5.0
|
CESCO’S REPLY TO THE OBJECTIONS
Mr. Charles Lenzi, Managing Director, CESCO submitted a set of
clarifications in response to the consumers’ objections to the retail
tariff application, 2000-01.
|
5.1
|
RATIONALE FOR RETAIL TARIFF APPLICATION
|
5.1.1
|
Validity and Frequency of Retail Tariff Application
|
5.1.1.1
|
Referring to maintainability of the tariff application
CESCO was of the view that the retail tariff application was as per
section 26 of the OER Act, 1995.
|
5.1.1.2
|
CESCO maintained that the consumer categories as stated in
regulation 80 were valid classifications.
|
5.1.1.3
|
CESCO agreed to the suggestion of a multi-year tariff
provided the Commission adopted a realistic loss levels. The licensee
did not agree to the contention that there was no nexus between the
purchase of power and sale of units.
|
5.1.2
|
Differential Tariff
CESCO has adopted the methodology provided in law for determination
of revenue requirement
|
5.1.3
|
Hearing
With regard to the proposal for a common hearing for all Distcos,
CESCO maintained that the situation in all Distcos was not identical.
|
5.1.4
|
Audited Accounts
CESCO has already finalised its trial balances for the relevant
period and handed the same to GRIDCO and is extending all possible
support to expedite the process of finalisation of accounts.
|
5.2
|
ENERGY SALE ESTIMATION
|
5.2.1
|
Method of Demand Estimation
CESCO has described the method of demand estimation in the tariff
application.
|
5.2.2
|
Sales Mix
Reacting to the objectors’ contention of a favourable sales mix
CESCO maintained that the share of LT in total consumption was 69.3% in
1999-00 which came down to 68% in 2000-01.
|
5.2.3
|
Energy Purchase from GRIDCO
CESCO has submitted the demand projection for five years to the
Commission and is ready to work on it further to revise the same.
|
5.3
|
ENERGY LOSSES
|
5.3.1
|
Loss Estimation
The loss was calculated as the difference between energy purchased
and energy billed. The licensee has undertaken a metering plan and the
World Bank has already approved the loan on the account.
|
5.3.2
|
Decrease in Loss
Reacting to the objection that the non-technical losses has not got
reduced, CESCO explained that the survey study showed a reduction of
non-technical loss from 11.23% at the beginning to 7% by the end of the
six months period. Comparing the losses of CESCO with SOUTHCO, CESCO
maintained that its proposed loss reduction was higher than what has
been projected by SOUTHCO. The impact of the system improvement
activities on loss reduction would be felt after the completion of the
ongoing Work In Progress.
|
5.4
|
EXPENDITURE OF CESCO
|
5.4.1
|
General
CESCO maintained that the expenditure on VRS scheme, computerisation
and automation, loan for metering, cyclone rehabilitation and IBRD and
RE work etc would lead to loss reduction and improvement in its cash
position.
|
5.4.2
|
Cyclone Expenses
Since the damaged assets on account of cyclone had no salvage value
the licensee had removed Rs.29 crores from its capital base and shown
this as revenue loss. Realising that the cost of damage could be much
more than that of insurance premium, the licensee has taken steps to
enter into insurance contract.
|
5.4.3
|
Employee Expenses and VRS
The employee expenses have gone up due to the implementation of the
fifth pay Commission. Implementation of VRS should rationalise CESCO’s
staff strength in future.
|
5.4.4
|
Bad Debts
CESCO has adhered to the Commission’s norm relating to bad debt.
|
5.4.5
|
Purchase of Power
CESCO purchased power from GRIDCO at a rate
prescribed by the Commission. Therefore the objection relating to
availability of cheap power from hydro or pithead thermal stations was
not relevant to retail tariff application.
Regarding purchase of extra power when the demand increased the
objectors said that the same should be charged at marginal costs. CESCO
requested the Commission to take a view on the higher cost of power
procurement and the mechanism on how to pass the same to the consumers. |
5.4.6
|
Engagement of Consultants
CESCO has restricted the use of consultants and saved on consultant
fees.
|
5.4.7
|
Stores
Reacting to the allegation that CESCO was incurring losses due to
mis-management of stores, the licensee argued that the value of stores
was projected to decrease from Rs.480.54 crores in 1999-00 to Rs.180.48
crores in 2000-01.
|
5.4.8
|
Depreciation
CESCO explained that the process of building an asset register would
require considerable time and expenses.
|
5.4.9
|
Administrative and General Expenses
The A&G expenses and the related details have been furnished in
the application.
|
5.4.10
|
Repair and Maintenance
R&M expenses were high due to obsolete assets and the impact of
cyclone.
|
5.4.11
|
Loans & Interest
Clarifying on loans and interest CESCO said that the Bulk Supply
Agreement with GRIDCO had a provision of working capital loan of Rs.174
crores which was to be repaid .The Govt. of Orissa has not provided any
loan to CESCO on account of cyclone or system improvement. The loans for
building assets have been availed of during the beginning of the year
and hence the interest was charged for the full year.
|
5.4.12
|
Legal Expenses
Regarding the high legal expenses CESCO maintained that those
largely depended on extraneous factors. With regard to the suggestion of
setting up of an effective customer grievance cell to solve disputes
CESCO submitted that a customer care centre had been set up in
Bhubaneswar and similar centres would be opened in Cuttack and Salipur
soon.
|
5.4.13
|
Previous Loss
Clarifying on previous loss CESCO said that it had not claimed any
amount on account of it in its tariff application.
|
5.4.14
|
Contingency Reserve
Contingency reserve has been calculated as per the provision of the
Sixth Schedule.
|
5.4.15
|
Computerisation and automation
The expenses on these heads were primarily for providing in-house
and specialised training to the CESCO employees for upgradation of
skills for the use of computers for data analysis and decision making.
Reacting to consumers’ demand for more of information on a number of
business parameters the licensee submitted that it was not equipped to
generate up-to-date information relating to those parameters
immediately.
|
5.4.16
|
Security Deposit
Investment made by CESCO on account of these has been accounted as
an income for the purpose of calculating income generated from existing
tariff.
|
5.5
|
CAPITAL BASE
|
5.5.1
|
Capital Base
The licensee’s computation of capital base was correct in view of
the fact that the same was based on the original cost of fixed assets as
obtained from GRIDCO.
|
5.6
|
Reasonable Return
Reasonable return has been calculated as per the stipulations of the
Sixth Schedule.
|
5.7
|
Revenue Requirement
Revenue requirement has been calculated as per the stipulations of
the Commission.
|
5.8
|
TARIFF PROPOSAL
|
5.8.1
|
General
Reacting to the objectors’ suggestion to bring changes in the
unbundled tariff structure consisting of demand, energy and customer
charges, CESCO submitted that the existing structure clearly described
the various components of cost. Referring to the consumer complaint that
the bills issued were complicated and confusing CESCO maintained that it
had redesigned the format of the bill as per guidelines issued by the
Commission.
|
5.8.2
|
Meter Rent
Some of the consumers have stated that the meter rent charged was
high and the consumers were not allowed to purchase their own meters.
CESCO clarified that it allowed the domestic/commercial consumers to fix
single phase meters at their own cost. The licensee had raised objection
only against installation of sub-standard meters by the consumers. It
had however no objection in consumers procuring meters of CESCO’s
specification and installing them after being duly tested in CESCO’s
laboratories. Reacting to the consumers’ proposal to withdraw meter
rents, CESCO submitted that it had claimed meter rent as per the
provisions of Indian Electricity Act, 1910. CESCO clarified that
consumers owning meters were not charged meter rent.
|
5.8.3
|
Special Categories
The licensee had proposed a special sub-category for EOUs under the
power intensive category to retain the industrial consumers under the
grid and help other consumers. In the absence of a special tariff these
EOUs might set up and use their own CPPs or continue to use the NTPC
power.
|
5.8.4
|
DPS, Overdrawal Penalty and Power Factor Penalty
Income on account of DPS, overdrawal penalty and power factor
penalty had been accounted for in the tariff proposal
|
5.8.5
|
Demand Charges
Regarding installation of demand meters CESCO submitted that these
were required only in case of demand charge levied on the basis of
recorded maximum demand.
|
5.8.6
|
Proposed Tariff Rates
The proposed tariff rates of CESCO were provided in Form T-8. The
proposal of Astaranga Salt Production and Orissa Cooperative Coir
Corporation that they should be charged for power at par with Irrigation
pumping & Agriculture category was not justified as these consumers
could not be classified as above.
|
5.8.7
|
Tariff for Railway Traction
The tariff for different categories of consumers did not match with
the cost of supply, as pointed out by the SE Railways, due to the
presence of cross-subsidy. The Railways had hinted at the simultaneous
maximum demand method on the basis of which CESCO paid demand charge to
GRIDCO. CESCO clarified that whereas the licensee had entered into a
single agreement with GRIDCO for mutiple-points, the consumers of CESCO
would have to enter into separate agreement with the licensee for each
point of supply.
|
5.8.8
|
NALCO Tariff
Regarding supply of power to NALCO, CESCO maintained that it had the
exclusive right of distribution and retail supply of electricity. NALCO
was bound to be a retail consumer of CESCO as far as import of power was
concerned. CESCO did not agree with NALCO that low power factor penalty,
demand charge etc. should not be levied on the latter. CESCO submitted
that it was unwilling to accept the wheeling of power from NALCO CPP,
Angul for NALCO Bhawan and NALCO Nagar Township at Bhubaneswar for the
simple reason that the area of operation came under the retail supply
business of the licensee.
|
5.9
|
REVENUE GENERATION
|
5.9.1
|
Revenue Generation From Existing and Proposed Tariff
Structure
Regarding the proposed generation of revenue under the existing
tariff, CESCO maintained that it would fall short of its revenue
requirement defying UCCI’s expectations of surplus in revenue
collections.
|
5.10
|
OPERATIONAL ISSUES
|
5.10.1
|
State of Finance
Some of the objectors had taken exception on the statement about the
possibility of CESCO being referred to BIFR. The licensee through this
statement wished to sensitise the stake-holders and did not agree with
the view that this was a threat or pressure tactics.
|
5.10.2
|
Metering
Reacting to the objectors’ view that CESCO was negligent on
metering the licensee argued that its metering plan was aggressive and
it wished to regularise illegal connections as fast as possible. The
non-availability of meters had rather delayed the metering programmes of
CESCO due to which the number of unmetered consumers increased in the
current year.
|
5.10.3
|
Power Theft
CESCO did not agree with the objector that increase in electricity
tariff might encourage consumers to steal power by various means.
|
5.10.4
|
Disconnection and Reconnection
Increase in reconnection charges had been proposed as a means of
disincentive for those who were irregular in paying the energy charges
or resorting to other illegal activities.
|
5.10.5
|
New Connections
Reacting to the objectors’ request for separate light and fan
connection in the premises of the industrial units, CESCO maintained
that two connections under different categories of consumers to the same
premises are prone to misutilisation of the different tariffs for
different categories of consumers.
|
5.10.6
|
Serving of Bills
Referring to consumers’ complaint that bills were not served in
time, CESCO submitted that although normally the bills reached the
consumers within the due date, the consumers should also themselves
arrange for a copy of the bill in case the bills did not reach in time.
|
5.10.7
|
Security Deposit
Security deposit was charged as per the provision in Section 20 of
the Distribution Code.
|
5.10.8
|
Consumer Benefit Proposal
The proposed expenses in respect of system improvement would result
in improved voltage and reliability of the system.
|
5.10.9
|
Low Voltage/Power Failure
Reacting to the consumers’ complaint of low voltage and power
failure CESCO submitted that the same was caused due to overdrawal by
registered as well as illegal consumers.
|
5.11
|
MISCELLANEOUS
|
5.11.1
|
DPS Payable to GRIDCO
The licensee has not claimed any payment towards DPS payable to
GRIDCO.
|
5.12
|
CESCO’S REPLY TO DIRECTOR (TARIFF)
|
5.12.1
|
Loss Estimation
CESCO recalculated LT & HT Distribution loss at 50.8% The licensee
has targeted to reduce the LT/HT losses by 3.73% in 2000-01.
|
5.12.2
|
Loss Studies
The licensee would carry out the necessary loss studies as required
by the Commission and would submit the same shortly.
|
5.12.3
|
A&G Expenses
While furnishing clarification to the Commission’s queries, CESCO
had shown consultancy charges as part of A&G expenses.
CESCO depended on outside agencies for printing, stationery and bill
generation during 1999-00 and hence the expenses were shown under
different sub-heads under A&G expenses. Now that printing of bills
are in-house the same is classified under the head of printing,
stationery and bill generation. Therefore, other expenses shown in the
A&G has gone down substantially.
|
5.12.4
|
Loss Due to Damaged Assets
In order to carry out repair and maintenance work after cyclone most
of the materials were ordered by CESCO before the Commission set a limit
on these expenses. Since the actual expenditure incurred under this head
was much more than what was approved, the licensee humbly requested the
Commission to allow these expenses by reconsidering its earlier stand.
|
5.12.5
|
Carry Forward of Past Losses
CESCO clarified that it had not claimed any amount on account of
previous losses in the tariff application. The figure of Rs.13.77 crores
shown against previous losses was on account of two factors (i) the
amount of Rs.1.48 crores disallowed by the Commission in the last tariff
order and (ii) the additional losses suffered due to calculation of
CESCO’s revenue requirement on the basis of the last year BST order
which was sub-judice.
|
5.12.6
|
Capital Expenditure
Since the cyclone related repair and restoration work was over
during 1999-00 CESCO submitted that it could deploy its entire workforce
for PMU work. The licensee therefore opined that the projected level of
PMU work could be implemented during 2000-01.
|
5.12.7
|
CESCO Stores
Materials lying in stores, worth Rs.31.23 crores, have been used for
the creation of fixed assets. The licensee, therefore, requested to
allow the capitalisation of the identified amount from stores.
|
5.12.8
|
Employee Expenses
CESCO has claimed only 6% increase in its employee cost over the actual
expenses in 1999-00. The details of employees and their pay scales were
furnished for the Commission’s perusal.
|
5.12.9
|
CESCO’s Metering Efforts
CESCO has submitted the details of the metering plan. The licensee has
conveyed that the current lot of meters were not sufficient to even
fully replace the existing defective meters.
|
5.12.10
|
Customer Care at CESCO
CESCO has set up a Customer Care Centre at Bhubaneswar for quick and
effective redressal of the consumer complaints and wished to establish
similar centres in other divisions.
|