CASE NO. 19 of 1998
Shri S.C. Mahalik, Chairman
Shri A. R. Mohanty, Member
Shri D. K. Roy, Member
In the matter of an application for revision of the
Distribution & Retail Supply Tariff by Gridco.
Dates of argument : 14.10.98 to 17.10.98
Date of Order : 21.11.98
ORDER
M/s. Grid Corporation of Orissa Limited (Gridco, for
short), the holder of the "The Distribution & Retail Supply
Licence, 1997 (No.1/97)" have applied for approval of its calculation of revenue
requirement and charges to be recovered for sale of electricity to consumers during
1998-99.
1.2
The said licensee, Gridco has recently implemented a restructuring programme, creating
four separate distribution zones to be managed by four subsidiary companies which have
already been incorporated. As on date, Gridco is the only licensee covering the entire
State of Orissa as its area of supply.
1.3 The proposal under sub-section (4) of Section 26 of the Reform Act, 1995 was submitted by Gridco on August 17, 1998 giving
details of calculation of estimated revenue requirement for 1998-99 and charges proposed
to be levied.
1.4 Upon Gridco meeting the
clarifications sought for by the Commission office and complying with the procedural
formalities, a notice was published by the Commission in several local newspapers on two
consecutive days outlining the tariff proposal and calling for objections from interested
persons. The objectors were required to submit their objections in quadruplicate to the
Commission with the fifth copy of the said objection to be served on Gridco. The notice
called on the interested parties to peruse further details of the proposal in the
corporate office of Gridco so also at the head offices of the four distribution zones so
as to enable them to submit their objections within thirty days from the date of
publication of the notice in the daily newspapers. It also stipulated that objectors, if
they so wished, could indicate their desire to be heard in person. A total of eighty eight
objections were received against Gridco's proposal for Distribution & Retail Supply
Tariff within the date line fixed i.e. 7th October, 1998. Out of the said eighty eight
objections, fifty one objectors who fulfilled the stipulated conditions were admitted for
personal hearing. Objections not admitted for personal hearing were also taken into
consideration by the Commission.
1.5 Commission, after receiving the
objections and admitting them for personal hearing as indicated above, published a notice
in a number of English & Oriya dailies for two consecutive days informing the
objectors as well as the public in general that the hearing on the proposal of Gridco for
Distribution & Retail Supply Tariff would take place from 14th to 17th October, 1998.
1.6 As notified, the public hearing on
the tariff proposal took place on the specified dates in the office of the Commission. The
Reform Act, 1995 does not require the Commission to hold public
hearing on tariff application. The Commission on its own however adopted the procedure of
inviting objections from the interested persons and called for a hearing with a view to
ascertain the views of a wide section of consumers and to ensure transparency, objectivity
and public participation. During the hearing, Gridco as well as objectors were requested
to confine themselves to issues relevant to the tariff proceedings so that the Commission
could arrive at a just and proper decision.
1.7 At the outset of the hearing, Mr.
K.N. Jena, Advocate appearing on behalf of M/s Orissa Consumers' Association, Cuttack
raised certain preliminary objections and sought the Commission's orders before proceeding
with the hearing.
1.8 Mr. Jena, raised the preliminary
objections on the following grounds, praying, inter alia, rejection of the proposal of the
Gridco for revision of the tariff structure:
(a) Provisions under section 57-A of Electricity
(Supply) Act, 1948 read with the provision of Reform Act, 1995
contemplate that charges for the supply of electricity, once fixed, shall be in operation
for three years. As such, revision of tariff within three years would be without authority
of law.
(b) When persons other than Gridco or private
entrepreneurs have not been granted licence, Gridco is not entitled to make provisions for
them in anticipation. As such the application for revision is premature. Furthermore he
alleged that the application seeks to defraud the consumers as companies which are being
floated are fake companies, have no financial standing, have not paid up any share capital
and have no bank account and infrastructure to carry on the business of distribution and
supply. This is being done to cover up Gridco's inefficiency, maladministration and loss
arising mainly due to extravagant expenditure.
(c) Since the licensee has revised the tariff twice
during the period 01.4.97 to this date, the present application is liable to be rejected.
(d) Licensee has failed to comply with the conditions of
licence. As such it should not be given any indulgence to revise the tariff until and
unless it fulfills the conditions of licensee and complies with the order of the
Commission.
1.9 The first objection refers to
Section 57-A of Electricity (Supply) Act, 1948 and holds that the present charges of
electricity effective from 01.04.97 should be in operation for 3 years. Mr. Jena in his
oral submission referred to the provisions of sub-clause (c) and (e) of sub-section (1) of
Section 57-A of Electricity (Supply) Act, 1948. These provisions are applicable only to
charges for electricity recommended by a Rating Committee and approved by the State Govt.
as per Section 57-A of Electricity (Supply) Act, 1948 and stipulate that such charges for
supply of electricity shall be in operation for such period not exceeding three years as
the State Govt. may specify in the order. Sub-section
(7) of Section 26 of the Reform Act, 1995 annuls the
constitution of a Rating Committee, making the above provisions of the Electricity
(Supply) Act, 1948 inapplicable in this case. We hold that this preliminary objection by
the learned counsel that the revision of tariff now proposed by the licensee is without
authority of law is not correct.
1.10 The second objection raised by the
learned counsel relates to premature submission of bulk supply tariff when persons other
than Gridco or other entrepreneurs have not been granted licence. The Commission has
carefully considered this issue. The Commission observes that the mandate of the Reform Act, 1995 is to provide for avenues for participation of private
sector entrepreneurs in the electricity industry. Gridco, the holder of the Distribution
& Retail Supply Licence, has already constituted four distribution zones and has
incorporated four subsidiary companies corresponding to these zones with Gridco as the
holding company. Further, the Gridco as the licensee for Distribution & Retail Supply
has initiated action proposing the divestment of the shares of these subsidiary companies
to private companies. Gridco's action in this regard is consistent with the Reform Act, 1995. Further, Gridco, the holder of Transmission &
Bulk Supply Licence, has applied for a bulk supply tariff to coincide with the aforesaid
action related to hiving off its distribution & retail supply business to different
companies. As action taken by Gridco with regard to restructuring and functional
unbundling are in pursuance of the objectives of the Act, 1995,
Gridco cannot be faulted on these accounts. Further, these have no material bearing on
Gridco's application for tariff amendment in respect of supply of energy to consumers and
related charges. Whether the licensee distributes and supplies electricity directly or
through four subsidiary companies, the revenue requirement and the tariff need scrutiny
and approval of the Commission. Therefore, it is perfectly in order for Gridco, holding
the licence for Distribution & Retail Supply, to file the revenue requirement and
charges for supply of energy.
1.11 The third objection has not been
amplified by the learned counsel. As there has been no tariff revision since 01.04.97 till
date, the objection is devoid of any merit.
1.12 The fourth preliminary objection
raised by the learned counsel relates to debarring the licensee from revising the tariff
until and unless they fulfill the conditions of the licence and comply with the order of
the Commission. The Commission observes that non-compliance of the licence conditions or
inadequate compliance, if any, is a totally separate issue relating to monitoring of
compliance of licence conditions by the Commission. It may have a bearing on the charges
to be levied but as long as the licensee has obligation to serve, it has to realise
charges. Elaborate provisions exist in the Reform Act, 1995 to deal
with non-compliance or violation of licence conditions. The filing of revenue requirement
is a statutory requirement of the licensee as provided in sub-section (4) of Section 26 of the Reform Act, 1995 and, therefore, this function must not be mixed up
with other issues. On these grounds the Commission did not admit any of the preliminary
objections raised by the learned counsel and ordered the proceeding to continue.
1.13 Before examining the Gridco's
proposal one more procedural objection raised in the hearing may be examined by us at this
stage. Mr. Indrajit Mohanty, Advocate, appearing on behalf of M/s Nalco raised a
procedural objection. Quoting section 28 and 29 of the Act, 1995 he argued that
the Commission should not only proceed under Section 26 of the Act, but after obtaining
consultation under the said section it has to issue a proposed order on which reaction has
to obtained and then only final order can be passed.
1.14 We have carefully considered the
objection. We find that Section 29 of the Reform Act, 1995 is in Chapter IX of the Act under the title "Commission's Power to Pass Orders And Enforce
Decisions". The provisions of the Sections under this Chapter form an interconnected
group and the scope of those provisions is defined by Sec.28(1). It runs as follows :
"Where the Commission is satisfied that a licensee
is contravening, or is likely to contravene any relevant conditions or requirement of its
licence, it shall by final order under section 29 and ,
if it thinks it appropriate in accordance with sub-section
(2) by interim order under this section, issue such directions as it deems proper for
securing compliance".
The orders contemplated under Section 29 or Sub-section (2)
of Section 28 relate to contravention or likely contravention of any relevant
conditions or requirement of the license and not to any other type of orders. An order
setting tariff is not an order relating to contravention of a condition or requirement of
a license. Section 29 is sequential to Section 28 and the words "final order" therein
has the same denotation as the words "final order" in Section 28(1) - that is, an order in respect of
contravention of a condition or requirement of a license.
1.15 Section
29 (1) (b) itself states that notice of the proposed "final order" shall set
out information referred to in Sec.28(3)(b), namely,
the relevant conditions or requirements (evidently of the license) with which the proposed
order is intended to compliance; the acts or omissions which, in the opinion of the
Commission, constitute contravention of that condition or requirement; other facts which
would justify the proposed order and the effects of the proposed order. This conclusively
suggests that the "final order" contemplated in Sec.29
is an order in respect of contravention of a license condition or requirement.
1.16 An order u/s 26 setting tariff is
a regulatory order in discharge of the Commission's function under Sec.11(1) (e). The tariff-setting power under Chapter VIII is one form of regulation and license-enforcing power
under Chapter IX is another form of regulation. They are
distinct fields of regulation. The methods employed in each field are distinct. The Act
deals with them in distinct Chapters. It is not permissible to take one provision out of
its context from one Chapter and apply it in another Chapter dealing with a different form
of regulation.
1.17 We therefore find that the
objection raised by the learned Advocate Mr. Indrajit Mohanty is not valid.
2.0 GRIDCO'S
PROPOSAL
2.1 The application filed by Gridco has
given elaborate calculation of its revenue requirements and upward revision of the tariff
approved by the Commission in its Order No.009 dated 12th March,
1997. The amendment to tariff is stated to be necessitated due to following reasons :
a) The revenue from existing tariff is not sufficient to
meet costs properly incurred by Gridco.
b) The restructuring of the Gridco's distribution and
retail supply business into four zones to be managed by four subsidiary companies has made
it necessary to disaggregate revenue requirement on zonal basis.
c) The tariff structure inherited by Gridco is required
to be redesigned keeping in view the objects of the Reform Act.
2.2 Gridco have proposed uniform retail
tariff for all four zones, calculating the revenue requirement on the basis of embedded
costs in accordance with the provision of the Sixth Schedule to the Electricity (Supply)
Act, 1948.
2.3 The revenue requirement for the
year 1997-98 has been estimated as Rs.2615 crores (including previous accumulated loss of
Rs.543.1 crores). The revenue from existing tariff without the proposed revision is
estimated as Rs.1646.2 crores. Gridco's estimate of revenue during 1997-98 on the basis of
the existing tariff applicable for 8 months and revised tariff for 4 months (from
01.12.97) is Rs.1715.9 crores. The estimated revenue on the basis of the proposed revised
tariff for a full year is estimated as Rs.1855.5 crores. During a full year, Gridco's
proposal leaves a gap of Rs.216.5 crores. It is stated by Gridco that the gap is
substantially accounted for by its outstanding subsidy claim of Rs.198.1 crores on the
Govt. of Orissa.
2.4 Gridco have estimated the
accumulated loss till the end of 1997-98 as Rs.543.1 crores, but have not proposed to
cover this amount in the tariff revision proposals, as they have approached Govt. of
Orissa to allow a "Special Appropriation" to cover the amount, as provided in
the Sixth Schedule of the Electricity (Supply) Act, 1948.
2.5 Gridco estimate the cost of power
purchase for 1998-99 as Rs.1276.2 crores, operational expenses as Rs.635.88 crores and
return on Capital Base at Standard Rate of (10.5+5)% as Rs.159.87 crores. Power purchase
from different sources is estimated at 10,814.97 MU corresponding to a sale of 6380 MU at
an overall T & D loss level of 41%.
2.6 Gridco have proposed that the
transmission charge of 40 paise per unit in the existing tariff may be retained for the
use of its transmission system within the State. A composite Bulk Supply &
Transmission tariff to be applied to the distribution licensees has been proposed as
Rs.300 per KVA of recorded maximum demand per month plus 81.70 paise per Kwh of energy
delivered.
2.7 Gridco have not proposed any change
in categorisation of retail consumers. It has been proposed to introduce an optional
tariff for power-intensive industries to provide incentive for such industries to avail
Gridco supplies in preference to setting up their own Captive Power Plants.
2.8 The proposal also provides for
several significant departures in the structure of tariff. Charges to all categories of
consumers are proposed to be unbundled into;
a) a Customer Service Charge to reflect cost incurred in
metering, meter reading, billing and providing related customer services,
b) a Demand Charge to reflect a portion of the fixed
cost of power purchase, and maintaining and developing the transmission and distribution
system, and
c) an Energy Charge to reflect remainder of fixed costs,
the variable cost of power purchase and system loss.
2.9 It is proposed by Gridco to
discontinue the existing provision of Monthly Minimum Energy Charge with the introduction
of a demand charge and a separate customer charge to recover the portion of fixed cost
associated with providing supply. With provision of tariff across voltage levels, the
provision of surcharge for supply at voltage other than that at which tariff is specified
is proposed to be withdrawn. It is proposed to allow without penalty overdrawal beyond
contract demand during off-peak hours upto 20% for EHT industries where TOU meters are
provided. This facility is to be extended to HT industries once TOU meters are provided
for them.
2.10 It is further proposed to provide
an incentive at one fourth of the rate of penalty when power factor is maintained above
0.92. The existing provision of a separate rent for meters provided by the licensee is
proposed to be withdrawn as costs associated with this are proposed to be recovered
through the customer service charge. Consumers providing their own meters are proposed to
be given an appropriate reduction in the customer service charge.
2.11 It has been stated that Gridco
have carried out a survey through Revenue Improvement Action Plan (RIAP). The survey
indicates that load factor billing for defective meters and unmetered supply constitute a
substantial proportion of LT supply, and that actual load factors in such cases are
substantially higher than those prescribed in the present tariff. This provides an
incentive for consumers not to have their defective meters rectified. Gridco have urged
the Commission to approve adoption of load factors higher than those specified in the
present tariff and much higher than the findings in the survey to provide correct
incentives for adoption of metering by consumers.
2.12 Gridco have submitted a formula
for fuel and power purchase cost adjustment.
2.13 Consultation with the
Commission Advisory Committee :
Gridco's proposal on Distribution and Retail Supply Tariff was discussed in the Commission
Advisory Committee meeting held on 8.10.98 for this purpose and the views expressed by the
members of the Committee have been taken into consideration by the Commission in this
order.
|
3.0 OBJECTIONS DURING HEARING
3.1 As stated earlier fiftyone
objectors were admitted for personal hearing. The objectors have raised vital issues and
have enlightened the Commission with many useful suggestions in various areas of concern.
At the same time, it is noted that several objections raised are not relevant to the
tariff proceedings.
3.2 Commission has taken note of the
almost universal complaint regarding poor quality of supply and poor consumer services.
While it is not possible to deal with these concerns effectively while dealing with tariff
revision proposals under Section 26 of the Reform Act, 1995, Commission takes note of them for evolving effective
methods for encouraging Gridco to move more rapidly towards functioning in an efficient,
economic and competitive manner.
3.4 As had been observed in Commission Order No.009 of the 12th March'97, (on Gridco's tariff application
for 1997-98), objections with regard to the reform, restructuring and privatisation
programme, various aspects of revaluation of assets on transfer to Gridco & OHPC are
beyond the scope of this Commission since they hinge on public policy and legislation.
3.5 Many of the issues raised by the
objectors such as classification of consumer categories, security deposits, interest on
security deposits, etc. although related to tariff, are more relevant to the Distribution
(Conditions of Supply) Code whose modification and amendment have to be considered
separately. We do not, therefore, intend to deal with them in this order.
3.6 Objections have been raised by
industries which are sick or potentially sick or covered by BIFR awards, or which seek
protection, concessions and special treatment. This was also dealt in Commission's order
on Gridco's proposal for 1997-98 tariff amendments. Gridco as an independent corporate
entity is neither expected nor is capable of taking care of socio-economic policies and
programms of the Govt. except with regard to electricity. It is mandated to be run with
efficiency and economy to deliver safe, reliable and economic power supply. It is bound by
law to arrange its affairs so as to realise cost of supply and earn reasonable return. It
cannot take care of the financial interests of the users. The objectors have to address
the issues of concession and protection etc. to the Govt. who may issue policy directives
in accordance with its socio-economic objectives. Hence we do not consider it necessary to
deal with objections pleading for concession, special treatment and subsidy by
Gridco.
3.7 Other important issues raised in
the objections may be indicated below before our observations and findings are given on
the same.
3.7.1 Revenue Requirement :
3.7.1.2 Gridco have projected a rather high T&D loss resulting in larger quantum
of power purchase from costlier sources. T&D loss reduction is not in compliance with
Commission order for 1997-98 tariff.
3.7.1.3 Power purchases has not been optimised. Cheaper power from hydro stations and CPPs
should be maximised and drawal of costlier EREB power reduced.
3.7.1.4 Capital base has been increased from Rs.523 crores in 1997-98 to Rs.1031 crores in
1998-99. Lower valuation of assets by the Gridco's chartered valuers should have been
used.
3.7.1.5 Subsidies due from the Government should be realised and the revenue gap on this
account should not be allowed to have impact on revenue requirement.
3.7.1.6 Previous losses should not be considered for the present revenue requirement.
3.7.1.7 Depreciation should not be charged on revalued used assets at Govt. of India
notified rates. Only assets created after 01.04.96 should be allowed for depreciation
based on book values in asset register.
3.7.1.8 O&M expenses have increased substantially over previous year.
3.7.2 Non - industrial (LT) category,
e.g.
Domestic, Commercial, Street Light, Agriculture, Public Institution etc.
3.7.2.1 The following objectors put forth objections and observations in respect of rate
of tariff proposed for domestic, commercial and agricultural consumers as also with regard
to categories of street light and public institutions:
-
United Hatchery Pvt. ltd., Jagamara, Khandagiri,
Bhubaneswar.
-
Dr. Atul Krushna Mohanty, S.C.B. Medical College,
Cuttack.
-
General Secretary. District Biju Janata Dal, Sambalpur.
-
Jt. Secretary, Federation of Consumer Organisations,
Budhanagar, Bhubaneswar.
-
Er. Amarendra Pradhan, Angul.
-
President, Koel Nagar Welfare Association, Rourkela.
-
Orissa Consumers Assn., Biswanath lane, Cuttack.
-
President, The Nayapalli Community care Assn.,
Bhubaneswar.
-
Mr. P. K. Mishra, Old Bhubaneswar.
-
President, Orissa Grahak Mahasangha, Jatni, Khurda
-
Er. B.N. Das, Bhubaneswar.
-
Utkal Chamber of Commerce & Industry Limited,
Cuttack.
-
Secy. Aska Chamber of Commerce, Aska, Ganjam
-
Confederation of Indian Industry, Bhubaneswar.
-
Er. Dhaneswar Dhal, Bhubaneswar and Er. R.P. Mohapatra.
-
Mr. C. S. Sastry, Cuttack
-
Er. R.C. Padhi, Bhubaneswar
-
Secy. The Senior consultant & Adviser Group,
Bhubaneswar
-
Mr. B. K. Mohapatra, Cuttack
-
Prof. N.C. Sahu, Rourkela
The objections are summarised below :
-
While withdrawal of monthly minimum charge is
welcome, imposition of Demand Charge and Customer Service Charge is not appropriate for
the LT consumers as this will be a serious burden.
-
Load Factor billing when meter is defective or for
unmetered supply is not appropriate in view of provision of Section 26 of I.E. Act, 1910.
Gridco's load assessment is arbitrary and does not recognise use of energy saving
appliances or infrequently used outlets. Meters are not being promptly replaced/repaired
by Gridco even when consumers report them as defective.
-
The rates proposed will mean small LT consumers pay
higher per unit charges compared to large consumers.
-
Cheaper hydro power should be earmarked for LT
consumers and cross subsidisation should continue considering the paying capacity of
consumers.
-
Gridco should provide rebate to consumers for
periods of low voltage, interruption and poor service.
-
Proposed new connection charge is arbitrarily high.
-
Temporary connection charge proposed is too high
considering that the consumer supplies all material.
-
Charging for line extensions is not as per
Distribution Code.
3.7.2.2 LT Industries : (Small/Medium)
Objections and observations were made in respect of tariff proposals for small and medium
industries by the following objectors :
-
District Small Scale Industry Assn., Koraput, Jaypore.
-
Orissa Young Entrepreneurs Assn., Cuttack.
-
Orissa Assembly of Small & Medium Industry,
Rayagada.
-
Orissa Assembly of Small & Medium Industry,
Cuttack.
-
Confederation of Indian Industry, Bhubaneswar.
-
Keonjhar District Small Scale Ind. Assn., Barbil.
-
Orissa Small Scale Ind. Assn., Cuttack
-
Dist Small Scale Ind Assn., Cuttack.
-
Jaypore Motor Garage Owner Assn., Jaypore.
The objections are summarised below :
-
Rates proposed for Small & Medium Industries are
too high and hence they will affect the financial viability these industries.
-
Imposition of Demand Charges on LT industries is not
appropriate.
-
There should be no charge when no power is drawn
during disconnection.
-
There should be no load factor billing for Small
Scale Industries because of Gridco's failure to replace defective meters. Load factor
billing is also illegal.
-
Time of Use tariff should be introduced for medium
& small scale industries also.
-
There should be no penalty for overdrawal as there
is no demand metering for small & medium Industries.
-
There should be a provision of rebate for timely
payment as there is a surcharge for delayed payment.
-
Industries should be reclassified with Small
Industries upto 99 KW and medium Industries upto 500 KW.
-
There should be no Delayed Payment Surcharge or
power factor penalty for medium industries.
-
In the absence of demand metering, demand should be
calculated on the average of energy consumed.
3.7.2.3 HT/EHT Industries
Objections and observations were made in respect of tariff proposals for HT/EHT industries
by the following objectors :
-
Larsen & Toubro
-
Jayashree Chemicals
-
Konark Jute Mills
-
Steel Authority of India Ltd.
-
Kalinga Iron Works
-
Orient Paper Mills
-
Aditya Aluminium
-
IPISTEEL
-
Confederation of Indian Industries
-
Nilachal Ispat Nigam Ltd.
-
JK Corporation
-
Sonepur Spinning Mill
-
Mr. Narottam Das
-
Western Orissa Sugar Mill
-
FACOR
-
Ispat Alloys
-
TISCO
-
Nava Bharat Ferro Alloys
The objections are summarised below :
-
HT tariff rate should be the same as EHT tariff
rate.
-
Rebate should be allowed for payments made before
due date.
-
Security deposit should not be enhanced with every
tariff revision.
-
Incentives for improved power factors over that
prescribed should be at the same rate as the penalty for power factor lower than that
prescribed. The prescribed limit should be reduced to 85% from the present 90%.
-
There should be no overdrawal penalty during
off-peak periods.
-
Energy allowed for consumption in industrial colony
should not be restricted to 10% of total consumption.
-
Demand charge should not be enhanced as this would
make the rate higher than in other States.
-
The load factor for the proposed incentive tariff
should be reduced from 60% to 40%. This tariff should also be applicable to large
industries and heavy industries.
-
The arrangement for supplying NTPC power to EOUs
should continue.
-
There should not be any load factor billing in case
of defective meters.
-
Monthly demand charge should be on actual demand and
not on 80% of contract demand.
-
Tariff should provide for rebate to consumers for
period of over-frequency.
|
3.7.5 Industries with CPPs
With regard to industries having Captive Power Plants, objections were raised and
suggestions were made by M/s NALCO, M/s ICCL, M/s INDAL, M/s Aditya Aluminium and also by
Bhubaneswar Chapter of Confederation of Indian Industry.
On merits of tariff proposal, all the objectors pointed
out that the rate of back-up power for CPPs is discriminatory and is unreasonably high.
Further common points of objections were that only incremental cost should be charged for
emergency power supply and that there should be no power factor penalty during periods of
high system voltage.
Mr. Indrajit Mohanty, learned advocate, representing of
M/s Nalco stated that M/s Gridco was not justified in ignoring the increased cost of fuel
and pay only 77 paise per unit towards cost of CPP power. It was urged that M/s Gridco
should be asked to honour the special agreement of June'94 which provided that while
emergency supplies are to be charged by M/s Gridco at three times of M/s Nalco's supply
rate, there would be no further charge towards wheeling, transmission loss, demand charges
etc.
Mr. S. K. Tamotia, Chairman-cum-Managing Director of M/s
Aditya Aluminium raised some general issues as well as issues on tariff for CPPs, special
treatment for construction industry, transmission charges and domestic rates. The main
objections relevant for the present proceeding raised by Mr. Tamotia relate to adverse
impact of high power cost in general and on CPP owners in particular on capital cost of
industries and on the industrial climate of the state. He suggested settlement between
Gridco and CPP on net exchange basis, non-discriminatory energy charge for CPPs, lower
demand charge and single part tariff for construction industry.
3.7.6 Railway Traction
The Chief Electrical Distribution Engineer of South Eastern Railway representing Indian
Railways urged that railway traction being a public utility should receive special
consideration for the tariff which is already too high and hence should be reduced. He
further urged that the tariff for supplies at 25 KV should be same as that at 132 KV,
demand should be assessed on half hour basis and not on 15 minutes basis, billing for
maximum demand should be on the basis of integrated simultaneous maximum demand for a
section and not at each supply point and that the railway traction tariff should not be
higher than the industrial tariff.
3.7.7 Investors
Mr. N.K. Gupta, DGM, Tata Hydro Electrical Power Limited Company wanted to be heard on
behalf of the investors. He stated that in the interest of achieving the objectives of
Reform Act, the apprehension of investors should be taken into account by the Commission
and right signals should be given in the tariff judgment ensuring adequate rate of return.
He invited attention of the Commission to the Schedule VI of Electricity (Supply) Act,
1948 and pleaded that linking rate of return to the lending rate of Reserve Bank of India
brings in an element of uncertainty which should be avoided. In view of the volatile
economic condition in a developing country, the rate of return should be delinked from the
bank rate and the Commission should declare a fixed rate of return of 18% or more for the
utility.
4.0 GRIDCO'S REPLY TO THE OBJECTIONS
4.1 Mr. B.C. Jena,
Chairman-cum-Managing Director, Gridco replied to the various issues raised by the
objectors. He categorised the objections broadly as follows :-
-
relating to the degree of compliance with statutory
provisions and directives of the OERC.
-
relating to the calculation of the revenue
requirement.
-
relating to the assessment of revenue.
-
relating to the proposed tariff design and level of
the proposed tariffs and charges.
-
miscellaneous objections
-
objections unrelated to the present filing.
4.2 Statutory Compliance
4.2.1 On the problem of high frequency in the system, he explained that due to inadequate
evacuation facility of surplus power from the Eastern Region, the entire region is
suffering from high frequency in the grid. Remedy of the problem is beyond the control of
Gridco but Gridco has initiated discussions for better grid discipline.
4.2.2 He submitted that due to inadequate investment in the past, there are interruptions
in the power supply and the situation is being attended through appropriate investment for
which investment programmes have been submitted.
4.2.3 To the objection about noncompliance like delay in the issue of Regulations,
Distribution Code and Performance Standards, he informed that Gridco's proposals have been
submitted for approval of the Commission.
4.2.4 On the allegation that Gridco have failed to implement the OERC directives he stated
that Gridco faces major constraints and the effort made by Gridco to comply with the
directives of the OERC have to be viewed in this context. Gridco have substantially
improved the information supplied in the tariff proposal of 1998-99.
4.2.5 On the issue of non submission of Audited Accounts for 1997-98, he stated that there
has been significant improvement over the past year. The management accounts for 1997-98
have been included as a part of the tariff filing and the Audited Accounts would be
available by the end of the year.
4.2.6 To the objectors' complaint that the system loss target of 35% set by OERC for
1997-98 has not been achieved, he pointed out that despite constraints, the extent of
reduction in system loss by end of the current year would be 8.5% over previous year
actual loss of 49%. He stated that the base figure of loss had been earlier wrongly shown
at 46% and hence there is a misleading impression that there has been no significant
reduction in loss.
4.2.7 To the complaint of the objectors that Gridco have not been able to control the
administrative costs and interest burden, he submitted that the employees cost, other
expenses and interest have declined per unit of sale of energy over the past year.
4.3 Revenue Requirement
4.3.1 Some of the objectors have stated that Gridco is mis-representing the transmission
loss by giving mis-leading data so much so that as against the actual transmission loss of
3.82%. Gridco is calculating it at 5.3%. It was explained by the CMD that by calculating
the transmission loss on the net basis, the loss is 5.3%.
4.3.2 On the issue of subsidy to be claimed from State Govt., he submitted that Rs. 198.1
Crores has been claimed towards subsidy from the Govt. for 1997-98. No subsidy has been
claimed for the year 1998-99. The Govt. of Orissa have not yet approved these claims for
subsidy. Even if these claims are approved, the subsidy received will go towards
receivables.
4.3.3 To the question that the asset valuation is arbitrary, he replied that the value of
asset has been based on the asset valuation reflected in the Transfer Scheme which has
been accepted by the OERC.
4.3.4 On the issue raised by the objectors that depreciation is not being charged as per
Electricity (Supply) Act 1948, he submitted that the depreciation has been charged as per
the appropriate Notification dated 29th March, 1994 of the Govt. of India.
4.3.5 To the question of increase of capital base from Rs.523 Crores in 1997-98 to Rs.1031
Crores in 1998-99 without investment, he submitted that during the year 1998-99, Rs.425.32
Crores is proposed for addition to the fixed assets. Besides, he submitted that Gridco has
moved the Government of Orissa for the conversion of Govt. loan to equity.
4.3.6 On the next issue that the cost of purchase of power would be lower if Gridco
adopted the principle of merit order dispatch, he submitted that variations from the
scheduled drawal do occur for reasons beyond the control of Gridco such as reduced
availability of hydro power due to hydrological failure and high frequency in the Eastern
Region putting constraints in drawal of power from CPPs.
4.3.7 On the issue that CPPs should be encouraged to supply more energy to reduce the cost
of purchase of power, he submitted that the power availability from the CPPs is infirm in
nature. He stated that induction of progressively higher volume of infirm power and
associated backing down of the plants where the utility has to pay the fixed cost of
generation will be financially adverse for the utility. Therefore, CPP power can be
considered cheaper only if the cost is less than the highest available variable cost of
the plants connected to the grid.
4.4 Assessment of Revenue
Some of the objectors had stated that the proposed high load factor for consumers with
defective meters and unmetered supply would increase the billing figure leading to
reduction of the estimated T&D loss. To these, he clarified that the estimated system
loss of 41% is contingent on the approval of higher load factor from December, 1998
onwards.
4.5 Tariff Design
4.5.1 To the issue raised by the industries that the cross-subsidy should be reduced as
they were not in a position to bear the cross-subsidy, he replied that the proposed EHT
tariff has stagnated in nominal terms and the rise is nominal for HT consumers.
4.5.2 On the issue that the increase in demand charge of Rs.200/- to Rs.300/- per KVA per
month will impose excessive burden on the industries he clarified that the demand charge
is based on the fixed cost associated with meeting the power demand of the customers. With
proposed withdrawal of minimum energy charge and decrease in the rates of energy charge,
the proposed increase in demand charge would be completely offset and shall pose no
significant additional burden on these consumers.
4.5.3 On the issue that the demand charge for HT and EHT industries are more than the
demand charge for LT industries, he clarified that while the demand charge for LT
consumers is based on the contract demand, in case of HT & EHT consumers the same is
being billed on the basis of the recorded demand.
4.5.4 Some objectors had raised the issue that the levy of demand charge on small
consumers was burdensome and would adversely affect the small industries, Shri Jena said
that the introduction of demand charge would not increase the burden as the minimum energy
charge payable by the consumers was being withdrawn. He further clarified that the demand
charge on these classes of customers has been kept very low in comparison to the demand
charge for large industries.
4.5.5 On the issue that there should be no distinction between the tariffs of EHT & HT
supply, he justified the necessity of a separate tariff due to the difference in the cost
of supply.
4.5.6 Some of the objectors had raised the issue that Gridco's tariff was high compared to
other States. Shri Jena clarified that the variations in tariff were on account of high
cost of power purchase, consumer profile and the investment required for growth. He stated
that Gridco's tariff was comparable to that of Maharashtra, Karnataka and Haryana.
4.5.7 Some of the objectors had raised the issue that the reduction of slabs in the
domestic category would hit the small consumers most. He replied that this was a necessity
and a part of tariff reform. He submitted that the proposed increase was 47% for rural
consumers and 20% for urban consumers with an average consumption level of 182 units per
KW per month and 270 units per KW per month respectively.
4.5.8 Some of the objectors had said that the proposed load factor billing was
unreasonable. He emphasised that the proposed high load factor was not a revenue earning
device alone. This was primarily intended to remove the existing incentive for preferring
unmetered billing.
4.5.9 To the question that the transmission tariff of Gridco is too high compared to the
transmission charge of PGCIL, the CMD replied that the lines of PGCIL operate at higher
voltage like 400 KV and 220 KV which results in lower losses. The PGCIL system consists of
longer lines and fewer sub-stations.
4.5.10 The calculation per unit of transmission charge in case of PGCIL is done on the
assumption that the entire energy despatched from the central generating station is being
transmitted through the PGCIL system. In reality a part of PGCIL generation is transmitted
through the lines of other constituents. As regards the lower rate being applied for
transmission of power to APSEB and MPSEB, he pointed out that the wheeling of such power
is necessary for export of surplus power from the region to raise the load factor of the
central generating stations. Operating central station at high load factor results in
economy to Gridco.
4.5.11 To the objectors issue that the distribution of cost between peak and off-peak
loads may provide the true average cost of transmission rather than the calculation of the
marginal cost on peak load he replied that the derivation of average cost is a concept
derived from the method of calculation on embedded or average cost basis. The same
methodology cannot be applied for calculation of costs at peak and off-peak on marginal
cost basis.
4.5.12 Some objectors had said that there should be no penalty for overdrawal during
off-peak. If a penalty is imposed the limit for overdrawal without penalty should be
increased. To this he replied that the limit of overdrawal at 120% of the contract demand
is meant for application to a select group of industries at EHT were facility of
appropriate metering is available. Allowing overdrawal without off-peak may pose a problem
to the system stability and security. With no restriction on overdrawal the usefulness of
agreement for contract demand will be lost and the utility may not be in a position to
estimate the power requirements at a future date.
4.5.13 Some of the objectors had stated that there is no justification for giving power
factor incentive at only 1/4th of the rate of penalty. The incentive should be equal to
the penalty. The incentive should start from 0.9 instead of above 0.92. To this he replied
that the penalty is intended to motivate large customers to maintain power factor at the
required level. The incentive proposed will offset the extra expenditure incurred by them.
Provision of incentive at a power factor above 92% serves as a bench mark and has to be
treated differently from that of the levy of a penalty.
4.5.14 To the question of stipulation of minimum energy consumption being reduced to 25%
to 30% in stead of the proposed 60% as proposed for the Power Incentive (optional
category), he replied that the proposed load factor of 60% would be calculated annually.
Therefore industries running at a load factor much below 60% can still avail the benefit
if high load factor is attained in other months of the year. To the question that the
energy charges for power intensive industries should be reduced and should be equal to the
cost of energy, he replied that the issue is related to the cross-subsidisation by EHT and
HT consumers to LT consumers which has to be rectified over a period of time. To benefit
the power intensive industries, reduction of rate has already been proposed by Gridco.
4.5.15 Miscellaneous Objections : To the issue of raising the limit of 120% of the
contract load for exemption of overdrawal by the Railways, he pointed out that in the
absence of appropriate metering facility for the Railway Traction, this facility cannot be
extended. This facility is for the present being proposed only in respect of the EHT
industries.
4.5.16 To the question of the Railways that no tariff has been proposed for supply to them
at 25 KV, the CMD clarified that the tariff at HT would apply to the supply at 25 KV. It
would not be appropriate to have one tariff for supply at 25 KV and another at 132 KV due
to difference in cost of supply.
4.5.17 To the question raised by L&T that the concessional rate of supply of power to
industrial colonies should apply without limit, he clarified that the present limit of 10%
of the total supply for residential colonies should be adequate as the industries are all
large consumers of energy.
|
5.0 COMMISSION'S ANALYSIS AND
DECISION ON GRIDCO'S PROPOSAL
5.1 In order to determine the revenue
requirement of the licensee on the basis of which the Retail Supply Tariff is to be
approved, the Commission has analysed the components of the licensee's costs. These are
discussed below:
5.1.1 Volume of Power Purchase
-
The Orissa Electricity Regulatory Commission in its
order on tariff for the year 1997-98 had approved a net sale volume of 6091 million units
corresponding to power purchase of 9371 million units on the basis of T&D loss of 35%.
This purchase did not include NTPC power for supply to the 100% export oriented units
(EOU) and 95 MU for back up supply to ICCL. Taken together, the total sale for the year
1997-98 approved by the Commission was 6380 (6091+194+95) million units corresponding to
9815 MU of purchase.
-
Gridco have estimated that the energy sale during
the year 1998-99 will be 940 million units more than the actual sale of 5440 MU during
1997-98. This increase has been attributed to an increase of 339 MU or about 6% in demand
on account of load growth over the previous year and about 601 million unit on account of
expected reduction in losses. Thus Gridco's estimated sale for the year 1998-99 is
projected as 6380 (5440+940) million units.
-
The Commission, after taking into consideration the
proposed increased sale of 339 million units on account of load growth over the approved
sale figure of 6091 million units for the year 1997-98, estimates the sale for the current
financial year (98-99) as (6091+339) 6430 million units excluding NTPC power to be wheeled
to Export Oriented Units. This sale figure includes increase in billing on account of
reduction in commercial losses. In other words, it includes the conversion of lost units
to billing units due to improvement in billing and revenue collection.
-
The Commission, while approving the tariff for the
financial year 1997-98, had considered the T&D loss level of 35% as reasonable and
appropriate. The Commission had expected Gridco to devise its management strategy with the
foremost objective of achieving rapid reduction in the T&D loss level. The Commission
while adhering to earlier loss figure of 35%, reiterates that Gridco must continue to take
all possible steps for reduction of T&D losses for the current year to the earlier
benchmarked level of 35%. On this basis, a projected sale value of 6430 million units,
Gridco may have to purchase 9891.39 million units. To meet the estimated sale of 194
million units to the export oriented units with EHT loss of 4% (194/0.96MU) 202 MU of
additional power may have to be purchased. Therefore, the total requirement of power
purchase will be 10093.47 million units.
Gridco, in its tariff proposal for the year 1997-98, had
estimated a purchase of 11000 million units from the various sources, but as per the
actuals for the year 1997-98 the total purchase was 10357 million units. This was 643
million unit less than what was projected by Gridco. The current year's projection by
Gridco is 10814 million units at a loss level of 41%. Taking into account the estimates
and the actuals for the year 1997-98, the Commission considers the estimates of purchase
for the current year as an over estimation. The purchase of power may, therefore, be
limited to 10093 million units, inclusive of the power requirement of the 100% export
oriented units. This is summarized as follows :-
|
|
Tariff proposal
of Gridco for 1997-98 (in MU) |
Approval by the Commission
(in MU) |
i.
|
Quantum of power purchase
|
11000
|
9815
|
ii.
|
Quantum of total sale
|
6380
|
6380
|
iii.
|
Sale to 100% EOU included in (ii) above
|
194
|
194
|
iv.
|
Sale to ICCL as back up power included in (ii) above
|
95
|
95
|
v.
|
Quantum of sale to consumers other than 100% EOU & back
up power supply to ICCL(ii-iii-iv)
|
6091
|
6091
|
Performance of Gridco for 1997-98
Quantum of power purchase 10357.29 MU
Quantum of total sale 5439.6 MU
|
|
Tariff proposal of Gridco for
1998-99 (in MU) |
Approval by the Commission
(in MU) |
i.
|
Quantum of power purchase
|
10814
|
10093
|
ii.
|
Quantum of total sale projected
|
6380
|
6430+194=6624
|
iii.
|
Sale to 100% EOU included in (ii)
|
Nil
|
194
|
iv.
|
Sale to consumers other than 100% EOU (assuming a sale of
194MU to EOU based on the projection of 97-98 but not reported by Gridco)
|
6186
|
6430
|
v.
|
Assumption of T&D loss
|
41%
|
35%
|
5.1.2 Gridco has proposed a total sale volume of
6380 million units for the year 1998-99. If the sale to 100% EOU estimated at the previous
year level of 194 million units is deducted then the sale figure of Gridco will be
modified to (6380-194) 6186 million units. As against this Commission has approved a sale
of 6430 million units excluding 100% EOU.
5.1.3 The additional sale now estimated by the Commission should be achieved by Gridco
through loss reduction measures and enhanced billing to consumers with defective meters
and unmetered supply for whom a higher load factor is being approved by the Commission.
A categorywise comparison of sale figures proposed by Gridco and approved by the
Commission for the year 1998-99 is given in Annex-E.
6.0 EXPENDITURE OF GRIDCO IN
DISTRIBUTION & RETAIL SUPPLY
6.1 Cost of Purchase of Power : The
Distribution & Retail Supply Licensee has to procure 9495.73 MU from the bulk supplier
at the Commission's approved rate of Rs.200/KVA/month + 85.5 paise per unit. The total
cost of power purchase works out to Rs.1282.47 crores. It is clarified that even though
supply of NTPC power to the EOUs shall be routed through the distribution companies,
revenue received from the same shall be payable to Transmission and Bulk Supply Licensee.
6.2 Expenditure on distribution and
supply : The expenditure of distribution and retail supply may be considered under
following heads :
-
Employees cost
-
Material cost
-
Administrative and general expenses
-
Less expenses capitalised
These are discussed below :
(a) Employees Cost : The expenses chargeable to
Operation and Maintenance for transmission and distribution taken together on account of
the employees cost for the year 1998-99 is estimated by Gridco at Rs.264.79 crores. These
expenses include impact of revision of wages and terminal benefits. The impact of revision
of wages and terminal benefits together amounts to Rs.24.12 crores. Thus, Employees Cost
excluding the impact of revision of pay and terminal benefit works out to Rs.240.67
crores. Corresponding figure for 1997-98 as approved by the Commission was Rs.214.34
crores. The Employees Cost of Gridco as per the audited accounts of 1996-97 was Rs.202.58
crores. With an upward adjustment of 3% and 6% towards normal annual increment and
inflation respectively, the Employees Cost works out Rs.240.67 crores for the year
1998-99. Keeping in view the wage revision impact of Rs.24.12 crores, a sum of Rs.264.79
crores claimed by the licensee is found reasonable. Out of Rs.264.79 crores, Rs.207.21
crores has been allocated to the Distribution and Retail Supply Business.
For calculating employees cost, no additional man power
has been assumed by Gridco. The commonly used indicators for man power utilisation are No.
of employees per MKwh sold & No. of employees per 1000 consumers. A comparative
statement with All India average is given below :
Number of employees per thousand consumers :
(i) All India average - 12 (Compiled upto end of 1995)
(ii) Gridco - 24.82 or 25 (Compiled upto end of 1998)
Number of employees per MKwh of electricity sold :
(i) All India average- 3.9 or 4 (Compiled upto end of 1995)
(ii) Gridco- 4.9 or 5 (Compiled upto end of 1998)
It is apparent that Gridco requires substantial growth
in number of consumers and sale to be at par with the all India norms.
(b) Maintenance Cost : This is the cost of
materials/spares required for maintenance of lines and substations. Gridco have estimated
the material cost at Rs.80.25 crores for 1998-99 for both transmission and distribution.
It is assumed by the licensee that it will spend approximately 4% of value of average
assets for maintenance of lines & substations (RTCL - 13).
World Bank in their observation (Staff Appraisal Report
on Orissa Power Sector Restructuring Project, April 1996) have assumed 5% of average fixed
assets towards material cost for distribution system. 5% of the average distribution
assets of Rs.1074.51 crores works out to Rs.53.73 crores. Keeping in view the present
rundown condition of assets and the urgent need to upgrade them it is considered
reasonable to take 5.4% of average asset which comes to Rs.58.29 crores for distribution
and retail supply.
(c) Administration & General Expenses :
Gridco have proposed an expenditure of Rs.26.3 crores on this account. This is an increase
of almost 30% over the base figure of Rs.20.3 crores (Provisional Accounts of 1997-98) and
is, therefore, unacceptable. The increase in cost is to be limited to the annual inflation
rate over the base year. Accordingly, a figure of Rs.21.49 crores for the year 1998-99 is
approved out of which Rs.10.25 crores has been apportioned to Distribution and Retail
Supply.
The incidence of both the Employee's Cost and
Administration General expenses taken together comes to 33.43 paise per Kwh as against the
all India average of 24.04 paise per Kwh. Gridco should improve its performance to achieve
the all India norms.
The share of expenditure on employees and A & G
taken together is 16.81% of the total cost as against All India Average of 12.91%
(Compiled upto 96-97).
(d) Expenses Capitalised : This is the portion of
employees cost, administration & general expenses, repair and maintenance expenses
allocated to capital. Gridco have proposed an amount of Rs.20.31 crores to be deducted
from revenue requirement. This figure is considered reasonable. Out of Rs.20.31 crores,
Rs.10.12 crores is apportioned to distribution and retail supply.
6.3 Interest on loans borrowed from approved
institutions : Gridco had originally proposed an amount of Rs.108.95 crores towards
payment of interest on long term loans which was subsequently revised to Rs.100.66 crores
after discussion and rectifications of some discrepancies. This needs to be further
revised to Rs.100.51 crores. This amount excludes Rs.57.53 crores charged towards interest
during construction. No penal interest has been assumed in interest calculation. The
average interest rate works out to 13.23% which is within the limit of Commercial Bank
rate. This interest does not include interest on Bond issued if any to Pension Trust Fund.
On the basis of the loan allocated to distribution and retail supply, the impact of
interest on distribution and retail supply works out at Rs.48.83 crores .
6.4 Bad Debt : Gridco have proposed an amount of
Rs.19.25 crores. The assumption underlying such projection has not been given. No basis
could be found either in the audited account or from Notes on Accounts for 1996-97 the
last year for which audit has been completed.
However, in the OSEB period, provision of reserve for
bad and doubtful debts was calculated at 10% of book debt against regular consumers and at
the rate of 100% of book debts against permanently disconnected consumers. Since the
amount due from permanently disconnected consumers was written off under the transfer
scheme, Gridco started with a clean slate. Therefore, it is presumed that all Book Debts
shown in Audited Accounts of Gridco are in respect of regular consumers. It may be
reasonable to keep a provision of upto 15% of differential between Gross book debt as on
31.3.98 & 31.3.99 as calculated below. This assumption of 15% is due to higher level
of sales, a figure which was considered reasonable for the tariff of 1997-98.
The entire amount of bad debt amounting Rs.19.25 crores
is allocated to retail supply as there is remote chance of there being any bad debt at
transmission end.
|
|
Rs. in crores
|
1
|
Amount of Gross Book debt as on 31.3.98
(Ref Retail Tariff clarification)
|
1051.7
|
2
|
Amount of Gross Book debt as on 31.3.99
|
1213.0
|
3
|
Increase in Book debt (2-1)
|
161.3
|
4
|
Provision @ 15% as adopted by the Commission
|
24.15
|
5
|
Gridco proposal
|
19.25
|
6.5 Depreciation : Gridco have proposed an
amount of Rs.148.56 crores towards depreciation in their tariff application for both
transmission and retail supply. This has been calculated as per principles contained in
Ministry of Power (Deptt. of Power) Notification No.265 (E) dt.29.03.94. Asset wise
classification and depreciation applicable there on have been given. The fixed asset
details given upto 31.03.97 in tariff filing are in agreement with the audited accounts
for 1996-97. For other years i.e. 97-98 & 98-99 amount of fixed assets given in RT.9
are in agreement with the figures shown in capital expenditure details (RTCL-11).
After detailed examination, the Commission accepts
Rs.147.58 crores towards depreciation out of which Rs.77.50 crores is allocated to
Distribution and Retail Supply.
6.6 Contribution to Contingency Reserve : Gridco
have provided Rs.8.1 crores towards contribution to contingency reserve under Para-IV of
the Schedule-VI of Electricity (Supply) Act 1948. As per provision of Para-IV of the
Schedule-VI such contingency reserve should have a minimum value of one quarter of one
percent and maximum value of one half of one percentum of the asset value. Applying this
principle on the asset value of Rs.1024.17 crores allocated for distribution and retail
supply, the Contingency Reserve of Rs.3.84 crores claimed by Gridco within the maximum and
minimum limit is considered reasonable and, therefore, accepted.
6.7 Based on the above observations and keeping
in view of the requirements of the Electricity (Supply) Act, 1948 and section 26(4) of the OER Act, 1995,
the expenditure requirement of the licensee in respect of Retail Supply work out to
Rs.1693.67 crores as tabulated in Annex-A.
|
7.0 REASONABLE
RETURN
7.1 Calculation of Capital Base : On
examining the Capital Base calculation of Gridco, we find it necessary to indicate our
findings only on important items and items in which Commission is adopting a different
figure than projected by Gridco.
7.2 Original cost of fixed assets :
The cost of fixed assets finds its origin from Transfer Scheme Resolution dt. 01.04.96
shown at Rs.1975.70 crores. Information on block capital is shown in appendix RT-6. The
figure as on 31.3.97 amounting Rs.2064.99 crores is in agreement with the balance as shown
in the audited balance sheet of 1996-97. Gridco have estimated capital addition of
Rs.96.32 crores for the year 1997-98 and Rs.425.31 crores for the 1998-99. Accordingly,
original cost of fixed assets as on 31.3.98 and 31.3.99 has been projected as Rs.2161.32
crores and Rs.2586.63 crores respectively. As segregated by the licensee, asset value of
Rs.1124.81 crores has been allocated to Distribution and Retail Supply business.
Commission accepts the amount for the purpose of calculation of capital base.
7.3 Original cost of
work-in-progress : Original cost of the work-in-progress has been taken from the
project wise capital expenditure statement (RT-7) submitted by Gridco and is accepted.
This includes a portion of interest capitalised pertaining to the period of construction.
Out of Rs.399.45 crores, an amount of Rs.154.18 crores belongs to Retail Supply business.
7.4 Investment in
"Contingencies Reserve" Account : 'Capital base' should include the amount
of investment compulsorily made under para IV of Schedule VI. No investment has been made
in this account and even the amount of Rs.7.5 crores permitted in last tariff order has
not been invested. Hence there shall be no such component in the capital base.
7.5 Working Capital :
-
Average cost of stores : As per Para XVII(e)(i)
of Schedule VI to Electricity (Supply) Act, 1948, an amount on account of working capital
equal to sum of i) one-twelfth of the sum of book cost of stores material and supplies
including fuel on hand at the end of each month of the year of account should be included
in calculating capital base. Gridco have proposed Rs.136.37 crores on this account. This
is almost 20 months consumption considering the material cost of Rs.75.60 crores annually.
In a reply to the Commission's query, Gridco stated that increase in the ratio of stores
to expenditure on R & M material is due to anticipated inflow of stock under
multilateral and bilateral line of credit. To support their statement Gridco have not come
up with any concrete proposal for treatment of the excess stock. During discussion, Gridco
clarified that their average lead time for procurement is three months. Stores on the
basis of three months consumption is considered reasonable. Accordingly, Rs.18.91 crores
is taken towards average cost of stores instead of Rs.136.37 crores shown for the purpose
of capital base calculation for transmission and distribution taken together. Out of this,
a sum of Rs.14.57 crores is allocated to Retail Supply business, considering three months
consumption.
-
Average cash & bank balance : According to in
Para XVII(1)(e)(ii) of Schedule-VI, an amount equal to 1/12 of the sum of cash & Bank
Balances is to be considered on account of working capital on certain conditions.
The fund requirement for two months payment of employees
cost and administrative and general expenses would be appropriate for meeting working
capital requirement. Hence instead of taking 1/12 of the sum of cash of bank balance at
the end of each month of the year of account, a lower amount of Rs.36.07 crores is
considered reasonable for the purpose of working capital in respect of Retail Supply
business.
7.6 Loans and debentures :
Amount of loan pertaining to retail supply business amounting Rs.500.12 is considered
acceptable for deduction for the purpose of calculation of capital base. (RT-8). No
debentures have been issued. But in consonance with the transfer scheme and subsequent
division between Transmission and Bulk Supply and Distribution and Retail Supply
businesses, Rs.400 crores of Zero Coupon Bond and Rs.30 crores of Pension Trust Bond has
been allocated by Gridco to Transmission business. Balance of Rs.120 crores pertaining to
Pension Trust Bond is allocated to Retail Supply business. But these amounts are long term
liability of the licensee and are in effect loans in terms of (ii-a) of XVII(i) of the
Schedule VI. Hence the amount of Rs.120 crores has to be deducted for calculation of
capital base. However, this amount does not qualify for reasonable return.
7.7 Calculation of Reasonable Return
: Reasonable Return as defined in Para XVII(9) of Schedule VI means :- in respect of
any year of account the sum of following :
(a) the amount found by applying standard rate to the
Capital Base.
(b) the income derived from investment other than those
included in capital base.
(c) the amount equal to 1/2 of one percentum on any
loans advanced by Board.
(c-1) an amount equal to 1/2 of one percentum on amounts
borrowed from organisations of institutions approved by State Govt.
(c-2) an amount equal to 1/2 of one percentum on the
amounts realised by issue of debentures.
(d) an amount equal to 1/2 of one percentum on
accumulation in development reserve created by Central Govt.
(e) such other amount
Out of above, only items (a) and (c-1) are applicable in
case of Gridco. The licensee has arrived at the figure of reasonable return by multiplying
standard rate of 15.5% to capital base. As per the provision of Schedule Six of the
Electricity Supply Act, 1948, the licensee is also entitled to get ½% on the amount
borrowed from the organisation or institution approved by the State Govt. as part of
reasonable return. Thus ½% of total loan of Rs.500.12 crores amounting Rs.2.5 crores can
be included while calculating reasonable return.
7.8 The calculation of reasonable
return works out as follows (detailed calculation is given at Annex-B
to this order) :
Standard rate of 15.5% on capital base of Rs.166.10 crores
|
Rs.25.75 crores
|
1/2% on loan borrowed from the approved institution i.e.
Rs.500.12 crores
|
Rs.2.50 crores
|
Total |
Rs.28.25 crores
|
8.0 MISCELLANEOUS
RECEIPT
8.1 The licensee has proposed
miscellaneous receipt of Rs.47.5 Crores for 1998-99 as follows:
Miscellaneous receipt from consumers
|
Rs.1.00 Crore
|
Delayed payment surcharge
|
Rs.36.00 Crores
|
Other income(house rent, hire charges tender paper etc.)
|
Rs.4.50 Crores
|
Meter rent
|
Rs.6.00 Crores
|
Total
|
Rs.47.50 Crores
|
8.2 Miscellaneous
receipt from consumers amounting Rs.1.00 Crores is accepted. Amount claimed by GRIDCO in
respect of Delayed payment surcharge is accepted. As per Audited Annual Accounts of GRIDCO
for 96-97 the figures shown under DPS amounts to Rs.32.98 Crores. Considering higher
volume of sale for 98-99, the figure of Rs.36.00 Crores assumed by GRIDCO is considered
reasonable. Other incomes of Rs.4.50 Crores shown by GRIDCO is on lower side in comparison
to audited figure of the accounts of 96-97. The Commission considers Rs.5.58 Crores as a
more reasonable estimate. Gridco have estimated meter rent as Rs.6.00 Crores for 1998-99.
As per audited annual accounts for the financial year 1996-97 the meter rent amounts to
Rs.4.27 Crores. The Commission has approved meter rents to the effective from 1.12.98.
Therefore estimate of Rs.6 crores for 1998-99 is acceptable.
8.3 To sum up, Commission estimates
miscellaneous receipt of Rs.48.58 Crores as against Rs.47.5 Crores proposed by the
Licensee.
9.0 SUBSIDY
It is understood that OSEB was claiming subsidy under
the following heads :
-
Rural Electrification Operation.
-
Industrial Policy Resolution.
-
Energisation of lift irrigation points.
GRIDCO have not claimed any amount towards subsidy in
their tariff application. No policy directive under Section
12(3) of the Act, 1995 has been issued by the Govt. of Orissa
with commitment to grant subsidy. Hence no subsidy element can be built into tariff for
1998-99. However, in a note to their Retail Tariff application, GRIDCO has stated that it
has not received any subsidy since its incorporation. An amount of Rs.198.1 Crores stands
receivable from Govt. of Orissa, as per details given below :
Supply of power to EOU at NTPC rates(1996-97)
|
Rs.42.49
|
IPR subsidy (1997-98)
|
Rs.22.87
|
Receivable against BIFR award of consumers
|
Rs.15.05
|
Subsidy against Sec.59 of Electricity (Supply) Act, 1948
|
Rs.68.78
|
Electricity duty of Govt. Dept. on 1.4.96
|
Rs.04.41
|
Capital subsidy for L I paid
|
Rs.44.50
|
|
Rs.198.10
|
9.3 We are unable to
comment on the position of subsidy receiveable because Gridco has not produced before us
any evidence to substantiate that the subsidy receivable is attributable to loss incurred
in complying with the Govt. policy directives and instructions issued by the Govt. of
Orissa. Gridco will have to take up the matter with the Govt. of Orissa.
10.0 TRANSMISSION & DISTRIBUTION LOSS
10.1 The documents filed by Gridco
indicate that the total loss rate for the system (sum of technical and non-technical
losses) for the period 1st April,1997 to 31st March, 1998 was approximately 46.6% of the
energy injected into the Gridco system. This level stands in contrast to the historic
levels as reported to various agencies by the OSEB and to the indication this Commission
received from Gridco in its previous tariff filing that losses for the period ending 31st
March, 1998 would be restricted to a level of 42%. In that proceeding, this Commission did
not find persuasive support for Gridco's position that customers should bear the costs of
this higher level of losses since it is difficult to describe operating at such levels as
efficient and determined that 35% was a more reasonable loss level.
10.2 That decision was the result of
the process that this Commission continually employs as it carries out its functions,
namely balancing the interests of the licensee with those of its customers. We know that
we must set tariffs that allow the licensee a reasonable opportunity to earn revenues that
are sufficient for operating, maintaining, rehabilitating and expanding the system to
provide a proper quality of service. However, we must also not force customers to pay for
inefficient licensee behaviour. We must carry out the same balancing in this proceeding.
10.3 Gridco has based its current
filing on a proposal to reduce its total loss rate for the system from 46.6% to 41%.
However, we are far from convinced that Gridco has been efficient in reducing losses thus
far, and we find little in the record to assure us that Gridco will succeed in achieving
its target. Rather, it is equally likely that Gridco will repeat its poor performance of
past years and once again discover that its losses are higher than either the level it
estimated previously or that it has committed to meet. Further, we remain convinced that
it is unreasonable to expect consumers to bear the burden of system losses that result
from Gridco's inefficiency and mismanagement in this area and for tariff purposes will
maintain the level that we accepted for the existing tariffs.
10.4 Nevertheless, as we stated in the tariff concept
paper, we are willing to consider some measures of performance based tariff design.
Accordingly, we consider it pragmatic to treat the amount of difference between the
revenue requirement calculated on the basis of Gridco's estimated T&D loss of 41% and
the revenue requirement calculated on the basis of the reasonable level of 35% as has been
determined by us as a special category of capital. This amount with RBI rate of interest
will be considered for inclusion in the revenue requirement for tariff purposes only when
Gridco or its successor licensees produce evidence of having reduced T&D losses to the
level of 35% which for us is a benchmark. If Gridco or its successor licensees are able to
reduce the T&D losses below the benchmark level of 35%, we will also consider, in line
with our approach outlined in our tariff concept paper, to increase the return from the
existing level by one percentage point for every percentage decrease in the T&D
losses. While providing an incentive to Gridco or its successor licensee to reduce T&D
losses, we hope that its fruits will be passed on to the consumers in general.
|
11.0 DETERMINATION OF TARIFF
11.1 Over the years, a tariff structure
has developed keeping in view the nature and purpose of supply as mentioned in Section 49
of the Electricity (Supply) Act, 1948. The endeavour of the government to accommodate many
socio-political objectives of the state in the tariff design and utility mangement has led
to inefficiency, inequity and sickness of the utility. In the process, certain categories
of consumers have been paying a small part of the cost of their supply and enjoying a high
degree of subsidy. On the other hand, some other consumer categories have been charged at
a rate higher than the cost of supply. Cross-subsidy within the electrical utility without
balancing the overall revenue-cost of the utility has often led to a revenue deficit and
sapping of the generation of investible resources. With the reform of electricity
industry, an attempt is being made now to gradually change over to a cost-based tariff to
promote end-use efficiency and make the utility economically viable.
11.2 During the tariff hearing, many
HT/EHT industries pleaded for a tariff structure which would reflect the cost of supply
and reduce the burden of cross-subsidy they carry so as to make their products competitive
in the market. They also pointed out that the policy of charging them much in excess of
their cost of supply makes it economical for them to switch over to captive power plants.
11.3 It was a universal demand on the
part of domestic consumers that the tariff in respect of domestic consumers should not be
fixed at a high rate as they were not in a position to bear any additional burden on their
consumption and they were not able to pass on the additional burden to others like the
industrial and commercial consumers. The Small & Medium Industries pleaded for a
tariff lower than the cost of supply to retain themselves in the business. Their
submission was that without cross-subsidy, they would go out of business. The investors on
the other hand want a tariff structure that ensures for them a reasonable return on their
investment.
11.4 The Commission has the difficult
task of balancing the needs of various user-groups with conflicting interests. The
Commission has to keep in view the objective of the Reform Act that
it should lead to the development and management of the electricity industry in the State
in an efficient, economic and competitive manner.
11.5 Taking into account all aspects of
licensees tariff filing and the representations and submissions made by the objectors
during the proceeding as also the views expressed in the meeting of the Commission
Advisory Committee we find it appropriate to redetermine tariff and the charges to be
realised by Gridco. Charges and treatment for various categories are given in the
succeeding paragraphs of this order. We direct that these are made effective from 1st
December, 1998 after publication in accordance with Section
26(5) of the Reform Act, 1995.
11.6 The proposal of Gridco contains
suggestion for unbundling of the tariff to distinguish between the various functions
undertaken by the utility. Separate charges have been proposed for separate activities :
(i) Customer service charge to recover the following :
(a) maintenance of meter
(b) meter reading
(c) preparation of bills
(d) delivery of bills
(e) collection of revenue
(f) maintenance of customer accounts.
(ii) Demand charge to meet a component of the fixed cost
incurred in the system for meeting the consumers' load.
(iii) Energy charge reflecting the variable cost of
power purchase.
11.7 Customer Charge
Gridco have proposed a Customer Service Charge as in the following table :
Customer category
|
Proposed CSS
Rs./month
|
Present meter
rent Rs./month
|
Rebate for own
meter Rs./month
|
EHT
|
1500
|
2100
|
Nil
|
Railway Traction
|
2000
|
2750
|
Nil
|
HT Customers
|
500
|
1275
|
Nil
|
LT 3 Phase
|
105
|
105
|
75
|
LT 1 Phase
|
15
|
15
|
10
|
11.8 There is convincing
logic in the proposal to realise the fixed monthly minimum charge from all types of
consumers to cover fixed cost of the licensee other than those covered under demand and
energy charges. The cost component of items covered as suggested by Gridco have been
looked into and it is considered desirable to exclude meter rent. This is due to the fact
that the consumer has the option to supply his own meter, in which case he shall not be
liable to pay meter rent. The Commission accepts the proposal of Gridco to have charges on
all categories of consumers based on (a) demand (b) energy (c) a fixed monthly minimum
charges, & (d) meter rent. However, in case of consumers with contract demand of less
than 110 KVA, the monthly minimum fixed charge will cover the demand as well as the
monthly customer charge.
11.9 However, customer charge may be
levied in respect of consumers with connected load of 110 KVA and above as in the
following table :
11.10 Customer
Charge for Consumers with connected load 110 KVA or above:
Category |
Energy
supplied |
Customer
charge/per month
(in Rupees) |
Public Water Works |
LT
|
30
|
General Purpose
|
LT
|
30
|
Large Industry
|
LT
|
30
|
Bulk Supply(Domestic)
|
HT
|
250
|
Irrigation
|
HT
|
250
|
Public Institution
|
HT
|
250
|
Commercial HT
|
HT
|
250
|
Medium Industry |
HT
|
250
|
General Purpose
|
HT
|
250
|
Public Water Works |
HT
|
250
|
Large Industry
|
HT
|
250
|
Power Intensive |
HT
|
250
|
Mini Steel Plant
|
HT
|
250
|
Railway Traction
|
HT
|
250
|
General Purpose |
EHT
|
700
|
Large Industry
|
EHT
|
700
|
Railway Traction
|
EHT
|
700
|
Heavy Industry
|
EHT
|
700
|
Power Intensive Industry
|
EHT
|
700
|
Mini Steel Plant
|
EHT
|
700
|
Emergency supply to
|
Captive Power Plants
|
EHT
|
700
|
Colony Consumption |
EHT
|
700
|
11.11 Demand Charge
for Consumers with contract demand of less than 110 KVA:
This is a well accepted principle that a utility's cost comprises a fixed component
relating to demand and a variable component relating to energy supplied. In fact, demand
charge is a standard recovery from consumers with contract demand of 110 KVA and higher.
Demand charge is not levied on consumers with contract demand lower than 110 KVA as demand
metering is not provided in such cases in the interest of economy. However, it will be
appropriate to recover this component of the fixed cost from consumers with contract
demand of less than 110 KVA. Also this charge being fixed in nature can be combined with
the customer charge for simplicity. With the introduction of this fixed charge, the
existing practice of minimum energy charge for specified consumer categories should be
withdrawn. Taking all these factors into consideration, the Commission has decided that a
monthly minimum fixed charge shall be payable by consumers having contract demand of less
than 110 KVA according to the scale below :
Consumer Category
|
Monthly minimum fixed
charge
|
1. Domestic :
|
Rs.20 for the first KW or part
thereof contract demand per month.
Rs.10 per month for each additional KW or part thereof contract demand.
|
Kutir Jyoti :
|
Rs.30 per month inclusive of all
charges.
|
2. Commercial :
|
Rs.30 per
KW/month for the first KW or part thereof contract demand.
Rs.20 per month for each additional KW or part thereof contract demand. |
3. Irrigation :
|
Rs.20 per
month for the first KW of connected load or part there of.
Rs.10 per month for each additional KW of connected load or part there of. |
4. Street Lighting :
|
Rs.20 per month for the first KW
of connected load or part there of.
Rs.10 per month for each additional KW or part there of.
|
5. Small Industries :
|
Rs.40 per month for first KW of
connected load or part there of.
Rs.30 per month for each additional KW or part there of.
|
6. Medium Industries :
|
Rs.80 per month for first KW of
connected load or part there of.
Rs.50 per month for each additional KW of connected load or part there of.
|
7. Public Institution :
|
Rs.80 per month for first KW of
connected load or part there of.
Rs.50 per month for each additional KW of connected load or part there of.
|
8. Public Water Works :
(less than 110 KVA)
|
Rs.80 per month for first KW of
connected load or part there of.
Rs.50 per KW/month for each additional KW of connected load or part there of.
|
11.12 Demand Charge for
Consumer with Contract Demand of 110 KVA and above :
The proposal of Gridco is to increase the existing demand charge from Rs.200/KVA/month to
Rs.300/KVA/month for all consumers with contract demand of 110 KVA and above. Gridco have
observed that such increase in demand charges would allow upfront recovery of fixed
expenses and would give a clear signal about the proposed "Availability Tariff"
of Central Sector Thermal Power Stations, which may increase the fixed cost liability of
Gridco. There was objections from all affected groups to this increase. The Commission
considered the following aspects in deciding this matter.
-
Gridco have estimated revenue from demand charges using a factor of 82%
of the sum of contract demands. From the figures furnished by Gridco for a period of six
months from 01.10.97 to 31.03.98, the above factor works out to about 90%, thus enabling
Gridco to recover higher revenue from demand charge.
-
The system load factor of Gridco is about 67% implying that 67% of the
fixed cost can be recovered through energy charges. Thus, 33% of fixed cost is to be
recovered through demand charge. On this basis, the Commission have separately approved
the demand charge of Rs.200/KVA/month in the bulk supply tariff.
-
Commission also took into account the demand charge prevailing in other
utilities in the country. High demand charge may motivate large consumers to set up their
own Captive Plants.
11.13 Keeping all these factors in
view, the Commission has decided not to change the present level of Demand Charge of
Rs.200/ KVA per month for all consumers with contract demand of 110 KVA and above.
11.14 Consumers with contract demand
110 KVA and above are required to pay a demand charge on the basis of maximum demand
recorded or 80% of contract demand whichever is higher. The revenue from consumers with
contract demand of 110 KVA and above has been calculated by Gridco by multiplying the
proposed rate by 82% of the contract demand expressed in KVA. The factor of 82% has been
arrived at by Gridco on the basis of recorded maximum demand and contract demand for the
period of Oct'97 to Mar'98 as given at page 4/10 of the clarification on retail tariff
application 98-99, for consumer categories of General Purpose, Large Industry, Heavy
Industry, Mini Steel Plant, Public Water Works, Power Intensive Industry and Railway
Traction.
11.15 The Commission has examined the
billing details of consumers liable to pay demand charge. Apart from the categories of
consumers mentioned above there are consumers belonging to other categories also with
contact demand of 110 KVA and above, who also pay demand charge. These have also been
taken into consideration.
11.16 Where the recorded demand is less
than 80% of the contact demand, the revenue from demand charge is calculated on the basis
of the demand charge realization of at least 80% and in case where the recorded maximum
demand is more then 80%, the demand charge is calculated on the basis of actual demand
recorded. Month wise contract demand, recorded maximum demand and evaluated billing demand
are indicated in the table, below for the period of six months from 10/97 to 3/98 as
furnished by Gridco :-
Date
|
Cd(KVA)
|
MD(Recorded)
|
|
MD(Billing Demand)
|
Billing Demand
|
10/97
|
957680
|
717573
|
75.73%
|
875388
|
90.19%
|
11/97
|
1012254
|
918900
|
90.77%
|
906048
|
98.60%
|
12/97
|
1011803
|
713983
|
70.53%
|
90800
|
89.74%
|
1/98
|
1022679
|
753636
|
73.69%
|
945839
|
92.48%
|
2/98
|
1001747
|
716406
|
71.51%
|
883466
|
88.19%
|
3/98
|
999977
|
728171
|
72.81%
|
898288
|
89.83%
|
Average
|
|
|
75.73%
|
|
90.16%
|
11.17 Analysis of the
figures indicates that the billing demand is on an average 90% of the contract demand.
This factor has been accepted by the Commission as reasonable and the proposed factor of
82% for the calculation of revenue from demand charge by Gridco is an under estimation of
revenue. The Commission expects that in subsequent tariff proposals Gridco will work out
the factor for a period of 12 months to assess the demand charges accurately for these
categories of consumers, when this factor may be reviewed.
11.18 Revenue likely to be earned on
account of levy of demand charge has been shown separately in the calculation of expected
revenue from charges for the year 98-99.
11.19 As per the provisions of the
Regulation all consumers covered under two part tariff shall pay a penalty in case actual
maximum demand exceeds the contract demand. No distinction is made between the customers
who exceed the contract demand at off peak hours and those who over burden the system by
exceeding the contract demand at peak hours. Gridco have accordingly proposed that as the
customers exceeding the contract demand outside the peak hours actually help the system by
leveling the load shape, no penalty should be levied on overdrawal outside the peak hours
up to a level of 120% of contract demand. Beyond this level, Gridco propose that a reduced
penalty of 1/4 (one fourth) of the existing penalty rate will apply. The existing rate of
penalty will continue for overdrawal at peak hours. The facility is proposed to be
extended only to industries drawing power in EHT system since TOD meters are in place for
this category at this time. Once TOD meters are put in place for industrial consumers at
HT, this facility will also be extended to them.
11.20 During the course of the hearing,
some of the objectors suggested that the overdrawal limit without penalty during off peak
hours may be totally removed or kept at 150% of contract demand without penalty. Allowing
an overdrawal limit during off peak hours to 150% of the contract demand may create
technical problems of over-loading of equipment. The overdrawal load limits of many of the
equipments being 20% Commission considers it reasonable to allow off peak drawal of power
to 120% of contract demand without penalty. Penalty at full rate shall apply for
overdrawals beyond this rate during off-peak hours.
11.21 Some objectors have questioned
the levy of demand charge at a minimum of 80% of Contract Demand. It has been suggested by
some objectors that demand charge should be levied on the average actual demand of the
consumer. The basis of levying demand charge subject to a minimum of 80% of the contract
demand is to ensure the recovery of minimum fixed costs for the installed facility.
Commission therefore does not consider it appropriate to make any change in the present
system of levying a demand charge at a minimum of 80% of the contract demand.
11.22 Energy Charge :
The energy charge paid by the consumer may be variable in nature and is dependent on the
quantum of power consumed by each individual consumer. Keeping in view the objective of
gradual change over to the system of cost-based tariff, the Commission considers it
appropriate to relate energy charge to the voltage of supply to reflect the associated
cost.
11.23 There is a practice of imposing a
surcharge/ rebate for supply at a voltage other than the voltage for which tariff was
fixed. With the introduction of tariff related to voltage of supply, it is not necessary
to continue with the levy of surcharge for different voltage levels. The Commission has
decided to adopt the following tariff structure for all loads of 110 KVA and above :-
Voltage of supply
|
Demand Charge
|
Energy Charge
|
L.T.
|
Rs.200/- per KVA
|
270 paise/unit
|
H.T.
|
Rs.200/- per KVA
|
260 paise/unit
|
E.H.T.
|
Rs.200/- per KVA
|
250 paise/unit
|
However, H.T. & E.H.T. consumers will
be charged at the rate of 200 paise/unit & 180 paise/unit respectively towards energy
charge for all consumptions in excess of 60% load factor calculated on contract demand.
11.24 The Commission has made several
exceptions to the above uniform tariff structure to insulate consumers from a steep rise
in tariffs. Tariff for consumers in the Domestic Category has been kept well below the
normative level. The same consideration has been adopted for Small Scale Industries,
Street Lighting and Public Institutions. Mini Steel Plant consumers will pay energy charge
of 240 paise/unit both at H.T. and E.H.T. supply with incentive as aforesaid for
consumption in excess of 60% load factor calculated on contract demand. Similarly, Public
Institutions comprising schools, colleges and hospitals will pay less than what would have
been payable by them according to the voltage of supply.
11.25 INCENTIVE FOR H.T. &
E.H.T. CONSUMERS :
GRIDCO has reported that during last three years, permission has been granted to a number
of industries to set up captive power plants with a total capacity of 2022 MW. These
permissions have been granted to the existing consumers of GRIDCO as well as to new
industries yet to come up. All these industries receive power either at HT or
EHT.
11.26 In order to provide adequate
incentive to the Power Intensive industries not to switch over from the GRIDCO's system in
favour of captive power plants, GRIDCO have proposed an incentive tariff to be made
applicable only to a selected group of power intensive industries. The proposed tariff is
lower than the tariff applicable to other industries in the same category as well as other
EHT consumers.
11.27 In the Tariff Concept Paper, the
Commission had stated that tariff should gradually be based on voltage of supply rather
than on the nature and purpose of supply. Further the Commission appreciates the
desirability of retaining industries as consumers and encourage new industries to become
consumers of the Distribution Licensee.
11.28 The Commission, therefore,
decides that incentive tariff may not only be introduced but such incentive should also be
available to industries other than the Power Intensive Industries. Those consumers who are
availing power supply at HT or EHT and are maintaining load factor above 60% should be
given incentive in the form of lower energy charges in respect of consumption beyond 60%
load factor. Accordingly the Commission has decided that the HT industries maintaining a
load factor above 60% calculated on the contract demand will be charged at the rate of 200
paise per unit for all consumption in excess of the consumption beyond the load factor of
60%. Similarly EHT consumers attaining a load factor above 60% calculated on the contract
demand will be charged at the rate of 180 paise/unit for all consumption in excess of load
factor of 60%. This tariff shall be applicable for the power consumed from GRIDCO source
only.
11.29 Adoption of load factor for
consumers with defective meter and without meter :
The Commission considered the proposal submitted by GRIDCO to revise the load factor in
respect of domestic and commercial consumers with defective meters and with unmetered
supply.
11.30 The Commission is seriously concerned about the
high commercial loss of Gridco and the imperative need to tackle the problems of theft,
abstraction and unauthorised consumption of energy. At the same time load factor billing
cannot continue as the sole instrument to meet Gridco's target of energy sale.
Rectification of defective meters and installation of meters in place of unmetered supply
has to be the central focus of Gridco's commercial strategy.
11.31 In addition, loss occurring in
the system due to theft of electricity directly from overhead distribution lines is also
causing commercial loss in the system. Priority should be given for replacement of meters
of consumers with three phase supply, consumers in the commercial category & other
large loads with single phase supply. The Commission directs Gridco to submit at the end
of each quarter the following information :
(i) improvements in rectification, replacement and installation of meters.
(ii) Measures taken for eradication of unauthorised tapping from the overhead distribution
lines.
11.32 At present assessment of
consumption in respect of domestic consumers is being done assuming the load factor of
15%. Similarly, for commercial consumers 20% load factor is used. Consumers covered under
small industries category are billed at a load factor of 15%. In case of irrigation
category for the period of June to October, a load factor of 8% is used and for the month
of November to May, a load factor of 15% is used.
11.33 The proposal of Gridco for
increase in the load factor for unmetered supply or defective meter is given below :
Domestic Consumers :
Upto 1 KW
|
-
|
55%
|
> 1 KW upto 2 KW
|
-
|
50%
|
> 2 KW upto 3 KW
|
-
|
45%
|
> 3 KW
|
-
|
40%
|
Commercial Consumers:
Upto 1 KW
|
-
|
55%
|
> 1 KW upto 2 KW
|
-
|
50%
|
> 2 KW upto 3 KW
|
-
|
45%
|
> 3 KW
|
-
|
40%
|
11.34 Field studies
conducted by Gridco reveal that energy consumed or physically drawn by consumers is
substantially more than that estimated through load factor criterion of 15% and 20%
presently in use for domestic and commercial consumers respectively. The Commission have
decided to raise the load factor in respect of Domestic category from 15% to 20% and for
Commercial category from 20% to 30%. The Commission also examined the present load factor
of consumers in Small Industries, and Irrigation and have decided that the present level
of load factor should continue.
11.35 The Commission's approval of
enhanced load factor will be reviewed from time to time. If the Commission comes to the
conclusion that the Distribution and Retail Supply Licensee has not taken effective steps
in metering and has sought to depend on load factor billing to increase sale of energy, it
will consider revising the load factor downwards.
|
12.0 Tariff
applicable for the consumers with connected load of less than 110 KVA
12.1 Domestic :
The majority of electricity consumers in Orissa are in Domestic category who enjoy a
high degree of subsidy in tariff.
(a) The existing tariff for Domestic category for supply
at 230/400 V is given below:
i) For the total monthly consumption not exceeding 30
units : 90 paise/kwh.
ii) For the total monthly consumption exceeding 30 units
:
First 75 units 105 paise per unit
Next 75 unit 150 paise per unit
Balance units 220 paise per unit
iii) For supply at 11/33 KV - energy charge 150 paise
per unit.
iv) The calculation of monthly minimum energy charge is
based on 22 units for half KW of contract demand or part thereof.
v) In case of unmetered or defective meter, energy
consumption is assessed and billed using the load factor of 15% on contract demand.
vi) A prompt payment rebate of 10 paise per unit is
allowed if payment of the bill is made in full within 15 days of the date of the bill.
(b) The Commission examined the existing tariff
structure for this category with particular reference to Gridco's proposal to have a
uniform rate instead of the existing slab rate. On balance of consideration to gradually
decrease subsidy and yet facilitate use of electricity by small consumers, the Commission
has decided to retain the slab system but rationalise it. The revised energy charge for
supply at 230/400 V shall be as under.
i) Kutir Jyoti Consumers - Rs.30.00 per month.
ii) In case of other Domestic consumers on the total
monthly consumption:
First 100 Units - 120 paise per unit
Next 100 units - 170 paise per unit
Balance units of consumption - 245 paise per unit
iii) The present practice of a monthly minimum energy
charge will cease with effect from the date of implementation of the new tariff.
iv) The Commission has decided to fix a monthly minimum
fixed charge at the rate of Rs.20 for the first KW of contract demand or part there of.
This charge will be enhanced at the rate of Rs.10 per KW per month for each additional KW
or part thereof.
v) In case of unmetered supply or defective meter, the
energy consumption shall be assessed and billed using a load factor of 20% on the contract
demand. For this purpose, the connected load of less than 0.5 KW shall be treated as 0.5
KW.
vi) For supply at 11/33 KV the energy charge shall be
payable at the rate of 160 paise/Kwh. The monthly demand charge for domestic consumers
availing power supply at HT shall be at the rate of Rs.10 per Kw per month.
vii) HT customers will pay a customer service charge of
Rs.250 per customer per month.
viii) The practice of prompt payment rebate of 10
paise/unit shall continue.
12.2 Commercial
(a) The existing tariff for the consumers covered under commercial category is given below
:-
For power supply at 230/400/1100 V :-
i) for all units if the consumption does not exceeds 100 units per month - 245 paise per
unit.
ii) for all units if the consumption exceeds 100 units
per month but upto 300 units-290 per unit.
iii) for all units if the consumption exceeds 300 units
per month-320 paise per unit.
iv) Monthly minimum energy is calculated at the rate of
23 unit for half KW of contract demand or part there of.
v) In case of unmetered supply or defective meter,
energy consumption shall be assessed and billed using the load factor of 20% of the
contract demand.
(b) The Commission reviewed the existing tariff
structure and decided the following:-
i) For the total monthly consumption :-
First 100 units - 270 paise/unit
Next 200 units - 360 paise/unit
Balance units - 410 paise/unit
ii) For supply at HT, the energy charge shall be 260
paise per unit.
iii) In case of unmetered supply or defective meter
energy consumption shall be assessed and billed using the load factor of 30% on the
contract demand. For this purpose the connected load of less than 0.5 KW shall be treated
as 0.5 KW. The present practice of prompt payment rebate shall continue. Minimum energy
charge for these categories of consumers will be discontinued with effect from the date of
implementation of this tariff.
iv) Monthly minimum fixed charge of Rs.30/- for the
first KW of contract demand per month shall be payable. This charge will go up at the rate
of Rs.20/- for each KW of contract demand or part there of.
12.3 Small Industry
The load factor shall be calculated @ 15% on the connected load in respect of these
consumers with defective meter and unmetered supplies for the purpose of assessment of
consumption and billing.
12.4 Irrigation
In respect of irrigation consumers for the months of June to October, a load factor of 8%
and for the month of November to May a load factor 15% shall be considered for assessment
of consumption and billing.
12.5 The rate of tariff as determined
above is reflected in Annex-D.
|
13.0 OTHER
CHARGES
The Commission also authorises levy of other charges as given below :
13.1 Demand Charge : The monthly
demand charge will be calculated on recorded/evaluated maximum demand or 80% of contract
demand whichever is higher.
13.2 Monthly Minimum Energy Charge :
The monthly minimum energy charge for categories of consumers for whom it is applicable
will be discontinued with effect from the date the new tariff comes into force.
13.3 Metering on LT side of
Consumers Transformer : Transformer loss computed as given below to be added to the
consumption as per meter reading.
Energy loss = 730 X KVA reading of the transformer/100.
Loss in demand = 1% of the reading of the transformer (for two part tariff)
13.4 Surcharge for supply at voltage
other than specified voltage shall not be applicable.
13.5 Delayed payment surcharge :
The Commission approves levy of delayed payment surcharge at the rate of 2% per month and
shall be levied prorata for the period of delay counted from the due date of payment
indicated on the bill in respect of the following categories of consumers.
i) Large Industries
ii) Medium Industries
iii) Public Water Works
iv) Railway Traction
v) Street lighting
vi) Power intensive Industries
vii) Heavy Industries
viii) General Purpose Supply
ix) Public Institutions
x) Mini Steel Plants
xi) Emergency supply to CPP
13.6 Power Factor Penalty : The
Commission approves the following :
A power factor penalty shall be added as a percentage of
monthly demand charges and energy charges as given below and shall be applicable to the
following categories of consumers.
i) Large Industries
ii) Public Water Works (110 KVA and above)
iii) Railway Traction
iv) Power Intensive Industries
v) Heavy Industries
vi) General Purpose Supply
vii) Public Institutions (110 KVA and above)
viii) Mini Steel Plants
ix) Emergency supply to CPP.
Rate of P.F. penalty :
i) 0.5 for every 1% falls from 90% upto and including 60%
plus
ii) 1% for every percentage fall below 60% upto and
including 30%
plus
iii) 2% for every 1% fall below 30%.
13.7 Penalty for overdrawal of power
above the contract demand : For maximum demand in excess of contract demand in a
month, a penalty at the prescribed rate of demand charge shall be imposed. However, in
case of EHT industries, no penalty would be imposed on overdrawal outside the peak hours
upto the level of 120% of the contract demand of the consumer. Beyond this level of 120%
of contract demand during off-peak hours, a penalty at the prescribed rate of demand
charge shall be added.
13.8 The existing rates of penalty will
continue for overdrawal at peak hours i.e. for maximum demand in excess of contract
demand, a penalty at the prescribed rate of demand charge shall be added.
13.9 Customer Charge : As
indicated in paragraph 11.10 above and also Annex-D.
13.10 Re-connection Charge :
Single Phase Domestic Consumer
|
Rs.30/-
|
Single Phase other consumer
|
Rs.50/-
|
3 Phase line
|
Rs.100/-
|
HT & EHT line
|
Rs.500/-
|
13.11 Temporary
connection charges : The existing practice should continue without any change.
13.12 New connection charges for LT
: Since the existing system of preparation of estimates causes delay in new
connections for prospective small consumers, for new connections upto and including 3 KW
load, there will be a flat charge of Rs.500/-. The existing practice of preparation of
estimate and payment of charge based on the estimated amount shall continue without any
change for connections above 3 KW load.
13.13 While the Commission finds it
logical to allow charges under a fuel surcharge formula, we have to indicate that the
formula shall be separately notified in the regulations.
13.14 Meter Rent : Monthly meter
rent shall be charged from consumers to whom meter has been supplied by the licensee
according to the following scale:
Meter
|
Rent in Rupees
|
1. Single phase electro-magnetic Kwh meter
|
15/-
|
2. Three phase
electro-magnetic Kwh meter |
30/-
|
3. Three phase electro-magnetic trivector
meter
|
800/-
|
4. Trivector meter for Railway Traction
|
800/-
|
5. Single phase Static Kwh meter
|
35/-
|
6. Three Phase Static Kwh meter
|
250/-
|
7. Three phase Static Trivector meter
|
800/-
|
8. Three phase Static Bivector meter
|
800/-
|
13.15 The revenue
requirement for 1998-99 submitted by the Gridco is modified to the extent indicated in
this order. It is estimated on the basis of tariff approved by us that the licensee shall
realise a total revenue of Rs.1725.95 crores for a full year implying a clear profit of
Rs.28.44 crores and "reasonable return" amounting to Rs.28.25 crores. Since the
new tariff shall be effective from 1st December, 1998. Gridco shall not be able to earn
clear profit during the current financial year.
13.16 For the financial year 1998-99,
it is estimated that Gridco is likely to incur a loss. This has partly arisen due to delay
in filing the tariff application. However, the actual loss to be incurred can be assessed
only on close of the financial year and Gridco may submit its claim in the revenue
requirement during the next tariff filing.
13.17 Gridco had submitted consolidated
as well as dis-aggregated revenue requirement in respect of all the four zones to which it
has restructured itself. While the Commission has noted the dis-aggregated figures as
given by Gridco, it is not in a position to confirm the dis-aggregated revenue
requirements. The capital base and the clear profit for the zones cannot be determined
before decision is taken on the licence applications filed by the four zonal distribution
companies.
The Commission orders that Gridco takes appropriate
action in pursuance of this order.
(S.C. MAHALIK)
CHAIRMAN
(A.R. MOHANTY)
MEMBER
(D.K. ROY)
MEMBER
|
Annexure - A
EXPENDITURE FOR THE FINANCIAL YEAR 1998-99
Commission's approval
Expenditure
Para XVII Clause-2(b) of Schedule VI of Elec.
(Supply)
Act 1948
|
Rs. in crores
|
I
|
Cost of Power
|
1084.88
|
|
Transmission cost
|
202.01
|
|
Reasonable return of Bulk Supply business
|
57.56
|
|
SUB TOTAL
|
1344.45
|
|
LESS
|
|
|
Revenue from wheeling & other misc. receipt
|
62.00
|
|
x
|
|
|
COST OF POWER FOR RETAIL SUPPLY
|
1282.45
|
II
|
Distribution & Sale of Energy
|
|
|
(a) Employees cost
|
207.22
|
|
(b) Material cost
|
58.29
|
|
(c) Admn. & General Expenses
|
10.25
|
III
|
Rents, rates and taxes other than all taxed on income & profits
|
(Included in A&G expenses)
|
|
IV
|
Interest on loans advanced by Gridco
|
48.83
|
|
(a) Interest on loan borrowed from organisation
|
|
|
(b) Interest on debenture issued by licensee
|
|
V
|
Interest on security deposit
|
|
VI
|
Legal charges
|
(Included in A&G expenses)
|
|
|
Less: Expenses capitalised
|
-10.12
|
VII
|
Bad Debt
|
19.25
|
VIII
|
Auditor's fees
|
(Included in A&G expenses)
|
|
IX
|
Management including managing agents remuneration
|
|
X
|
Depreciation
|
77.50
|
XI
|
Other expenses
|
|
XII
|
Contribution to P.F., Staff Pension, Gratuity
|
(Included in A&G expenses)
|
|
|
(a) Expenses on training & other training scheme
|
(Included in A&G expenses)
|
|
|
(b) Bonus
|
(Included in A&G expenses)
|
|
(Total Expenses I to XII) |
1693.67
|
|
Annexure - B
CALCULATION OF CAPITAL BASE AND REASONABLE RETURN FOR FINANCIAL
YEAR 1998-99
GRIDCO
|
Commission's approval |
[In accordance with para XVII of
Schedule VI of Electricity (Supply) Act, 1948] |
(Rs. In crores)
|
BULK
|
DISTCOS
|
GRIDCO
|
A.
|
(a) Original cost of fixed asset Less consumers contributtion
|
1461.82
|
1124.81
|
2586.63
|
Less Consumer Contributions
|
0.00
|
209.21
|
209.21
|
Sub-total
|
1461.82
|
915.60
|
2377.42
|
(b) Cost of intangible asset
|
0.00
|
0.00
|
0
|
(c) The original cost of Work in progress
|
245.27
|
154.19
|
399.45
|
(d) The amount of investment compulsorily made under para-IV
|
0.00
|
0.00
|
0
|
(e) An amount on account of working capital equal to the sum of:
|
|
|
|
(i) Average cost of stores (1/4th of the annual expenditure of materials)
|
4.34
|
14.57
|
18.91
|
(ii) Average cash and bank balance (1/6th of the sum of annual employees cost and adm
& general expenses)
|
11.64
|
36.07
|
47.71
|
Total of A:
|
1723.06
|
1120.43
|
2843.49
|
Less
|
B.
|
a) The amounts written off or set aside on account of depreciation of
fixed assets
|
197.29
|
223.42
|
420.71
|
b) The amount of any loan advanced by Board
|
761.88
|
500.12
|
1262.00
|
i) The amount of any loans borrowed from organisations or institutions approved by the
State Govt.
|
|
|
|
ii) The amount of any debenture issued by the licensee
|
|
|
|
c) The amounts deposited in cash with the licensee by consumers, by way of
security
|
430
|
120
|
550.00
|
d) The amount standing to credit of Tariffs and Dividends control reserve
at the beginning of the year of account
|
0.00
|
110.77
|
110.77
|
e) The amount standing to the credit of the Development reserve at the
close of the year
|
|
|
|
f) The amount carried forward (at the beginning of the year of accounting)
in the accounts of the Licensee for distribution to the consumers
|
|
|
|
Total of B:
|
1389.17
|
954.31
|
2343.48
|
Capital Base (A-B)
|
333.89
|
166.11
|
500.01
|
Reasonable return @ 15.5% on Capital Base
|
51.75
|
25.75
|
77.50
|
|
1/2% of THE LOAN BORROWED FROM INSTITUTION & BOND
|
5.81
|
2.50
|
8.31
|
TOTAL REASONABLE RETURN
|
57.56
|
28.25
|
85.81
|
Annexure - C
CALCULATION OF CLEAR PROFIT FOR A PERIOD OF TWELVE MONTH
AS PER THE SCHEDULE VI OF ELECTRICIY SUPPLY ACT, 1948
PARA - XVII (2)
Commission's approval
(Rs. In crores) |
(A)
|
Income derived from:
|
i)
|
Gross receipt from Sale of energy less discounts
applicable thereto
|
1677.37
|
ii)
|
Rental of meters and other miscellaneous Charges
|
48.58
|
iii)
|
Sale & repair of lamps & apparatus
|
|
iv)
|
Rents
|
|
v)
|
Transfer fees
|
|
vi)
|
Interest on investment
|
|
vii)
|
Other general receipts accountable for income
tax and arising from & ancilliary or incidental to business of electricity supply
|
|
|
Total of (A) (i to vii)
|
1725.95
|
|
(B)
|
Expenditure properly incurred on:
|
i)
|
Generation & purchase of electricity
|
1282.45
|
ii)
|
Distribution and sale of energy
|
|
|
a) Employees cost
|
207.22
|
|
b) Material
|
58.29
|
|
c) A & G expenses
|
10.25
|
iii)
|
Rents, rates & taxes, other than all taxed
on income & profit
|
Included in A & G expenses
|
iv)
|
Interest on loan advanced by Board
|
48.83
|
|
a) Interest on loan borrowed from
|
|
|
b) Interest on debenture issued by licensee
|
|
v)
|
Interest on security deposit
|
0.00
|
vi)
|
Legal charges
|
Included in A & G expenses
|
|
Less Expenses Capitalised
|
-10.12
|
vii)
|
Bad debts
|
19.25
|
viii)
|
Auditors fees
|
Included in A & G expenses
|
ix)
|
Management including managing agents
renumeration
|
0.00
|
x)
|
Depreciation
|
77.50
|
xi)
|
Other expenses
|
0.00
|
xii)
|
Contribution to P.F., staff pension and gratuity
|
Included in A & G expenses
|
|
a) Expenses on apprentice & other training
scheme
|
Included in A & G expenses
|
xiii)
|
Bonus
|
Included in A & G expenses
|
|
Total expenditure i.e. total of (B) (i
to xiii)
|
1693.67
|
|
(C)
|
Special appropriation to cover:
|
i)
|
Previous losses
|
0.00
|
ii)
|
All taxes on income and profits
|
0.00
|
iii)
|
Instalments of written down amounts in respect
of intangible asset and new capital issue expenses
|
0.00
|
iv)
|
Contribution to contingency reserve
|
3.84
|
v)
|
Contribution towards arrear depreciation
|
0.00
|
|
a) Contribution to Development Reserve.
(referred to in para)
|
|
|
b) Debt redemption obligation
|
|
vi)
|
Other special appropriation permitted by the
State Govt.
|
0.00
|
Total expenditure i.e. total of (C) (i to vi)
|
3.84
|
CLEAR PROFIT (A-B-C)
|
28.44
|
Reasonable Return (Form no. F 16)
|
28.25
|
Excess or deficit of clear profit over reasonable
return
|
0.19
|
Annexure - D
TARIFF EFFECTIVE FROM 1st DECEMBER, 1998
Sl. No.
|
Category
of
Consumers
|
Voltage of Supply
|
Demand Charge (Rs/KW)/ (Rs/KVA)
|
Energy Charge (P/KWh)"
|
Customer Charge (Rs/ Customer)
|
Monthly Minimum
Fixed Charge for first KW or part (Rs.)
|
Monthly Fixed Charge for any additional
KW or part
(Rs.)
|
Rebate (P/KWh)
|
LT Category
|
1.
|
Kutir Jyoti < 30U/month
|
200/400 V
|
FIXED MONTHLY CHARGE Rs. 30
|
|
|
2.
|
Domestic (Cons.<=100U/month)
|
200/400 V
|
|
120
|
|
20
|
10
|
10
|
Domestic (Cons.>100,<=200U/month)
|
200/400 V
|
|
170
|
|
20
|
10
|
10
|
Domestic (Cons.>200U/month
|
200/400 V
|
|
245
|
|
20
|
10
|
10
|
3.
|
Commercial (Cons.<=100U/month)
|
200/400 V
|
|
270
|
|
30
|
20
|
10
|
Commercial (Cons.>100,<=200U/month)
|
200/400 V
|
|
360
|
|
30
|
20
|
10
|
Commercial (Cons.>200U/month)
|
200/400 V
|
|
410
|
|
30
|
20
|
10
|
4.
|
Irrigation
|
200/400 V
|
|
90
|
|
20
|
10
|
10
|
5.
|
Street Lighting
|
200/400 V
|
|
245
|
|
20
|
10
|
DPS
|
6.
|
Small Industry
|
200/400 V
|
|
245
|
|
40
|
30
|
10
|
7.
|
Medium Industry
|
200/400 V
|
|
270
|
|
80
|
50
|
DPS
|
8.
|
Public Institution
|
200/400 V
|
|
245
|
|
80
|
50
|
DPS
|
9.
|
Public Water Works <100KW
|
200/400 V
|
|
270
|
|
80
|
50
|
DPS
|
10.
|
Public Water Works
|
200/400 V
|
200
|
270
|
30
|
|
|
DPS
|
11.
|
General Purpose
|
200/400 V
|
200
|
270
|
30
|
|
|
DPS
|
12.
|
Large Industry
|
200/400 V
|
200
|
270
|
30
|
|
|
DPS
|
|
HT Category
|
13.
|
Bulk Supply* - Domestic
|
11/33KV
|
10
|
160
|
250
|
|
|
10
|
14.
|
Irrigation*
|
11/33KV
|
30
|
80
|
250
|
|
|
10
|
15.
|
Public Institution*
|
11/33KV
|
50
|
240
|
250
|
|
|
DPS
|
16.
|
Commercial*
|
11/33KV
|
50
|
260
|
250
|
|
|
10
|
17.
|
Medium Industry*
|
11/33KV
|
50
|
260
|
250
|
|
|
DPS
|
18.
|
General Purpose
|
11/33KV
|
200
|
260
|
250
|
|
|
DPS
|
19.
|
Public Water Works
|
11/33KV
|
200
|
260
|
250
|
|
|
DPS
|
20.
|
Large Industry
|
11/33KV
|
200
|
260
|
250
|
|
|
DPS
|
21.
|
Power Intensive Industry
|
11/33KV
|
200
|
260
|
250
|
|
|
DPS
|
22.
|
Ministeel Plant
|
11/33KV
|
200
|
240
|
250
|
|
|
DPS
|
23.
|
Railway Traction
|
11/33KV
|
200
|
260
|
250
|
|
|
DPS
|
24.
|
Colony Consumption
|
11/33KV
|
|
160
|
|
|
|
DPS
|
|
EHT Category
|
25.
|
General Purpose
|
132KV
|
200
|
250
|
700
|
|
|
DPS |
26.
|
Large Industry
|
132KV
|
200
|
250
|
700
|
|
|
DPS |
27.
|
Railway Traction
|
132KV
|
200
|
250
|
700
|
|
|
DPS |
28.
|
Heavy Industry
|
132KV
|
200
|
250
|
700
|
|
|
DPS |
29.
|
Power Intensive Industry
|
132KV
|
200
|
250
|
700
|
|
|
DPS |
30.
|
Ministeel Plant
|
132KV
|
200
|
240
|
700
|
|
|
DPS |
31.
|
Emerg. Supply to CPP
|
132KV
|
|
350
|
700
|
|
|
DPS |
32.
|
Colony Consumption
|
132KV
|
|
160
|
700
|
|
|
DPS |
|
D.C.Services
|
|
RATE FOR D.C. SUPPLY
|
|
|
|
|
33.
|
Domestic
|
|
RATE AT SL. 2+25% SURCHARGE
|
|
|
10 |
34.
|
Commercial
|
|
RATE AT SL. 3+25% SURCHARGE
|
|
|
10 |
35.
|
Small Industry
|
|
RATE AT SL. 6+25% SURCHARGE
|
|
|
10 |
" EHT/HT consumers
consuming in excess of 60% Load Factor (L.F.) calculated on the Contract Demand shall pay
at the rate of 180p/KWh & 200p/KWh respectively for all consumption in excess of the
60% L.F..
|
|
Annexure - E
COMPARISON OF SALES PROPOSED BY GRIDCO AND APPROVED BY THE
COMMISSION FOR THE YEAR 1998-99
Sl. No. |
Category of Consumers |
Voltage of Supply |
1998-99
|
1998-99
|
Consumption (MU) Gridco's Proposal
|
Consumption (MU) Commission's Proposal
|
1
|
2
|
3
|
4
|
5
|
LT CATEGORY
|
1.
|
Kutir Jyoti
|
200/400 V
|
30
|
30
|
2.
|
Domestic
|
200/400 V
|
1995
|
2134.665
|
3.
|
Commercial
|
200/400 V
|
354
|
432.31
|
4.
|
Irrigation
|
200/400 V
|
197
|
236.857
|
5.
|
Street Lighting
|
200/400 V
|
31
|
31
|
6.
|
Small Industry
|
200/400 V
|
161
|
146.972
|
7.
|
Medium Industry
|
200/400 V
|
120
|
120
|
8.
|
Public Institution
|
200/400 V
|
41
|
41.3
|
9.
|
Public Water Works <100 KW
|
200/400 V
|
51
|
51
|
10.
|
Public Water Works
|
200/400 V
|
11
|
11
|
11.
|
General Purpose
|
200/400 V
|
12
|
11.6
|
12.
|
Large Industry
|
200/400 V
|
13
|
13
|
Total |
|
3016.30
|
3259.70
|
|
HT CATEGORY
|
13.
|
Bulk Supply - Domestic
|
11/33 KV
|
30
|
30
|
14.
|
Irrigation
|
11/33 KV
|
3
|
2.6
|
15.
|
Public Institution
|
11/33 KV
|
13
|
12.7
|
16.
|
Commercial
|
11/33 KV
|
0
|
0
|
17.
|
Medium Industry
|
11/33 KV
|
0
|
0
|
18.
|
General Purpose
|
11/33 KV
|
223
|
223.4
|
19.
|
Public Water Works
|
11/33 KV
|
38
|
38
|
20.
|
Large Industry
|
11/33 KV
|
806
|
806.5
|
21.
|
Power Intensive Industry
|
11/33 KV
|
218
|
218
|
22.
|
Ministeel Plant
|
11/33 KV
|
38
|
38
|
23.
|
Railway Traction
|
11/33 KV
|
42
|
42
|
Total |
|
1410.7
|
1411.2
|
|
EHT CATEGORY
|
24.
|
General Purpose
|
132 KV
|
60
|
60
|
25.
|
Large Industry
|
132 KV
|
351
|
350.5
|
26.
|
Railway Traction
|
132 KV
|
138
|
138
|
27.
|
Heavy Industry
|
132 KV
|
710
|
710
|
28.
|
Power Intensive Industry
|
132 KV
|
100
|
369
|
29.
|
Ministeel Plant
|
132 KV
|
12
|
12
|
30.
|
Emerg. Supply to CPP
|
132 KV
|
0
|
0
|
31.
|
Colony Consumption
|
132 KV
|
120
|
119
|
32.
|
Power Int. Ind. (Opt. Incentive Trf.)
|
132 KV
|
463
|
0
|
33.
|
100% EOU
|
132 KV
|
0
|
194
|
Total |
|
1953
|
1952.5
|
|
Grand Total
|
6380.00
|
6623.40
|
|
T & D Loss (%)
|
41%
|
35%
|
Total Purchase
|
10814.97
|
10093.47
|
* except for 100% EOU units where 4% loss has been assumed on 194 MU
sales
|
|
|