| 6.5 | Reasonable Return With
    regard to reasonable return it is clarified that the same has to be calculated on the
    basis of the capital base arrived at in accordance with the provision of Sixth Schedule to
    the Supply Act, 1948. | 
  
    | 6.6 | Treatment of Working Capital | 
  
    | 6.6.1 | The Commission believes that the
    companies must commit themselves to a higher level of efficiency, bring loan to meet the
    working capital needs so that the transmission utility and the generators are not starved
    of funds. There is a gap between the revenue billed and the revenue realised due to
    inefficiency on the part of the licensees for failing to take appropriate and expeditious
    steps like disconnection in time or initiation of civil suits to realise the arrear dues.
    Domestic, irrigation and agricultural consumers are not required to pay any DPS for delay
    in payment, whereas small and medium industries and other categories only pay one time
    DPS. This is a disincentive for revenue collection especially when the licensees are not
    capable of realising the dues after the due date of payment is over. The Commission also
    may at appropriate time consider for levy of DPS for those consumers who are at present
    not covered under DPS for delay in payment. | 
  
    | 6.6.2 | The distribution companies have
    failed to bring required working capital to ensure cash balance in the system to meet all
    expenses. The licensee can get rebate on prompt payment from GRIDCO @2% per month, which
    will reduce its power purchase liability. In a sense if the licensee arranges working
    capital from the commercial and financial institutions they can save not only the DPS but
    will earn a rebate from the GRIDCO that will compensate the interest on working capital
    and may accrue some revenue in the form of rebate. The Commission also may at appropriate
    time consider for levy of DPS for those consumers who fail to pay the bills during the
    stipulated period. | 
  
    | 6.7 | T&D loss | 
  
    | 6.7.1 | The next issue is determination of
    the total cost of distribution and retail supply. The supply business requires purchase of
    power by the DISTCOs from the transmission company (GRIDCO) for supply to consumers. The
    energy received at grid sub-stations at 33 kV by the DISTCOs and supplied to the end-use
    consumers at different voltage levels entails both technical and commercial losses. The
    Commission hitherto have been following the concept of determination of power procurement
    after applying a normative loss level to the total power proposed to be sold by the
    licensee, irrespective of the quantum of actual power purchase by DISTCOs from GRIDCO.
    This quantum of power purchase is metered in each grid sub-station and is reflected in the
    various data recorded in the energy billing centre (EBC) of GRIDCO and also in the BST
    bill of GRIDCO raised on DISTCOs. | 
  
    | 6.7.2 | The World Bank Staff Appraisal
    Report of April 1996 projected different levels of transmission and distribution loss for
    the year 1996-97 to the FY 2002-03 based on the studies made by a group of reputed
    consultants. The Commission while approving the tariff application in the year 1997-98
    took cognizance of these projected loss figures. While adopting a loss level of 35% for
    the year 1997-98, the Commission went by the estimate of 34.8% made in the SAR as against
    the claim of 47% made by GRIDCO for that year. The projections made in the
      SAR, the level
    of T&D loss as established by the audit report of GRIDCO gives a wide disparity in the
    projections and actual performance as can be revealed from the table below.  Table : 6As per SAR of 1996
 
      
        |   | FY 97 | FY 98 | FY 99 | FY 00 | FY 01 | FY 02 | FY 03 |  
        | Energy available for sale (MU) | 9785 | 10902 | 12726 | 13902 | 14809 | 15560 | 16342 |  
        | T&D losses (%) | 39.5 | 34.8 | 29.2 | 24.3 | 22.7 | 21.7 | 20.6 |  
        | Electricity sale (MU) | 5924 | 7103 | 9004 | 10528 | 11442 | 12187 | 12976 |  Table : 7Actual performance
 
      
        |   | FY 97 | FY 98 | FY 99 | FY 00 |  
        | Energy available (MU) | 9651Audited
 | 10324Audited
 | 10571BST order 2000-01
 | 10131BST order 2000-01
 |  
        | T&D losses (%) | 49.47 | 49.24 | 48.60 | 45.36 |  
        | Electricity sale (MU) | 4876 | 5240 | 5433RST filing 00-01
 | 5536Tax audit RST filing of CESCO 00-01
 |  | 
  
    | 6.7.3 | The members the Commission Advisory
    Committee specifically discussed the issues of high percentage of T&D loss,
    Distribution loss, poor performance of Distcos, subsidy, cross-subsidy. Majority of the
    members suggested that the recomendation of the Kanungo committee should be kept in view
    while finalising the tariff and revenue requirement of DISTCOs as neither the Government
    of Orissa filed any objection nor depute any representative to appear in the hearing.
    Members also advocated in favour of uniform retail tariff for the whole State. Some of the
    Members raised issues specific to the interest groups they represent. But there was near
    unanimity with regard to the certain issues. It was felt that T&D loss was still high
    and while fixing the target level of loss, the Commission should not go back to the level
    already set. Rather the target level of loss be set at still lower. It was also felt that
    installation of meters and consumer services were far from satisfactory. Most of the
    members opined that there should be thorough scrutiny on the input cost of the licensees,
    while Some suggested that depreciation should not be charged on the assets those have
    already outlived. The Chief Electrical Engineer, S.E. Railways raised certain vital issues
    to be tackled while passing this tariff order to give benefit to the Railways. | 
  
    | 6.7.4 | The objectors in general were of
    the opinion that the adoption of a uniform loss figure for the four distribution companies
    with a different load mix was hiding the inefficiency of the companies with higher
    components of HT and EHT load. EHT component of load makes a big difference to the overall
    loss figure for the company as loss in EHT category is practically negligible. The overage
    loss as a percentage of the total power procurement from the GRIDCO by DISTCOs as well as
    the direct sale figures at EHT as projected by the four DISTCOs are given in the table for
    the FY 2001-02.(RR02-03 filing of DISTCOS). Table : 8 
      
        |   | NESCO | WESCO | SOUTHCO | CESCO | TOTAL |  
        | Input for the DISTCOs (MU) | 2208.4 | 2920.2 | 1541.3 | 4024.6 | 10694.45 |  
        | Sale at EHT (MU) | 243.72 | 583.5 | 122.27 | 266.02 | 1215.51 |  
        | Proposed Distribution Loss (%) | 47.4 | 45.1 | 41 | 45 | 45 |  | 
  
    | 6.7.5 | Some of the objectors have pointed
    out that the distribution loss is being computed after taking into account even the zero
    loss EHT energy input into the system to show a reduced level of loss. The total power
    sale to a DISTCO is arrived at the Energy Billing Centre of GRIDCO by integrating the EHT
    drawal at 132/220 kV and bulk power drawal at 33 kV in any grid sub-station. Therefore,
    sale at EHT can be taken out from the total power purchase figures to determine the energy
    input to various DISTCOs for supply to HT and LT consumers. If the EHT sale projected by
    the four DISTCOs are taken out from the total sale projected by these companies then the
    distribution loss as the percentage loss of HT and LT input works out to 53.3% for NESCO,
    56.3% for WESCO, 44.1% for SOUTHCO and 48.2% for CESCO with an overall loss figure of
    50.6% for the State as a whole under HT & LT category. | 
  
    | 6.7.6 | As we will be determining the
    energy input into the DISTCOs system based on the billing figures of GRIDCO for the FY
    2001-02, it will be appropriate to determine the loss as a percentage of HT and LT input
    after deducting the direct sale at EHT to show a comparative picture of performance of the
    four DISTCOs and also plan for bringing down the distribution loss at the HT & LT
    level, which will ultimately bring down the overall distribution loss in a DISTCO. | 
  
    | 6.7.7 | Identical comparison can be done for
    the FY 2002-03 by determining distribution loss as a percentage of HT and LT input. | 
  
    | 6.7.8 | The Commission in the tariff order
    dtd.19.01.2001 had observed that the task of fixing a level of loss in the absence of
    verifiable and reliable data has led it to apply a value judgement that should be fair,
    reasonable and financially sound. Any arbitrariness on the part of the Commission will
    either affect the financial viability of the licensee or sustain undue burden on the
    consumers. | 
  
    | 6.7.9 | The Commission had also observed in
    the last tariff order that the high T&D loss is not an isolated phenomena in Orissa.
    Higher level of loss figures are being gradually disclosed in all most all the reforming
    states in the country. The Commission was also of the view that the benchmark of T&D
    loss at 35% was as a measure of performance perceived to be unrealistic and unacceptable
    by GRIDCO and the DISTCOs. The World Bank on whose SAR Commission relied in fixing an
    overall loss level of 35% in FY 1997-98 subsequently came out in its midterm review report
    dtd.31.10.1998 that it underestimated the actual loss level. The World Bank states
    "Consultation with the Commission on the issue of recognizing the actual system loss
    levels and pass through of prior years financial losses, given that we all so
    severely underestimated GRIDCOs system losses in 1996 and set unachievable
    performance targets". | 
  
    | 6.7.10 | Therefore DISTCOs all along
    complained about to unrealistic loss level of 35% adopted by the Commission while adopting
    a loss level of 34% for the FY 2000-01 including the losses at EHT transmission system of
    3.7%, the Commission had directed the DISTCOs during the course of the hearing to carry
    out pilot studies within a period of six months from April, 2001 to September, 2001 and
    submit the same to the Commission for its appraisal while determining the target level of
    loss reduction from year to year. The Commission is constrained to place on record the
    utter failure of licensees to address this most important and crucial issue which was
    being raked up by them time and again. DISTCOs have not initiated any concerned and
    vigorous effort to fix meters in feeders, LV side of transformer and consumers served by
    the feeder to ascertain the actual level of loss. | 
  
    | 6.7.11 | Due to insistence by Commission the
    DISTCOs started determination of loss on a selected feeder. It was a much delayed exercise
    by all the licensees. Also Commissions effort to engage outside consultants to
    oversee the pilot loss study could not take off due to the financial problem of the
    licensees. Only WESCO initiated a study by engaging an outside agency. | 
  
    | 6.7.12 | However, the Commission with the
    assistance of the Department for International Development (DFID) has conducted pilot
    study in one 11 kV feeder for WESCO, NESCO and SOUTHCO and two feeders of CESCO by
    appointing its own consultants. The report of this pilot study demonstrates that there is
    ample scope and opportunity for quick reduction of loss by the DISTCOs. | 
  
    | 6.7.13 | The distribution companies while
    submitting the business plan for a period of 5 years to the Committee of independent
    expert in the month of October, 2001 have supplied the following distribution loss figures
    for the year 2001-02 to 2004-05:- Table-9Figure of distribution loss projected by DISTCOs before
 the Committee of Independent Experts
 
      
        | Name of the company | FY 01-02 | FY 02-03 | FY 03-04 | FY 04-05 |  
        | CESCO | 40.94% | 39.35% | 37.57% | 36.08% |  
        | NESCO | 46.98% | 40.77% | 36.85% | 34.12% |  
        | WESCO | 41.08% | 39% | 36.93% | 34.89% |  
        | SOUTHCO | 40.89% | 39.21% | 36.01% | 33.14% |  
        | ALL ORISSA | 42.21% | 39.56% | 37.00% | 34.87% |  | 
  
    | 6.7.14 | This, however, excludes the
    transmission loss of 4.65%, projected by GRIDCO from 2001-02 to 2005-06. | 
  
    | 6.7.15 | The committee, however, accepted a
    distribution level loss of 42.21% for the base year of FY 2001-02 after hearing the
    DISTCOs and suggested reduction of distribution loss by 5% each year from FY 2002-03 to
    reach a level of 22.21% in the year 2005-06. Similarly, the committee had also approved a
    reduction of transmission loss at a rate 0.3% each year from FY 2002-03 till the losses
    reach 3.7% by 2005-06. This is projected in the table below. Table
    : 10Loss figures approved by the Committee of Independent Experts
 
      
        |   | FY 01-02 | FY 02-03 | FY 03-04 | FY 04-05 | FY 05-06 |  
        | Distribution loss | 42.21% | 37.21% | 32.21% | 27.21% | 22.21% |  
        | Tranmission loss | 4.7% | 4.4% | 4.1% | 3.8% | 3.7% |  | 
  
    | 6.7.16 | As explained in para 6.7.6,
    computation of loss after deducting the zero loss EHT energy from year to year is given
    below.  Table : 11Computation of loss as a percentage of HT & LT input based on the Business Plan
    submitted by DISTCOs to the Committee of Independent Experts
 
      
        |   | FY 01-02 | FY 02-03 | FY 03-04 | FY 04-05 | FY 05-06 |  
        | Loss as a %age HT & LT input | 49.67% | 45.01% | 39.9% | 34.25% | 28.39% |  | 
  
    | 6.7.17 | The committee of independent
    experts appointed by the Government of Orissa to review the power sector reform in their
    report have suggested reduction of distribution loss at the rate of 5% per annum. The
    pilot study conducted by the Commission brings out very clearly that the scope of
    reduction of distribution loss is enormous provided the companies take effective steps
    such as technical, financial and managerial decisions for reduction of distribution loss.
    Any number of alibis expressing inability for not reducing the distribution loss are not
    acceptable to the Commission. Besides higher level of loss found out on the basis of pilot
    study is purely indicative as the number of feeders selected were very few compared to the
    existing number of feeders. Pilot study results cannot be taken as basis of loss levels
    existing in different DISTCOs, as study on one feeder out of hundreds of feeders in the
    company with varied load mix, concentration of loads, length and size of feeders cannot be
    a representative one. But this study brought to the fore very interesting facts like
    direct tapping of 11 kV feeder by industrial consumers, by-passing of meter CTs. It so
    happened in some areas where pilot study was being taken up, the consumers locked their
    houses and went away forbidding the utility staff and Commission consultant to check the
    status of the meter. Pole scheduling in the study area revealed unauthorized abstraction
    of energy by the illegal consumers, consuming energy far more in excess of what was shown
    in the consumer ledger of the DISTCOs. | 
  
    | 6.7.18 | In the 2001-02 tariff filing, WESCO
    had reported a loss level of 38% for that year. But while submitting the revenue
    requirement application FY 2002-03, WESCO have reported distribution loss for the year
    2001-02 as 45%. This kind of irresponsible reporting for a particular year has been made
    within an interval of 3 months. It implies that the DISTCOs have demonstrated a very
    casual attitude in projecting the figure to the Commission for the purpose of
    determination of tariff or revenue requirement. The case of other companies are also not
    different. | 
  
    | 6.7.19 | The Commission accepts the
    distribution loss figure as approved by the Kanungo Committee as 42.21% for the FY 2001-02
    which is treated as the base year. This figure of 42.21% represents the overall average
    distribution loss for the entire State but varies across the four distribution companies.
    The variation in loss figures across the DISTCOs are exhibited in Table-12. The Commission
    also adopts the recommendation of the committee for reduction of distribution loss at
    least at the rate of 5% per annum from 2001-02 to 2002-03. The Commission therefore
    directs that for the purpose of determination tariff and the revenue requirement the rate
    of loss reduction will be calculated at the rate of 5% (overall average for the state)
    starting from the FY 2001-02 and 2002-03. Accordingly, the following loss figures are
    approved for the aforesaid purpose for the year 2001-02 and 2002-03. While formulating the
    multi-year tariff proposed to be effective from 01.04.2003, this aspect of loss reduction
    along with collection efficiency etc will be decided for subsequent years. Table : 12 
      
        | PURCHASE & SALES BY
        DISTCOs BASED ON 10 MONTHS ACTUAL |  
        |  | FY 2001-02 | Expected/Projected
        for FY 2002-03 |  
        |  | Purchase (MU) | Loss(%) | Sale(MU) | Purchase (MU) | Loss(%) | Sale(MU) |  
        | CESCO | 4167.77 | 40.94% | 2461.485 | 4321.00 | 35.94 | 2768.03 |  
        | NESCO | 2253.62 | 46.98% | 1194.8693 | 2291.20 | 41.98 | 1329.36 |  
        | WESCO | 2980.64 | 41.08% | 1756.1931 | 3066.54 | 36.08 | 1960.13 |  
        | SOUTHCO | 1525.07 | 40.89% | 901.46888 | 1682.39 | 35.89 | 1078.58 |  
        | TOTAL | 10927.10 | 42.21% | 6314.02 | 11361.13 | 37.21 | 7136.10 |  | 
  
    | 6.7.20 | Commission wants to make it
    expressly clear that there is no shortcut way unless a systematic drive is made to reduce
    the distribution loss. This should necessarily include metering of 11 kV feeders, metering
    at LV side of transformers, pole scheduling, verification if deemed necessary of consumer
    connected loads, rectification or replacement of consumer meters so that each feeder is
    converted to a Profit Centre as has been very aptly stated by the Ministry of
    Power, GoI, which is allotting large sum of funds to meet cost of metering etc. to achieve
    the goal in a time bound manner, which will be available through State Govts. to utilities
    and SEBs under APDRP programme. | 
  
    | 6.7.21 | There are 846 Nos. of 33/11 kV
    feeders in the State under the four DISTCOs. There are about 900 field sections in the
    DISTCOs. This means that there may be 1 to 2 Nos. of 11 kV feeders under each section and
    1 No. of 33 kV feeder and 9 Nos. of 33/11 kV transformers and at least 30 Nos. of
    distribution transformers in each feeder. Once members and other supporting staff
    including MRT personnel are made available, it would be possible to complete within one
    year for monitoring of all feeders along with complete pole scheduling leading to
    identification and regularisation of unauthorised connection. Progressive achievements
    will bring substantial in reduction of loss in feeders. | 
  
    | 6.7.22 | Commission, among other things shall
    attach highest priority on these aspects and would expect the licensee to aggressively
    start taking up related activities. Commission would, on its part approach DFID to provide
    support to temporarily hire services of technical personnel by the Commission to oversee
    the progress made in this regard by the licensee on a day to day basis. | 
  
    | 6.7.23 | Although the Commission in
    deference to the spirit of OER Act, 1995 would have liked for a hands-off regulation while
    dealing with DISTCOs. But it finds to its dismay that utilities have taken advantage of
    this liberal gesture and have done precious little to address this single major factor of
    loss reduction which constitutes a menace to the viability of the power sector. Therefore,
    Commission would closely associate itself in monitoring the activities of DISTCOs in this
    regard. | 
  
    | 6.7.24 | As indicated in para 6.7.16 the loss
    as a percentage of HT & LT input for the year 2005-06 approved by the Kanungo
    Committee should be targeted at 28.39% to be attained by all the DISTCOs. |