the objectors and thereafter only tariff application processed.
|
4.9.5
|
Section 57A (1)(e) of Electricity (Supply) Act,
1948 provides that "charges for supply of electricity" fixed under clause (01)
shall be in operation for such period not exceeding 3 years as the state Govt. may specify
in the order. Hence the application under consideration is premature.
|
4.10
|
ORISSA GRAHAK MOHASANGHA, PALASPALLI,
BHUBANESWAR.
|
4.10.1
|
Shri K. Acharya represented Orissa Grahak
Mohasangha, Palaspalli, Bhubaneswar. He pleaded for uniform tariff for the state as a
whole. According to him consumers cannot be segregated zone wise.
|
4.10.2
|
He argued that the Orissa consumers should not
be made accountable for losses on unmetered supply and defective meters and theft by
non-consumers. The Electricity industry in Orissa required financial investment by private
entrepreneurs to develop the system and management. Obviously the Reform did not intend to
bring in private companies who would be propelled only by profit motive and go on
enhancing tariff.
|
4.10.3
|
He requested the Commission that the licensee
should be directed to withdraw proposal for increasing the present tariff at the close of
the millennium and take tangible steps to bring in efficiency in operation.
|
4.11
|
FEDERATION OF CONSUMERS ORGANISATION
|
4.11.1
|
Shri Debabrata Jena, Advocate represented the
Federation of Consumer Organisation. He stated that the Licensee has proposed revision of
tariff without improving efficiency.
|
4.11.2
|
The poor state of Orissa is always affected by
natural calamities and any increase of tariff will affect them as well as
industrialisation in the state.
|
4.12
|
RAMA CHANDRA MOHAPATRA
|
4.12.1
|
Shri R.C. Mohapatra, Retd. Chief Engineer did
not appear during the hearing. In his written submission, he stated that revised uniform
tariff should be applicable to the whole of the state of Orissa.
|
4.12.2
|
He assailed the proposal for increasing minimum
fixed charges. He found no justification in enhancing tariff without increasing efficiency
and reducing T&D loss.
|
4.13
|
NAYAPALLI COMMUNITY CARE ASSOCIATION
|
4.13.1
|
Shri B.N. Dash represented Nayapalli Community
Care Association. He stated that after reforms, a lot of investments have been made for
system improvement without appreciable increase in load.
|
4.13.2
|
It is desirable to take up consideration of BST
of GRIDCO before retail tariff of different companies.
|
4.13.3
|
As there is no competition. the purpose of
reforms to manage electricity industry in an efficient, economic and competitive manner in
the interest of consumers in particular and the state in general is defeated.
|
4.13.4
|
From the analysis it is found that there is no
necessity of increase in present tariff and rather, there should be reduction in the
existing tariff.
|
4.13.5
|
Interest for non payment of bills of GRIDCO is
due to inefficiency and bad management of CESCO and certainly the consumers are not to be
penalised for it.
|
4.14
|
ANAND INDUSTRIAL GASES LTD., BHUBANESWAR
|
4.14.1
|
Shri J.N. Mohapatra, MD, Anand Industrial Gases
Ltd., Bhubaneswar stated that increase in power tariff should always be related to hike in
coal prices, freight, transportation, electricity duty etc. not to absorb the transmission
loss operational loss and other factors like increase in overheads.
|
4.14.2
|
He highlighted the poor quality of power and
stated that the consumers have a right to expect better quality and efficiency from the
licensee who has the experience and wherewithal in the field of distribution.
|
4.14.3
|
He suggested for an incentive for night shift
operation of the industry to utilise the surplus available during the off-peak hours.
|
4.15
|
ADITYA ALUMINUM PROJECT, BHUBANESWAR
|
4.15.1
|
The representative of Aditya Aluminium Project,
Bhubaneswar in their submission have stated that :
|
4.15.2
|
Tariff for commercial and domestic category
should not be considered for revision at this stage as it is already on the higher side.
|
4.15.3
|
Tariff should be fixed for a period of at least
5 years and actual energy charges should be based on variation of consumable cost only and
the rise of minimum fixed charge should be related to the inflation during the year.
|
4.16
|
THE SENIOR CONSULTANT AND ADVISOR GROUP,
NAYAPALLI
|
4.16.1
|
Shri RP Mohapatra, Director of the Senior
Consultant and Advisor Group, Nayapalli in his submission stated that :
|
4.16.2
|
The bill should be very much clear and
informative to the consumer.
|
4.16.3
|
The proposals for dispensing with the slab
system is an unfair one and hit the poor honest and disciplined consumers.
|
4.16.4
|
The system frequency is remaining high most of
the time crossing the limits of ±3% over the declared frequency of 50 HZ. Such situation
is causing the consumers additional billing without their knowledge. This is a matter of
serious concern to all consumers and the OERC need to take proper note of this.
|
4.16.5
|
Due to super cyclone the people of Orissa are
suffering a lot. It should be the time to consider reduction of the tariff instead of
contemplating further increase under the present circumstances.
|
4.16.6
|
It is urged not to increase the tariff at least
for a period of next twelve months. |
|