| 8.0 | DETERMINATION OF TARIFF  | 
  
    | 8.1  | The determination of tariff by the Commission has been done
    after examination of all details based on the records submitted by the Licensee, written
    and oral representations of the objectors and after duly consulting the Commission
    Advisory Committee. In addition to this the Commission also gave due consideration to the
    comments and observations made by various national and international authorities on the
    tariff orders earlier issued by the Commission as well as suggestions and complaints
    received from the actual electricity users of Orissa during the past years. | 
  
    | 8.2 | The tariff structure that this Commission inherited was a
    highly distorted one and like the past years the Commission this year has also tried to
    further rationalise the tariff structure so as to ensure that there is a progressive
    increase in the rate of tariff for those who are paying less than the average cost of
    supply. The Commission has been taking steps for rationalisation of tariff i.e. gradually
    adopting a uniform rate for all consumer categories using electricity on the same voltage
    of supply which is a good measure of the cost of supply. The Commission considers it
    reasonable to determine tariff and charges as in the following paragraphs. | 
  
    | 8.3  | The tariff structure as it exists for different voltage of
    supply are summarised. | 
  
    | 8.3.1  | LT supply upto 100 KW/110 KVA : Kutir Jyoti
    consumers : Monthly Fixed Charge (Rs./ Month) Other classes of consumers : (a) Energy Charge (Paise/unit) (b) Monthly Minimum Fixed Charge (MMFC) (Rs./KW/ Month) | 
  
    | 8.3.2 | LT supply with connected load 110 KVA and above : 
      
        Demand Charge (Rs./KVA)
        Energy Charge (Paise/unit)
        Customer Service Charge (Rs./Month) | 
  
    | 8.3.3 | HT Consumers : 
      
        Demand Charge (Rs./KVA, Rs./KW)
        Energy Charge (Paise/unit)
        Customer Service Charge (Rs./Month) | 
  
    | 8.3.4  | EHT Consumers : 
      
        Demand Charge (Rs./KVA)
        Energy Charge (Paise/unit)
        Customer Service Charge (Rs./Month) | 
  
    | 8.3.5 | DC Services : Same as LT Supply for consumers
    with CD less than 100 KW. | 
  
    | 8.3.6 | Consumers covered under two-part tariff are not required to
    pay the MMFC but are to pay Demand Charge and Customer Service Charge. Consumers covered
    under single-part tariff and liable to pay MMFC will not be required to pay either the
    Demand or the Customer Service Charge. | 
  
    | 8.3.7  | In addition to above, certain other charges
    like power factor penalty, incentive, prompt payment rebate, meter rent, delayed payment
    surcharge, over drawal penalty/incentive, tariff for special class of consumers, other
    miscellaneous charges, etc. are to be payable in cases and circumstances mentioned in the
    later part of this order. The details of charges applicable to various categories of consumers
    classified under OERC Distribution (Condition of Supply) Code, 1998 are discussed
    hereafter. | 
  
    | 8.4 | Tariff for consumers availing power supply at LT | 
  
    | 8.4.1 | Monthly Minimum Fixed Charge (MMFC) for consumers with
    contract demand of less than 110 KVA | 
  
    | 8.4.1.1 | The MMFC as decided in the previous tariff order by the
    Commission is payable by the consumers with contract demand less than 110 KVA supplied
    power at LT. This is intended to meet a component of the fixed cost incurred in the system
    for meeting the consumers load and also to recover the expenses on maintenance of
    meter, meter reading, preparation of bills, delivery of bills, collection of revenue and
    maintenance of customer accounts. | 
  
    | 8.4.1.2  | The licensee had proposed an enhancement of the MMFC with
    which the Commission does not agree and decides that the existing rate of MMFC should
    continue as there has been no change in the Demand Charge payable by the licensee to the
    bulk supply licensee. Accordingly the rates applicable to all such customers shall be as
    given below at Table : 10. Table : 10 
      
        | Sl.No | Category of Consumers | Monthly Minimum Fixed Charge for first KW
        or part(Rs.) | Monthly Fixed Charge for any additional KW
        or part(Rs.) |  
        | LT Category |  
        | 1 | Kutir Jyoti  | 30 |   |  
        | 2 | Domestic (other than Kutir Jyoti) | 20 | 10 |  
        | 3 | Commercial | 30 | 20 |  
        | 4 | Irrigation | 20 | 10 |  
        | 5 | Street Lighting | 20 | 10 |  
        | 6 | Small Industry | 40 | 30 |  
        | 7 | Medium Industry | 80 | 50 |  
        | 8 | Public Institution | 80 | 50 |  
        | 9 | Public Water Works | 80 | 50 |   | 
  
    | 8.4.1.3 | Consumers with connected load of less than 110 KVA are
    provided with simple energy meters that only records energy consumption and not the
    maximum demand. The OERC (Condition of Supply) Regulation provides that contract demand
    for a connected load below 100 KW shall be the same as the connected load. Therefore, for
    the purpose of calculation of MMFC the connected load shall form a basis. | 
  
    | 8.4.2  | Energy Charge | 
  
    | 8.4.2.1 | Consumers with connected load less than 110 KVA The
    Commission in moving towards a cost-based tariff structure and as a first step has started
    rationalising various charges linked to the voltage of supply which reflects the cost of
    supply to that particular category of consumers. In keeping with that objective the
    Commission has decided that the Energy Charge per unit for supply at LT will be uniform
    rate for all classes of consumers except domestic consumers consuming upto 200
    units/month, irrigation and commercial consuming more than 100
    units/month. | 
  
    | 8.4.2.2 | The relevant rates applicable to these classes of consumers
    have been discussed at appropriate paragraphs and details given in the Annex-D. | 
  
    | 8.4.2.3 | Domestic :Total number of consumers of NESCO
    as on 31.3.2000 is 2,92,345 out of which 2,48,271 or 84.9% constitute the domestic
    category including the Kutir Jyoti. The estimated sale of energy to this category during
    the FY 2000-01 is given below :-
 
      
        |  | MU |  
        | Kutir Jyoti Consumers | 7.36 |  
        | Other Domestic consumers |  |  
        | (0 < 100 unit) | 256.13 |  
        | (>100 <200) | 118.61 |  
        | (>200 ) | 26.10 |  
        | Total  | 408.19 |  | 
  
    | 8.4.2.3.1 | Domestic consumers consume 27.51% of the total units sold by
    NESCO. | 
  
    | 8.4.2.3.2 | Domestic consumers are given power supply at Low/Medium
    voltage. The cost of supply to this category for the FY 2000-01 is 4.51 paise/unit. | 
  
    | 8.4.2.3.3 | The proposal submitted by the licensee with regard to the
    tariff rise for domestic category of consumers were examined. Some of the objectors
    complained that in the grab of Kutir Jyoti some consumers have got connected load much in
    excess of the single point supply for lighting envisaged under Kutir Jyoti programme. They
    also complained that extension of electricity being a State policy the State should
    subsidise such type of consumers. The Commission directs that wherever Kutir Jyoti
    consumers have got loads in excess of a single point supply, all such consumers should be
    metered and charged at normal domestic tariff. | 
  
    | 8.4.2.3.4 | The Commission is conscious of affordability consideration for
    non-Kutir Jyoti consumers with connected load of 1 KW and below who constitute nearly 70%
    of the total domestic strength. Dwelling units with five light points and two fan points
    with normal use may not exceed about 100 units per month on an average. Keeping this in
    view the Energy Charge for supply for domestic consumers availing low tension supply shall
    be as under :- | 
  
    | 8.4.2.3.5 | In case of other Domestic consumers, on the total monthly
    consumption :-
 
      
        | First 100 Units | -  | 140 paise per unit |  
        | Next 100 units | -  | 230 paise per unit |  
        | Balance units of consumption | -  | 320 paise per unit |  | 
  
    | 8.4.2.3.6 | The Kutir Jyoti consumers will also pay the monthly minimum
    fixed charge @ Rs.30/- per month. | 
  
    | 8.4.2.3.7 | In case of unmetered supply or defective meter, the energy
    consumption shall be assessed and billed using a load factor of 20% on the contract
    demand. For the purpose of calculation, connected load of less than 0.5 KW shall be
    treated as 0.5 KW. | 
  
    | 8.4.2.4 | Commercial : The Commission reviewed the
    existing tariff structure and decided upward revision of the rates as follows :-
 
      
        | First 100 units | - | 320 paise/unit |  
        | Next 200 units | - | 410 paise/unit |  
        | Balance units | - | 450 paise/unit |  | 
  
    | 8.4.2.4.1 | Load factor billing in case of unmetered supply or defective
    meter in commercial category shall be assessed and billed using the load factor of 30% on
    the contract demand which is same as connected load. For the purpose of calculation,
    connected load of less than 0.5 KW shall be treated as 0.5 KW. | 
  
    | 8.4.2.5 | Small Industry : In the existing tariff,
    consumers covered under small industry are charged @ 280 paise/unit. The revised rate for
    this category of consumers will be 320 paise/unit. In respect of these consumers with
    defective meter and unmetered supply load factor shall continue to be calculated @ 15% on
    the connected load for the purpose of assessment of consumption and billing. | 
  
    | 8.4.2.6 | Irrigation : The proposal of licensee for
    substantially raising the tariff of irrigation category of consumers was examined. The
    Commission decides that the Energy Charge for this category will be 110 paise/unit in
    place of 90 paise/unit. Consumers in the irrigation category availing power supply at HT
    will pay 100 paise/unit in place of the existing rate of 80 paise/unit. In respect of
    irrigation consumers for the months of June to October, a load factor of 8% and for the
    month of November to May, a load factor 15% shall be considered for assessment of
    consumption and billing. | 
  
    | 8.4.2.7  | The rate of tariff as determined above is reflected in Annex-D. | 
  
    | 8.5  | Tariff for consumers availing power supply at LT WITH
    CONTRACT DEMAND 110 KVA and above | 
  
    | 8.5.1  | Customer Service Charge | 
  
    | 8.5.1.1  | The Commission examined the present level of Customer Service
    Charge being levied for the consumers with connected load with 110 KVA and above and
    decided to continue with the existing level of Customer Service Charge. Table
    : 11 
      
        | Category | Voltage of Supply | Customer Service Charge (Rs./month) |  
        | Public Water Works | LT | 30 |  
        | General Purpose | LT | 30 |  
        | Large Industry  | LT | 30 |   | 
  
    | 8.5.2 | Demand and Energy Charges | 
  
    | 8.5.2.1 | The Commission, in keeping with its objective of
    rationalisation of tariff structure by progressive introduction of a cost-based tariff,
    has related the Energy Charge at different voltage levels to reflect the cost of supply.
    While determining Energy Charge, the principle of a higher rate for supply at a low
    voltage and a gradually reduced rate as the voltage level goes up has been adopted. The
    following Energy Charge has been adopted for all loads of 100 KVA and above.
 
      
        | Voltage of supply  | Energy Charge |  
        | LT | 320paise/unit |  | 
  
    | 8.5.2.2 | The Commission examined the existing level of Demand Charge of
    Rs.200/KVA/month payable by the consumers with a contract demand of 110 KVA and above. The
    Commission studied the Demand Charges for similarly placed consumers of other utilities.
    After examination of the details the Commission has decided not to change the present rate
    of Demand Charge of Rs.200/KVA/month payable by the consumers with contract demand of 110
    KVA and above which shall be payable in addition to the Energy Charge. 
 
      
        | Voltage of supply  | Demand Charge |  
        | LT | Rs.200/ KVA/month |  | 
  
    | 8.6  | Tariff for HT & EHT consumers  | 
  
    | 8.6.1 | Customer Service Charge for consumers with connected
    load of 110 KVA and above | 
  
    | 8.6.1.1  | The licensee has obligation for a consumer once connected to
    the power system of the licensee and incurs an expenditure for meeting the cost of meter
    reading, preparation of bills, delivery of bills, collection of revenue and maintenance of
    customer accounts. The licensee is bound to meet these expenses irrespective of the level
    of consumption of the consumer. Table : 12 
      
        | Category | Voltage of Supply | Customer service charge (Rs./month) |  
        | Bulk Supply (Domestic) | HT | 250 |  
        | Irrigation | HT | 250 |  
        | Public Institution | HT | 250 |  
        | Commercial | HT | 250 |  
        | Medium Industry | HT | 250 |  
        | General Purpose | HT | 250 |  
        | Public Water Works | HT | 250 |  
        | Large Industry | HT | 250 |  
        | Power Intensive  | HT | 250 |  
        | Mini Steel Plant | HT | 250 |  
        | Railway Traction | HT | 250 |  
        | General Purpose | EHT | 700 |  
        | Large Industry | EHT | 700 |  
        | Railway Traction | EHT | 700 |  
        | Heavy Industry | EHT | 700 |  
        | Power Intensive Industry | EHT | 700 |  
        | Mini Steel Plant | EHT | 700 |  
        | Emergency Supply to CPPs | EHT | 700 |   | 
  
    | 8.6.2 | Demand Charge for consumer with contract demand of 110
    KVA and above | 
  
    | 8.6.2.1 | The Commission examined the existing level of Demand Charge of
    Rs.200/KVA/month payable by the consumers with a contract demand of 110 KVA and above. The
    Commission studied the Demand Charges for similarly placed consumers of other utilities.
    The Commission also took into consideration the Demand Charge being paid by the
    distribution licensee to the bulk supply licensee. After examination of the details the
    Commission has decided not to change the present rate of Demand Charge of Rs.200/KVA/month
    payable by the consumers with contract of 110 KVA and above. The class of consumers and
    the voltage of supply to whom this charge shall be applicable are listed below. HT
    Category General PurposePublic Water Works
 Large Industry
 Power Intensive Industry
 Mini Steel Plant
 Railway Traction
 EHT Category General PurposeLarge Industry
 Railway Traction
 Heavy Industry
 Power Intensive Industry
 Mini Steel Plant
 No Demand Charge has been prescribed for emergency supply to CPPs. | 
  
    | 8.6.2.2 | Consumers with contract demand 110 KVA and above are billed on
    two part tariff on the basis of reading of the demand meter and the energy meter. They are
    also allowed to maintain loads in excess of their contract demand. The Demand Charge
    reflects the recovery of fixed cost payable by the consumer for the reservation of the
    capacity made by the licensee for the consumers. To insulate the licensee from the risk of
    financial uncertainty due to non-utilisation of the contracted capacity by the consumer it
    is necessary that the consumer pays at least a certain amount of fixed cost to the
    licensee. To arrive at that cost the Commission studied the pattern of demand recorded by
    the demand meters of all such consumers of the licensee for a period of one year from
    April, 1999 to March, 2000. The Commission after examination of all such facts have
    decided that the existing method of billing the consumer for the Demand Charge on the
    basis of the maximum demand recorded or 80% of the contract demand whichever is higher
    should continue. The method of billing of Demand Charge in case of consumers without a
    meter or with a defective meter shall be in accordance with the procedure prescribed in
    OERC (Conditions of Supply) Code, 1998. | 
  
    | 8.6.2.3 | As per the OERC (Condition of Supply) Code, 1998 for contract
    demand above 70 KVA but below 555 KVA supply shall be at 3-phase, 3-wire, 11 kV provided
    that the consumers connected prior to 01.10.95 may be allowed to continue to receive power
    at LT. But there are some consumers in the category of domestic, irrigation, public
    institution, commercial and medium industry have availed power supply at HT. For such
    types of consumers the Commission has decided to allow the existing Demand Charge as
    indicated below :-
 
      
        |  | (Rs./KW, Rs./KVA) |  
        | Domestic  | 10 |  
        | Irrigation  | 30 |  
        | Public Institution | 50 |  
        | Commercial | 50 |  
        | Medium Industry | 50 |  | 
  
    | 8.6.2.4 | Bills should be raised for these categories of consumers on
    the basis of their contract demand/connected load calculated in KW. | 
  
    | 8.6.3 | Energy Charge for consumer with contract demand of 110
    KVA and above | 
  
    | 8.6.3.1 | The Commission, in keeping with its aim of rationalisation of
    tariff structure by progressive introduction of a cost-based tariff, has related the
    Energy Charge at different voltage levels to reflect the cost of supply. While determining
    Energy Charge, the principle of a higher rate for supply at a low voltage and a gradually
    reduced rate as the voltage level goes up has been adopted. The following tariff structure
    has been adopted for all loads of 110 KVA and above.
 
      
        | Voltage of supply  | Energy Charge |  
        | HT | 300 paise/unit |  
        | EHT | 290 paise/unit |  | 
  
    | 8.6.3.2 | However, the Commission has made certain exception to the
    above provision in respect of domestic and irrigation consumers availing power at HT. | 
  
    | 8.6.4 | HT Supply for Domestic (Bulk) and Irrigation : With
    a view to avoid steep rise in tariff in respect of domestic (bulk supply) and irrigation
    category availing power at HT, the Energy Charge is fixed at @ 230 paise/unit and @ 100
    paise/unit respectively. The details are given in Annex-D. | 
  
    | 8.6.5 | Industrial Colony Consumption : The
    Commission further directs that the units consumed for the colony shall be separately
    metered and the total consumption shall be deducted from the main meter reading and billed
    @ 230 paise/unit for supply at HT and EHT for the energy consumed in colony in excess of
    10% of the total consumption shall be billed at the rate of Energy Charge applicable to
    the appropriate class of industry. | 
  
    | 8.6.6 | Emergency supply to CPP The Energy Charge
    which is being billed @ 350 p/u will be raised by 30 p/u like other consumers getting EHT
    supply. As such emergency power supply to CPP will be billed @ 380 p/u. | 
  
    | 8.6.7  | Incentive Tariff for HT and EHT Category of Consumers | 
  
    | 8.6.7.1 | The Licensee in para 9.3 of their application
    has proposed a special tariff for industries with load of 25 MVA and above having high
    load factor. The offer as under is in the form of reduction of Energy Charges for the
    entire consumption in the relevant month to any industrial consumer having contract demand
    of 25 MVA or above only if it achieve load factor of at least 70% in the relevant months. 
 
      
        | For Load Factor of 70% or above but less than 80% | Rs.2.25 per unit |  
        | For Load Factor of 80% or above but less than 90% | Rs.2.20 per unit |  
        | For Load Factor of 90% or above | Rs.2.15 per unit |   | 
  
    | 8.6.7.2 | The above rate would be only towards the Energy Charge. Demand
    Charge as applicable would be chargeable in addition to above. In case in any month any
    industrial consumer having above stated Contract Demand fails to achieve the required Load
    Factor then the usual Retail Supply Tariff applicable to the said class of consumer would
    be chargeable. The above Special rates are based on the present Bulk Supply Tariff rates
    and upon any revision of the same the above special Rates would be revised by the
    Commission by way of notification in pursuance of decision in this paragraph and could not
    be kept pending till next tariff revision. | 
  
    | 8.6.7.3 | The Commission in its last tariff order dtd. 30.12.99 in para
    8.5.4.1 had discussed the issue of an incentive tariff for HT and EHT consumers. The
    Commission being conscious of the revenue requirement of the licensee designed a tariff
    with the objective of incentivising the consumers for a higher consumption of the
    licensees purchased power and dissuade them from switching over to captive
    generation. The existing incentive tariff was examined with reference to the suggestion of
    the licensee and vehement objections were also made by some objectors to the proposal of
    the licensee as explained in earlier part of this order. | 
  
    | 8.6.7.4 | The Commission analysed the consumption in respect of all
    consumers having contract demand 110 KVA and above for the period April, 99 to November,
    2000. | 
  
    | 8.6.7.5  | The Commission observes that the consumption during the months
    of April to November, 2000 is much higher compared to the consumption recorded during the
    corresponding period of the previous financial year after incentive was given in form of
    lower Energy Charge for consumption in excess of 50% load factor. | 
  
    | 8.6.7.6  | The Commission analysed the load factor from month to month
    from the months of April, 99 to November, 2000 of all the consumers with CD 110 KVA and
    above. | 
  
    | 8.6.7.7 | The Commission also takes into consideration the comparative
    rates of NTPC tariff and the wheeling charge and transmission loss payable by NESCO
    consumers utilising such power. | 
  
    | 8.6.7.8  | The Commission took cognizance of the marginal cost of power
    procurement from NTPC stations due to additional drawal by the consumers on account of
    grant of incentive in the form of reduction of Energy Charges for maintaining high load
    factor. | 
  
    | 8.6.7.9  | The Commission also takes a broader view of the power
    situation in the country and has to take into account the possible impact after
    introduction of ABT which will require payment of fixed charges by GRIDCO to the central
    generating stations requiring optimum utilisation of energy received from these
    facilities. | 
  
    | 8.6.7.10  | The tariff structure for various categories of Power Intensive
    Industries prevailing elsewhere in the country and impact of switching over of these
    industries to CPPs in yielding lesser revenue for cross-subsidising have been examined. | 
  
    | 8.6.7.11  | After taking all these factors into consideration the
    Commission has come to the conclusion that since the Demand Charge is same for all HT and
    EHT categories of consumers a higher consumption means a higher plant utilisation and
    results in a reduced fixed cost per unit. The Commission like the previous year decides to
    apply the incentive tariff for any consumer availing power supply at HT or EHT who becomes
    eligible for the same. The Commission does not agree to the proposal of the licensee to
    limit incentive tariff to 25 MVA and above. | 
  
    | 8.6.7.12  | It is decided to provide incentive in shape of reduced Energy
    Charge to those who maintain a high level of consumption. The normal Energy Charges for
    EHT and HT consumers shall be @ 290 and @ 300 paise/unit respectively as stated in para
    8.6.3.1. | 
  
    | 8.6.8  | Method of Determination of Incentive | 
  
    | 8.6.8.1  | Incentive shall be available to those
    consumers who will not reduce their contract demand during the next three financial years. | 
  
    | 8.6.8.2  | Some objectors objected to recording of load factor during the
    FY 1999-00 in excess of 100% in the filing made by the licensee on the ground that it had
    an element of absurdity. As prescribed in OERC Condition of Supply Regulation, 1998 load
    factor of a consumer under no circumstances can exceed 100%. It is necessary that the
    method of determination of incentive should be clearly understood. | 
  
    | 8.6.8.3 | For the purpose of determination of eligibility for incentive
    tariff percentage of consumption shall be with reference to contract demand or the maximum
    demand whichever is higher (e.g. CD or MD X PF X number of hours in a month). | 
  
    | 8.6.8.4  | The ratio of the total number of units consumed during a given
    period to the total number of units that would have been consumed had the contract demand
    or the maximum demand whichever is higher was maintained through out the same period as
    indicated above, exceeds 50%, of the total consumption the consumer will be entitled to
    get the benefit of incentive. | 
  
    | 8.6.8.5 | Different rates of Energy Charges in excess of the ratio
    mentioned above is shown below and explained in the paragraphs hereafter.
 
      
        |   | HT | EHT |  
        | Consumption upto 50% | 300 p/u | 290 p/u |  
        | >50% = < 60 % | 200 p/u | 180 p/u |  
        | >60% | 170 p/u | 150 p/u |  | 
  
    | 8.6.8.6  | Demand Charges as applicable would be chargeable in addition
    to the above. | 
  
    | 8.6.9  | EHT Consumer | 
  
    | 8.6.9.1  | Consumption in a month calculated on the
    basis of the contract demand or maximum demand whichever is higher upto 50% shall be
    payable @ 290 paise/unit for consumers availing power at EHT. | 
  
    | 8.6.9.2 | In addition to the above all consumption in excess of 50% but
    upto and including 60% shall be payable @ 180 paise/unit for consumers availing power at
    EHT. | 
  
    | 8.6.9.3  | When the consumption exceeds 60% in a month all such excess
    consumption shall be payable @ 150 paise/unit for consumers availing power at EHT in
    addition to the charges indicated at para 8.6.8.2. | 
  
    | 8.6.10  | HT Consumer | 
  
    | 8.6.10.1  | Consumption upto 50% shall be payable @ 300
    paise/unit for consumers availing power at HT. | 
  
    | 8.6.10.2  | In addition to the above all consumption in excess of 50% but
    upto and including 60% shall be payable @ 200 paise/unit for consumers availing power at
    HT. | 
  
    | 8.6.10.3  | When the consumption exceeds 60% in a month all such excess
    consumption shall be payable @ 170 paise/unit for consumers availing power at HT in
    addition to the charges indicated at para 8.6.9.2. | 
  
    | 8.7  | Special Tariff for Industries with Contract Demand of
    100 MVA and above | 
  
    |   8.7.1 | A special tariff for industries with a load
    of 100 MVA and above was prescribed by OERC to encourage prospective large consumers to
    avail power from the licensee and to ensure that such large industries do not set up
    captive power plants. The licensee in para 9.2 of the application has proposed no change
    in the special tariff specified under RST order dtd.30.12.99. The licensee has also stated
    that this tariff has no impact on the revenue compilation for the year 2000-01 as no
    consumption is envisaged under this category. | 
  
    | 8.7.2 | The Commission in the last tariff order had approved a rate of
    200 paise/unit for consumption by industries with a contract demand of 100 MVA and above
    and maintaining a guaranteed monthly load factor of 80%. These consumers will not pay a
    monthly Demand Charge and shall pay only a consolidated Energy Charge. They will have to
    restrict their maximum demand within the contracted capacity. In case the maximum demand
    exceeds the contracted capacity, Demand Charge as applicable to the relevant consumer
    category will be payable only on the maximum demand in excess of the contract demand. The
    Commission approves the continuance of this tariff. | 
  
    | 8.7.3  | The rate of tariff as determined above is reflected in Annex-D. | 
  
    | 8.8  | Other Charges The Commission also
    authorises levy of other charges as given below :- | 
  
    | 8.8.1 | Penalty for overdrawal of power
    above the contract demand : As per the existing tariff provisions there is no
    penalty for overdrawal out side the peak hours upto 120% of the contract demand. This
    issue was raked up during the course of the public hearing. Some of the objectors pointed
    out that this provision is being circumvented by consumers who are reducing their contract
    demand to avail this benefit of overdrawal upto 120% during off peak hours. In the absence
    of frequency related metering the pious objective of the Commission in helping the
    flattening of load curve and containing the frequency is not being achieved. The
    Commission is of the opinion that a beginning has been made and this has to be enforced
    such that the system gets the benefit due to flattening of the load curve as well as
    control of frequency which is necessary in a surplus generation situation. Frequency
    related metering is not essential for measurement of overdrawal and this facility is
    available only to those industries who are provided with time of day (TOD) metering. The
    railway traction consumers have consistently demanded for extension of this benefit during
    off peak hours as well as other hours to them. The Commission after taking all these
    factors into consideration has decided that this facility which is now available for HT
    and EHT industries should extend to all consumers availing power supply at HT and EHT. The
    existing rate of penalty however will continue for overdrawal during peak hours. When the
    maximum demand exceeds the contract demand during peak hours, such excess demand is liable
    for a penalty and payable at the prescribed rate of Demand Charge. For this purpose
    the peak hours is defined as 700 hrs to 1000 hrs and 1800 hrs to 2200 hrs. | 
  
    | 8.8.2  | Metering on LT side of Consumers Transformer : Transformer
    loss computed as given below to be added to the consumption as per meter reading. Energy loss = 730 X KVA rating of the transformer/100. Loss in demand = 1% of the rating of the transformer (for two part
    tariff) | 
  
    | 8.8.3 | Incentive for prompt payment : The licensee
    in his application has estimated that the rebate on account of incentive for prompt
    payment will be of the order of Rs.0.97 crores during the financial year 2000-01. It has
    also suggested continuance of the existing rate of incentive for timely payment. The
    Commission examined the existing method of incentive and its financial implication. The
    Commission has decided to grant incentive for early and prompt payment as below. 
      
        A rebate of 10 paise/unit shall be allowed on Energy Charges if the payment of the bill
        (excluding arrears and electricity duty) is made by the due date indicated on the bill or
        within a period of 7 (seven) days from the date of receiving the bill in respect of the
        following categories of consumers.LT : Domestic, Commercial, Irrigation and Small Industry
 HT : Bulk supply domestic, commercial and irrigation
        Consumers other than those mentioned at para a above shall be entitled to a
        rebate of 1% (one percent) of the amount of the monthly bill (excluding arrears and
        electricity duty), if payment is made within 48 hours of the presentation of the bill. | 
  
    | 8.8.4 | Delayed Payment Surcharge : The Commission
    has examined the present method and rate of DPS and has decided that if payment is not
    made within the due date, Delayed Payment Surcharge shall be charged for every day of
    delay at 2% per month on the amount remaining unpaid (excluding arrears on account of DPS)
    in respect of following categories of consumers. 
      
        Large industries
        Medium industries
        Public Water Works
        Railway Traction
        Street Lighting
        Power intensive industries
        Heavy industries
        General Purpose Supply
        Public Institutions
        Mini Steel Plants
        Emergency supply to CPP | 
  
    | 8.8.5  | Incentive for improvement in power factor : The
    Commission examined the desirability of continuing with the present method of incentives
    allowable to the consumers for improvement in power factors. NESCO estimates that the
    rebate alone on this account to HT/EHT consumers will be the order of 9.25 crores during
    the financial year 2000-2001. NESCO further states that they have been installing
    capacitor banks for improvement of power factor in the system and benefits of power factor
    improvement by the HT/EHT consumers has gone to GRIDCO and not to NESCO. | 
  
    | 8.8.6  | The Commission reviewed the present method of incentive plan
    and after examining the financial liabilities directs that incentive for maintenance of
    high power factor shall be given as a percentage of the monthly Demand Charge and Energy
    Charge and shall be applicable to the HT/EHT categories of consumers who are liable to pay
    power factor penalty. The rate of this incentive will be 0.5% for every 1% rise above 97%
    upto and including 100% on the monthly Demand Charge and Energy Charge. | 
  
    | 8.8.7 | Power Factor Penalty : The Commission also
    orders for continuance of the power factor penalty as a percentage of monthly Demand
    Charge and Energy Charge as given below to the following categories of consumers : i) Large Industriesii) Public Water Works (110 KVA and above)
 iii) Railway Traction
 iv) Power Intensive Industries
 v) Heavy Industries
 vi) General Purpose Supply
 vii) Public Institutions (110 KVA and above)
 viii) Mini Steel Plants
 ix) Emergency supply to CPP
 Rate of Power Factor Penalty :- i) 0.5 for every 1% fall from 90% upto and including 60% plusii) 1% for every 1% fall below 60% upto and including 30% plus
 iii) 2% for every 1% fall below 30%
 | 
  
    | 8.8.8  | Adoption of load factor for consumers with defective meter and
    without meter : The Commission in its last tariff order dtd.30.12.99 had directed
    continuance of the existing method of load factor billing subject to review from time to
    time. The progress with regard to the repair/replacement/ installation of new meters by
    the licensee in the premises of the consumers is being reviewed by the Commission at the
    end of every quarter (OERC Form P-13). The details of the metering as reported by NESCO is
    given in para 5.29.11 of this order. The licensee has stated that arrangements have been
    made to procure 2 lakh single-phase meter and proposes to install 50,000 meters during FY
    2000-01 as reported in OERC Form No.P-14. The licensee estimates loss reduction of 3.25%
    on account of detection of unauthorised abstraction of electricity and replacement of
    meters. The licensee has requested for continuance of the present load factor percentage
    to serve as a dis-incentive for the consumers and help adoption of metering by consumers. | 
  
    | 8.8.8.1 | The Commission examined the facts and figures submitted by the
    licensee and had the view expressed by the objectors, some of whom wanted reduction in the
    present level of load factor being applied for defective and unmetered consumers. It was
    also brought out by some of the objection that there has been an actual enhancement in the
    number of unmetered consumers and reduction and marginal reduction of consumers with
    defective meters. The Commissions serious area of concern is metering. The licensee
    should take all out efforts for maximisation of installation of meters, repair and
    replacement of meters, and the method of load factor billing cannot continue in
    perpetuity. The licensee must submit a plan of action within a period of 3 months about
    100% metering of all consumers to be completed within a definite time frame. The
    Commission will continue to review the status of metering and measures taken for
    eradication of unauthorised tapping from the distribution mains. The licensee shall submit
    the information at the end of each quarter for information and review of the Commission.
    The Commission however, orders for continuance of the existing method of load factor
    billing mainly because of the ground situation that control over large scale of pilferage
    of electricity shall take some more time. | 
  
    | 8.8.9  | Customer Charge : As indicated in paragraph
    8.6.1 above and also Annex-D there shall be no change in the existing rate of customer
    charge. | 
  
    | 8.8.10  | Re-connection Charge : The existing rates of
    reconnection charge as below shall continue :-
 
      
        | Single Phase Domestic Consumer | Rs.30/- |  
        | Single Phase other consumer | Rs.50/- |  
        | 3 Phase line | Rs.100/- |  
        | HT & EHT line | Rs.500/- |  | 
  
    | 8.8.11  | Rounding off a consumer billed amount to nearest rupee
    : The Commission directs for rounding off of the electricity bills to the nearest
    rupees and at the same time directs that the money actually collected should be receipted
    and accounted for. | 
  
    | 8.8.12  | Temporary Connection Charges : The tariff for
    the period of temporary connection shall be at the rate applicable to the relevant
    consumer category. | 
  
    | 8.8.13  | New Connection Charges for LT : The
    Commission in its last tariff order had directed that prospective small consumers
    requiring new connections upto and including 3 kW load should pay a flat charge of
    Rs.500/-. This was intended to do away with the then practice of preparation of estimate
    and payment of charge based on the estimated amount shall continue without any change for
    connections above 3 kW load. It was also directed for preparation of estimate for
    connection above 3 kW connected load. Complaints were raised during the course of the
    hearing about non-observance of this direction of the Commission. The licensee should
    submit a statement of new connections given during the first six months of the current
    financial year and intimate the rate that has been charged in each of the consumer cases. | 
  
    | 8.8.14 | Fuel Surcharge Adjustment Formula : The
    Commission has already prescribed a fuel surcharge adjustment formula for the distribution
    licensee which shall continue to be valid. | 
  
    | 8.8.15 | Meter Rent : Monthly meter rent as per the
    existing rate shall be charged from the consumers to whom meter has been supplied by the
    licensee. The scale of meter rent including associated equipment applicable to various
    classes of consumers is given below :-
 
      
        | Meter | Rent in Rupees |  
        | 1. Single phase electro-magnetic Kwh meter | 15/- |  
        | 2. Three phase electro-magnetic Kwh meter | 30/- |  
        | 3. Three phase electro-magnetic trivector meter | 800/- |  
        | 4. Trivector meter for Railway Traction | 800/- |  
        | 5. Single phase Static Kwh meter | 35/- |  
        | 6. Three Phase Static Kwh meter | 100/- |  
        | 7. Three phase Static Trivector meter | 800/- |  
        | 8. Three phase Static Bivector meter | 800/- |  | 
  
    | 9.0 | In the light of our findings, the Commission decides
    as follows :- 
      
        The Commission does not approve the licensees calculation of revenue and proposal
        for tariff.
        The Commission directs that tariff as determined in this order be implemented by the
        licensee effective from 1st February, 2001 until further order in this regard.
        The tariff schedule for various classes of consumers at Annex-D is approved.
        The Commission does not approve of the expected revenue from charge at the existing
        tariff from 2000-01 as proposed by the licensee and has approved a modified figure after
        due examination of the facts, figures and submissions made by the licensee.
        The Commission accepts the request of NESCO that it will be permitted to carry forward
        the gap between the expected revenue and the revenue requirement for 2000-01 as well as
        for 1999-00 within the benchmark approved by the Commission for adjustment during the
        future years after vetting of the figures by the Commission.
        The Commission does not accede to the prayer of the licensee for accepting the loss for
        the year 1999-2000 as it occurred due to inability to remain within performance parameters
        set by the Commission.           The application
    of M/s. NESCO is disposed of accordingly. | 
  
    |  | H. S. Sahu Member
 | D. K. Roy Chairman
 | 
  
    |  | Previous | Contents page |