>
DISTRIBUTION SYSTEM PLANNING
AND SECURITY STANDARDS,
1.TITLE 1.1 These standards may be called as:
1.2 Definitions: CBI & P Manual: Manual published by central Board of Irrigation and Power, a Technical body of the Government of India. KVA-KM Loading: Capacity of a line to deliver a certain load in KVA for a certain distance in KM with certain Voltage Regulation and Power Factor. P.G. Clamps: Parallel Groove Clamps used for conductor jumper connection. R.E.C. Specification: Specification issued by Rural
Electrification Corporation Ltd. (A Government of India Undertaking).
2. APPLICATION 2.1 Distribution System Planning
and Security Standards
2.2 Distribution
System Operating Standards
2.3 The standards applicable to
Distribution System at EHT shall be the same as provided under power
supply planning and security standard, operating standard, power supply operating standard
approved by the Commission under Condition
20 of Transmission and Bulk Supply License.
3. REFERENCE These standards also require reference to the following Acts, Rules, Codes etc.
4. DISTRIBUTION SYSTEM PLANNING & SECURITY STANDARDS 4.1 General: 4.1.1 The Licensee shall plan and develop its Distribution System, particularly to ensure that subject to the availability of adequate generating and transmitting capacity, the system is capable of providing consumers with a safe, reliable, economical and efficient supply of electricity. 4.1.2 The Licensee's Distribution System
shall conform to the statutory requirements of Indian Electricity Act 1910, Electricity
Supply Act 1948, and Indian Electricity Rules 1956.
4.2.1 The Licensee shall prepare a long term load forecast for a period of 5 (five) years in its Area of Supply taking into account the probable load growth and consumption pattern of the consumers. The Licensee shall adopt appropriate load forecasting methods using reliable data and relevant indices. The methods may include one or more of the following methods.
4.2.2 Consumers seeking to contract demands of 5MW and above shall submit application to the Licensee along with load data in the manner to be prescribed by the Licensee in conformity with Distribution Code, as follows :
4.2.3 The consumers shall inform in writing to the Licensee promptly regarding changes, if any, in their load demand and its scheduling. 4.2.4 The Licensee shall work out the annual Energy Demand and Peak Demand for each of the succeeding five years relating to each point of interconnection on the basis of its load forecast. 4.2.5 By suitable sampling and installation of meters the Licensee shall workout the Diversity Factor/Coincidence Factor of each class of consumers fed from each point of interconnection in the area of supply. The Licensee shall maintain a record of such data and update the same at last once in 5(five) years. The licensee shall prepare the long term load forecast based on these data as refered to in para 4.2.1. 4.2.6 The Licensee shall arrange to
publish a Data Book listing all System Data relating to its Distribution
System as detailed in the Distribution Code. The Data Book shall
be updated every year and copies of same shall be made available to any effected person
upon request on payment of fair copying charges:
4.3 Planning Standards Criteria 4.3.1 Standardization of Sizes and Ratings 4.3.2 Standardisation of Sub-Station Layouts 4.3.2.1 33/11kV Sub-Station (20MVA and above)
4.3.2.2 33/11kV Sub-Station (10 MVA above but less than 20MVA)
4.3.2.3 33/11kV Sub-Station (Less than 10MVA)
4.3.2.4 11/0.4kV 3-phase Distribution Transformer Centres
4.3.2.5 11/0.23kV 1-phase Distribution Transformers (up
to 16KVA Capacity.) 4.3.3 Design Criteria for Distribution lines: 4.3.3.1 The lines shall be designed and constructed in accordance with relevant provision of I.E. Rule 1956 applicable to overhead lines and under-ground cables. 4.3.3.2 The distribution network fed from 11/0.4kV transformers and 33/11kV transformers shall be initially planned as independent networks within their respective service area. A service area of any particular substation shall mean for this purpose, an area, load in which shall normally be supplied by that sub- station by one or more number of feeders, as required, without exceeding the specified KVA-KM Loading limit of any feeder within the area. 4.3.3.4 The Licensee shall take suitable measures, sufficiently in advance, to augment the capacity of the feeders in the event of the specified KVA-KM Loading of any feeder being exceeded. 4.3.3.5 The design of the distribution lines shall incorporate features to enable their augmentation, in future, with minimum interruption to power supply. The existing Rights of Way shall be fully exploited. 4.3.3.6 KVA-KM Loading limits for conductors may be calculated in accordance with a sample calculation shown at Annexure-I. 4.3.4 Capacitive Reactance compensation: 4.3.5 Service lines: 4.3.6 Metering Installations:
4.4 Security Standards:
5.1 General:
5.2 Operation Criteria:
5.2.1.1 Load monitoring:
5.2.1.2 Load Balancing: 5.2.2 Voltage Monitoring and Control 5.2.2.1 Voltage monitoring at each 33/11 kV Sub-station shall be carried out by data logging. 5.2.2.2 Voltage monitoring on the secondary side of 33/0.4kV and 11/0.4kV distribution transformers shall be carried out at least once in one year during Peak Load hours to cover at least two nos. of transformers in each 11KV feeder as follows:
5.2.2.3 Improvement to voltage conditions shall be achieved by operating ON LOAD TAP CHANGE CONTROL of transformers in the Distribution System where such facility exists. The Licensee shall contact over Telephone the operators of Transmission and Bulk Supply Licensee at the point of interconnection, to correct voltage at the sending end as required. 5.2.3 INTERRUPTION MONITORING 5.2.3.1 Licensee shall maintain accurate record of consumer interruption caused by (a) Planned and unplanned outages of following equipments in the Distribution System.
or (b) Outage of power supply from interconnection points with GRIDCO or other power supplier Each record shall contain at least the following information:
5.2.3.2 Based on the above records, the Licensee is required to evaluate and monitor electricity supply reliability indices as stated in "Statement of System Performance" appended at the end of this document. 5.2.4 Data Logging: 5.2.5 Load Management: 5.2.5.1 In the event of total or partial black outs of Transmission System or Regional System the Licensee shall follow procedures as laid down in the GRID CODE under the Section contingency planning. 5.2.5.2 In the event of breakdown within its own System, the Licensee shall restore/maintain supply within the limit specified under security standards (Sub Section 4.4) by taking appropriate measures. 5.2.6 Communication: 5.2.7 Safety Coordination: 5.2.7.1 The Licensee and consumers shall abide by the general safety requirements of the I.E.Rules 1956 for construction, installation, protection, operation and maintenance of electric supply lines and apparatus. 5.2.7.2 Procedures laid down in the relevant section of the grid code and distribution code shall be followed by the Licensee and its consumers, in this regard. 5.2.7.3 The Licensee and its consumers shall abide by provisions of I.E. Rules, 1956 under Chapter VII. "Electric supply lines, Systems and Apparatus for High and Extra High Voltages." 5.2.7.4 The Licensee shall develop its own Safety
Manual to satisfy requirements of I.E. Rules and implement the same.
KVA-KM LOADING 1. Conductor Data Conductor Size --------------------------------------(6/3.35mm + 1/3.35mm)ACSR Gross Area of Aluminium--------------------------52.95mm2 Copper Equivalent-----------------------------------32.26mm2 Resistance in ohms per KM (at 20°C)------------0.5449* Inductive reactance at 50 Hz in ohms per KM---0.421* * Appropriate values may be taken for any other temperature and equivalent spacing. 2. Assumptions Length of line-------------------------1 KM KVA loading--------------------------1000 KVA 3 phase voltage-----------------------11,000 V 3. Regulation Percent Regulation (approx) = {I (R cos ø + X sine ø) / E } x 100 Where I = Current per phase in amp Percent Regulation = {48.2 (0.5449 x 0.8 + 0.421 x 0.6) / 6351} x 100 = 0.523% For 1% Voltage Regulation the KVA-KM loading for the selected conductor
size at 0.8 PF will be 1912 KVA-KM. For any other Power Factor, voltage and conductor
temperature the Voltage Regulation may be calculated by substituting appropriate values of
current, Resistance Cos ø and Sine ø in the formula.
SHUNT CAPACITOR INSTALLATION 1. Capacitor Required KVAR = KVA1 (Sin ø1 [Cos ø1 / Cos ø2] . Sin ø2) Where KVAR is : amount of capacitance to be added to improve the Power Factor from Cos ø1 to Cos ø2. KVA1 is : Original KVA. 2. Optimum location of capacitors L = [1 (KVARC / 2 KVARL) x (2n-1)] Where, L = distance in per unit along the line from sub-station 3. Voltage Rise due to Capacitor installation % Rise = (KVARC.X) / 10V2 Where, X = Reactance per phase
STATEMENT OF SYSTEM PERFORMANCE Ref:- Condition 20.2 read with Condition 20.4 of Distribution and Retail Supply Licence A quarterly report on performance of the system, with reference to the operating standard shall be submitted to OERC within 25 days of end of each quarter i.e., by 25th of April, July, October and January each year. An annual report on the year ending 31st March shall be submitted by 25th April along with the report on the first quarter report. The report on the electricity supply reliability indices shall contain the following information : a) "SAIDI" or the System Average Interruption Duration Index : This represents the average time each consumers is interrupted. SAIDI is expressed by the following formula : SAIDI = Sum of consumer interruption durations / Total number of consumers served b) "SAIFI" or the System Average Interruption Frequency Index : This represents the average number of interruptions per consumer SAIFI is expressed by the following formula : SAIFI = Total number of consumer interruptions / Total number of consumer served c) "CAIDI" or the Customer Average Interruption Duration Index : This represents the average interruption duration or average time to restore service per interrupted consumer CAIDI is expressed by the following formula : CAIDI = Sum of consumer interruption durations / Total Number of consumer interruptions
= SAIDI / SAIFI |