6.0
|
Commissions OBSERVATIONS AND Analysis on GRIDCOs Proposal
The filings of GRIDCO made under Section 26(4) of the Reform Act, 1995 and subsequent
information and clarifications filed before us have been scrutinised, written and oral
representations of the objectors have been carefully examined and the views expressed in
the meeting of the Commission Advisory Committee convened for the purpose of consultation
on the tariff determination have been taken into account.
|
6.1
|
The Committee Advisory Commission specifically discussed the issues of
subsidy, cross-subsidy, percentage of T&D loss, percentage of transmission loss,
advisability of differential BST among the distribution companies and uniform retail
tariff for the whole State. Some of the Members raised issues specific to the interest
groups they represent. But there was near unanimity with regard to the certain issues. It
was felt that T&D loss was still high and should be brought down at least by 5% every
year so as to justify tariff increase. It was also felt that installation of meters and
consumer services were far from satisfactory. While the suggestion for uniform retail
tariff for the whole State was put forward by most of the members, the proposal did not
find favour with the representatives of the DISTCOs.
|
6.1.1
|
Before we record our observations and orders on general and specific
aspects of GRIDCO proposal and proceed to determine tariff, we may indicate the
perspective, principles and the regulatory environment in which tariff has been determined
by us in the later part of this order.
|
6.1.2
|
During the state-owned SEB days, tariff in Orissa was historically based
on nature and purpose of use. The State Govt. subsidised the consumers belonging to the
economically weaker domestic class and agricultural irrigation to a considerable extent
possibly on considerations of affordability and public policy.
|
6.1.3
|
The present reform scenario under Reform Act, 1995 has given a go by to
the administrative price mechanism, Govt. intervention and subsidy of any kind except
cross-subsidy. GRIDCO is a corporatised entity which has taken over the transmission and
distribution business on 01.4.96. It was expected that the newly formed GRIDCO would turn
around by 1997-98 based on assumption of substantial reduction in T&D loss, increased
load growth, investment for system improvement and tariff increase. The assumptions were
not realistic and did not materialise to a great degree. The cost of power substantially
went up due to revaluation of assets of OHPC and transfer of TTPS to NTPC. The revenue
requirement further went up due to additional depreciation on account of revaluation of
assets of GRIDCO and distribution companies. For instance, the cost of power which was
Rs.469 crores in the FY 1994-95 went up to Rs.1199 crores by the year 1997-98.
Unfortunately the assumption of load growth failed to materialise and the pace of
reduction of T & D loss has not been upto expectation. The quantum of purchase of
power remaining same, total cost went up substantially on account of revaluation of assets
as a part of the reform process.
|
6.1.4
|
No provision was made by the Government of Orissa to provide subvention or
subsidy to GRIDCO, successor of State Electricity Board during the transitional phase from
a state-owned, state supported entity to a viable transmission and distribution licensee.
Such support was needed for socially purposive but un-economic measures such as rural
electrification, supply to urban poor, for meeting massive debt service burden and for
meeting accumulated losses.
|
6.1.5
|
The Commission is convinced that subsidies are not in harmony with the
spirit of the Reform Act, 1995. In any case, the government cannot afford to grant
subsidies to companies or consumers for the electricity they consume. However, it is also
quite clear that during the transition from the highly subsidised State monopoly situation
to an economically viable self sustaining electricity industry, there has to be certain
amount of financial support in the form of subsidy and subvention. Investments to improve
the system have immediate impact on tariff whereas the effect of improvement and the gains
of efficiency take considerable time. It was perhaps necessary for the State government to
give some sort of financial support in the form of subvention or subsidy during the
transitional period. This is why the Governments of Andhra Pradesh, Gujarat and Utter
Pradesh have been providing subsidies during the first few years of reform. The above
named states have provided Rs.1585 crores, Rs.1260 crores and Rs.790 crores respectively
as subsidy in the FY 2000-01. As a result of total withdrawal of subsidies in Orissa, the
tariff rise has to be of considerable magnitude if cost reflective tariff has to be
adopted for 2000-01. In response to the Commissions query to ascertain whether Govt.
was prepared to grant subsidy or subvention to reduce the impact of tariff increase, the
State Govt. has clearly stated that they are not in a position to provide subsidy or
subvention which could have resulted in lower Bulk Supply Tariff and enhanced financial
viability of GRIDCO.
|
6.1.6
|
In the post-reform era the Orissa Electricity Regulatory Commission has
been addressing the issue of tariff setting in accordance with the Reform Act, 1995 in a
pragmatic manner. Sec. 26 of the Reform Act, 1995 and the financial principles laid down
in Sec. 57 & 57(A) of the Act, 1948 have been the guiding factors in tariff setting.
Further, it is the economic and financial principles which have played key role in
deciding the tariff structure and in determining charges for various categories of
consumers.
|
6.1.7
|
It was discernible from the filings before OERC that the currently
proposed tariff would have to be much higher as compared to those of the immediate
previous years even after pruning all expenditure items by the Commission on the same
lines as in the past. The Commission is faced with a formidable predicament in balancing
the interest of the ultimate end-users i.e. the consumers vis-a-vis the financial health
of the licensee as defined under Sec.26(2) and Sec.11(1)(e) of the Reform Act, 1995. Many
objectors had alleged that there should be no revision in tariff since licensees have not
brought about desired improvements and had not been able to reduce the T & D loss
substantially. We ourselves have been very much concerned with the performance of the
licensees and have been suo motu monitoring in various ways. We agree that price of
electricity has to be linked to performance. But ground realities have to be considered
and it has to be admitted that Distribution Companies cannot bring about improvement
overnight because of historical, technical and socio-economic reasons. Secondly, tariff
fixation and other aspects cannot wait till after performance improves to the desires
extent. We may quote, the authority of Honble Orissa High Courts observations
in Appeal No.51 of 2000 decided on December 22, 2000:
"One cannot but agree with the sentiments expressed by Shri K. N. Jena regarding
the inefficiency in the services provided as well as inaction/failure on the part of the
various Distribution Companies in checking the growing menace of pilferage of electric
energy by unauthorised persons. This is a matter which can be looked into by the
Regulatory Commission in future, but this cannot be a ground to set at naught the fixation
of tariff".
|
6.1.8
|
Another recurring objection against tariff increase has been the
constraint of affordability. The domestic consumers have urged to leave them out of tariff
increase because they cannot afford and they cannot pass on the burden which the
commercial and industrial consumers can do. On the other hand commercial and industrial
consumers have pleaded that their products cannot be competitive and therefore their
tariff should be reduced rather than increased. Every category has pleaded that tariff, if
increased, should be for other categories. We cannot ignore the affordability factor
because safeguarding interest of consumers is one of the main parameters in tariff
fixation. But affordability cannot be the prime consideration. We are constrained to
observe that these objections are mostly due to inadequate understanding of financial,
economic and legal parameters of tariff determination. Electricity industry licensees may
be expected to gird their loins, reduce expenditure, reduce T & D loss and improve
consumer service. But that industry also has to survive and that is why Section
11(1)(e) of
OER Act mandates that the supply and distribution industry cannot be maintained unless
the charges for the electricity supplied are reasonably levied and collected. Licensees
of electricity supply and distribution cannot be expected to forego their legitimate dues
and charge low rate to ameliorate financial stringency of any category of consumers or to
make industrial consumers competitive in national and international market.
|
6.1.9
|
It is the duty of the Commission to scrutinise the claims of licensee with a
fine tooth-comb and allow only useful assets for capital base and only properly/prudently
incurred expenditure for revenue requirement. But after we do so whatever Revenue
requirement finally is determined has to be allowed to be raised through tariff. This is
the position in Law and has to be appreciated by the consumers of all categories. Keeping
the above objective in view, the Commission has gone ahead in deciding the various
parameters regarding determination of revenue requirement and tariff of the licensee in an
endeavour to strike a balance between the interests of end consumers on one hand and
financial viability of licensee on the other.
|
6.1.10
|
It is because of our concern for the views of various categories of
consumers that the Commission has decided to leave a gap between the approved revenue
requirement and the revenue to be garnered through this tariff order for recovery in
future. This decision has been taken in exercise of power vested in the Commission under
subsection (3) of Section 26 to depart from the factors specified in the Sixth Schedule.
Strict adherence to the Sixth Schedule will result in what may be called tariff shock in
view of sudden rise in tariff. The industrial load growth in Orissa has been in the negative
and hence full increase to fill the revenue gap may allow further shrinkage in the
electricity demand. We therefore consider it appropriate not to permit the entire gap to
be recovered in this year's tariff. Once efficiency gains bridge the gap such departure
will possibly not be needed.
|
6.1.11
|
The Commissions analysis of GRIDCOs proposal and its finding
as to reasonableness of various items and determination of the extent to which the
expenses projected shall be considered to be "properly incurred" in the context
of the Sixth Schedule as well as other parameters stipulated in Section 26 of the Reform
Act, 1995 need to be given at length.
|
6.2
|
Quantum of Power Purchase
|
6.2.1
|
Out of GRIDCOs estimated revenue requirement of Rs.1937.90 crores
for the year 2000-01 cost of power alone accounts for Rs.1432.20 crores or 73.90% of the
total requirement. Since cost of power constitutes the major chunk of expenditure, it is
extremely important that the power purchase is done scrupulously following the concept of
least cost combination of power procurement while maintaining the system stability.
|
6.3
|
Demand Estimation and Power Procurement Proposal of GRIDCO
|
6.3.1
|
GRIDCO has stated that WESCO, CESCO and SOUTHCO have provided their
forecast of monthly energy requirement and maximum demand sub-station wise. NESCO has
provided only an annual forecast. The energy forecast provided by the DISTCOs includes
supply to the Export Oriented Units (EOUs). GRIDCO had also stated that if OERC approves
the proposed treatment of EOU sale as a part of DISTCOs supply then GRIDCO will modify the
present method of billing from the date of approval. Subsequently GRIDCO was asked to
clarify the following issues by Director (Tariff) on 15.12.2000 as follows :-
Whether there was any agreement for utilisation of NTPC power during off-peak hours to
the EOUs
Whether there was any fresh allocation of power to the EOUs from the unallocated quota
of the central station by CEA
If any allocation exists, whether steps have been taken by the interested parties
requesting cancellation of allocation to the EOUs
|
6.3.2
|
GRIDCO in its rejoinder to OERC Query dtd.23.12.2000 stated that there is
no existing agreement of GRIDCO with the EOUs. The supplementary agreement entered by
GRIDCO with the EOUs for the supply of NTPC power during off-peak hours was valid upto
31.3.99. An order allocating power from the unallocated share of NTPC stations of Eastern
Region has been passed by CEA in March 2000 in favour of FACOR, Ispat Alloys, Charge
Chrome Plant of Bamanipal of TISCO, Nava Chrome, Meramundali and IDC. But this allocation
order has not been followed up with tripartite agreements among NTPC, GRIDCO and EOUs.
Hence, notwithstanding the finding given by us for earlier years, we have to note that
there is no legal or contractual framework for direct supply of NTPC power to EOUs during
2000-01. GRIDCO had requested Govt. of Orissa to move the Ministry of Power, Govt. of
India not to allocate power to the EOUs in the State of Orissa out of the unallocated
share of NTPC stations and to allocate the same power on firm basis to other States. The
Govt. of Orissa vide letter dtd.27.11.99 had also requested the Ministry of Power, Govt.
of India not to continue with allocation of power to the EOUs from the unallocated share.
Govt. of Orissa also stated that the EOUs will be supplied power from the DISTCOs on
continuous basis (24 hours).
|
6.3.3
|
A verification of the global accounts issued by the Eastern Regional
Electricity Board for the months of April to August, 2000 indicate that there has been no
drawal by GRIDCO during off-peak hours from the unallocated share of NTPC stations for use
of EOUs. GRIDCOs forecast includes consumption by the EOUs as a part of its bulk
supply to DISTCO. Taking all these factors into consideration the Commission accepts the
proposition of GRIDCO for inclusion of energy consumed by EOUs as a part of its bulk
supply to DISTCOs.
|
6.3.4
|
GRIDCO has reported that at the time of filing, it had the actual data for
energy and demand for five months (April 2000 to August 2000). Therefore, the demand
forecast has been modified to incorporate these actuals for the five months and the
forecast provided by the DISTCOs has been considered for the balance period in respect of
WESCO, CESCO and SOUTHCO. In case of NESCO, the actuals for the first five months is taken
and for the balance period the forecast is based on the average of last five months for
EHT loads and previous years pattern for non-EHT load adjusting for cyclone effect.
Accordingly, the picture of annual energy requirement is given in Table : 5. Table : 5
Annual Energy Requirement
DISTCOs |
Energy requirement for FY 01 provided by DISTCOs
(in MU)
|
Actual for 5 months and forecast for
balance period (in MU) |
NESCO |
2355.00 |
2520.82 |
WESCO |
2710.10 |
2751.66 |
CESCO |
3995.11 |
4011.97 |
SOUTHCO |
1534.28 |
1535.98 |
Total |
10594.49 |
10820.44 |
|
6.3.5
|
The annual energy requirement for the DISTCOs has been projected as
10820.44 for the year 2000-01 by GRIDCO.
|
6.3.6
|
GRIDCO is required to purchase power from the various generating units and
deliver to the DISTCOs which would also include direct sale to EHT consumers. In the
process of delivery of this power, transmission loss occurs in the system which is
estimated to be 4% by GRIDCO. Thus out of the energy purchased from the generators at EHT
bus 4% is deemed to have been lost in transmission and the balance is supposed to be
delivered to the DISTCOs. Therefore, based on this assumption GRIDCO is required to
purchase 10820.44/0.96 = 11271.29 MU from the generators (DF 1).
|
6.3.7
|
Demand charge is proposed to be charged at the actual
simultaneous maximum demand or 80% of the contract demand whichever is higher in the month
for the DISTCOs. GRIDCO has stated to have written to the DISTCOs to submit their contract
demand at various grid supply points. GRIDCO has adopted the figure of contract demand
based on the maximum of the monthly demand forecast provided by the DISTCOs incorporating
the actual data available for five months of the year 2000-01 which comes to 1949.40
MVA.
Table : 6
Contract Demand (Page 38/42 of main text)
DISTCOs |
Proposed Contract Demand MVA |
NESCO |
439.60 |
WESCO |
513.30 |
SOUTHCO |
308.00 |
CESCO |
688.50 |
Total |
1949.40 |
|
6.3.8
|
GRIDCO in its BST application initially had proposed a
contract demand of 1949.40 MVA and billing demand of 1560 MVA as 80% of 1949.4 MVA. GRIDCO
in query to the clarification has reported that no agreement with DISTCOs could be
concluded despite several discussions on the subject. GRIDCO, therefore, request OERC to
adopt a billing demand the average SMD of 1735.7 MVA based on five months of actual demand
and the projection at the rest of financial year as indicated in Table : 7. Table : 7
DISTCOs |
Proposed Billing Demand MVA |
NESCO |
413.30 |
WESCO |
469.60 |
SOUTHCO |
187.30 |
CESCO |
665.60 |
Total |
1735.70 |
(para 2.1.2, page
14/32 clarification to queries on BST application 2000-01) |
6.3.9
|
The Commission has examined the evidential document
supplied by GRIDCO about energy drawal from the months April, 2000 to August, 2000 along
with the projections made by the various DISTCOs. Based on this study the Commission has
considered it prudent to accept the actual consumption for the first five months of the
year 2000-01 and extrapolated it to determine the energy requirement of the balance seven
months to derive the figure of energy sale by GRIDCO to various DISTCOs in line with the
concept approved in the last tariff order of dtd.30.12.99. Accordingly, the figures are in
Table : 8. Table : 8
DISTCOS |
Actual drawal for 5 months |
Total requirement for
12 months
|
CESCO
|
1641.08 |
3938.60 |
WESCO
|
1160.56 |
2785.34 |
NESCO
|
991.89 |
2380.53 |
SOUTHCO
|
624.79 |
1499.50 |
TOTAL
|
4418.32 |
10603.97 |
Transmission loss
|
3.70% |
407.42 |
Net energy requirement
|
|
11011.39 |
Net energy for sale
|
|
10603.97 |
|
6.3.10
|
It is worthwhile to examine that the estimate of power sale
by GRIDCO to DISTCOs works out little higher i.e. 10820.44 MU compared to 10603.97 MU or a
difference of 216.47 MU.
|
6.3.11
|
It is worth mentioning that some of the objectors namely
UCCI, INDAL, Shri R.C. Padhi, Retd. Chief Engineer, CII have suggested that the quantum of
power purchased by GRIDCO for the year 2000-01 should be back calculated based on the
quantum of power to be sold by the DISTCOs and adopting a normative loss level varying
from 30-32.5%. By their calculation GRIDCOs revenue requirement should be based on a
total requirement of 8303.711 MU (30% loss) to 9500 MU (32.5%).
|
6.3.12
|
The Commission however
considers that GRIDCO should not bear the burden of the losses of the distribution
utilities and the estimated actual quantum of power purchase should be the criteria for
determining the expenses of power purchase allowable to GRIDCO. Based on this criteria the
Commission approves a total of 11011.39 MU as energy requirement by GRIDCO for FY 2000-01.
Table : 9
(Figures in MU)
Year |
GRIDCOs Proposal
|
Commissions Approval
|
GRIDCOs Actual
|
1997-98 |
11000 |
9815 |
10324.30 |
1998-99 |
10814.97 |
10093.47 |
10570.91 |
1999-00 |
10229.90 |
10176.13 |
10131.40 |
2000-01 |
11271.29 (including
EOU)
|
11011.39 (including
EOU)
|
|
|
6.3.13
|
Similarly the Commission
also examined the maximum demand figures considered by GRIDCO for the purpose of billing
to various DISTCOs and calculated the average of the maximum demand of the last five
months to determine the average billing demand for different DISTCOs which are in Table :
10.
Table:10
DISTCOs |
Max. Demands of
5 months
|
Avg. of Max. Demands for 5
months |
CESCO
|
667.30 |
643.95 |
WESCO
|
512.81 |
465.90 |
NESCO
|
393.64 |
376.49 |
SOUTHCO
|
307.98 |
267.17 |
TOTAL
|
1881.72 |
1753.51 |
|
6.3.14
|
The Commission approves 1753.51 MVA as the billing demand
for the year 2000-01.
|
6.4
|
Computation of Transmission Loss
|
6.4.1
|
GRIDCO in para 2.2 of the main text of the BST application has stated to
have used the gross method for determination of transmission loss as approved by OERC
earlier instead of the net method of computation. GRIDCO has re-stated that irrespective
of the method of computation, the transmission loss in MU is the same whether gross or net
method of computation of transmission loss is adopted. Therefore, GRIDCO should be allowed
full recovery of units lost in transmission.
|
6.4.2
|
The calculation of transmission loss in EHT system submitted by GRIDCO in
OERC Form No. TRT 8 is shown as 4.11% of the gross output. In this transaction the input
of 1076.38 MU for EREB has neither been shown in the input nor output side of the
calculation. By not considering this GRIDCO has calculated the transmission loss on net
basis and not on gross basis as approved by the Commission. In query to the clarification
GRIDCO has stated that some amount of energy lost in the system is not attributable to the
system and is to be realised proportionately for all users of the system.
|
6.4.3
|
GRIDCO in modified Table 34 of the
clarification has stated that a sum of Rs.26.5 crores is to be deducted from miscellaneous
receipt due to 4% loss on wheeling of power to MP. The rate adopted for such energy lost
in transmission has been calculated at NTPC rate or the marginal cost of power purchase.
GRIDCO has further clarified that the cost of the lost units on account of wheeling to
outside states is deemed to have been recovered within the levy of transmission charge
billed to other states. Since GRIDCO gets paid in full for the units lost in transmission
on account of wheeling to outside the state it is imperative that the energy exported to
EREB is treated both as an input and as an output for the purpose of calculation of
transmission loss. Therefore, the calculation furnished by GRIDCO in form No. DF 3 is
modified incorporating 1076.38 MU exported to EREB as per the details in Table : 11.
Table : 11
Source |
Gross
Input
|
Gross Output |
Proportionate
loss sharing |
Proportionate
loss sharing (%) |
EREB
|
5542.57 |
4056.23 |
154.37 |
1.03% |
State dedicated
|
|
|
|
|
OHPC
|
3186.65 |
|
|
|
INDRAVATI
|
0.00 |
|
|
|
MACHHKUND
|
309.14 |
|
|
|
OPGC
|
2839.67 |
|
|
|
TTPS
|
2035.96 |
|
|
|
CPPs
|
|
|
|
|
ICCL
|
371.90 |
293.12 |
11.16 |
0.07% |
NALCO
|
658.59 |
61.57 |
2.34 |
0.02% |
Others
|
16.90 |
14.94 |
0.57 |
0.00% |
Consumers (DISTCOs)
|
|
|
0.00 |
0.00% |
CESCO
|
|
3607.29 |
137.29 |
0.92% |
WESCO
|
|
2688.679 |
102.33 |
0.68% |
NESCO
|
|
2257.619 |
85.92 |
0.57% |
SOUTHCO
|
|
1433.403 |
54.55 |
0.36% |
Total DISTCOs
|
|
|
|
|
Grand Total
|
14961.38 |
14412.85 |
548.53 |
3.67% |
Loss
|
548.53 |
|
|
|
Loss (% of Gross Input)
|
3.67% |
|
|
|
|
6.4.4
|
The
objectors in general had stated that the huge investment made by GRIDCO during the last
four years should be reflected in some tangible form and result in reducing the existing
level of 4% transmission loss to 3.5%. The Commission has examined as indicated above and
by actual calculation has arrived at the figure of 3.67% and accordingly approves 3.70%
for the purpose of computation of transmission loss. |
6.5
|
Sources of Power
|
6.5.1
|
The quantum of power purchased by OSEB/GRIDCO since 1992-93
onwards is indicated in Table : 12 generating station-wise. Table
: 12
(Units in MU)
Sources |
1992-93 Actual |
1993-94 Actual |
1994-95 Actual |
1995-96 Actual |
1996-97 Actual |
1997-98 Actual |
1998-99 Actual |
1999-00 Prov.
|
Hydro (State)
|
3757.00 |
3645.00 |
4020.00 |
4357.00 |
3608.00 |
3210.15 |
3280.20 |
4377.44 |
Hydro (Machhkund) |
364.00 |
302.00 |
306.00 |
349.00 |
372.00 |
296.67 |
245.00 |
337.65 |
Hydro (Chukha) |
174.00 |
331.00 |
230.00 |
239.00 |
221.43 |
247.10 |
236.73 |
148.00 |
Thermal (CPP) |
907.00 |
930.00 |
1352.00 |
1102.00 |
992.00 |
667.29 |
1015.60 |
650.26 |
Thermal (TTPS) |
1257.00 |
1302.00 |
1069.00 |
991.00 |
1320.82 |
1810.17 |
1954.78 |
2035.96 |
Ib TPS
(OPGC) |
|
|
285.00 |
1086.00 |
1792.00 |
2058.03 |
2509.31 |
2839.67 |
Farakka |
349.00 |
1005.00 |
1061.00 |
1001.00 |
1057.24 |
1011.36 |
391.47 |
238.31 |
Kaniha (Firm) |
|
|
|
165.00 |
218.89 |
785.12 |
680.87 |
495.68 |
Kahalgaon |
|
|
|
419.00 |
280.58 |
238.41 |
256.95 |
5.88 |
MPSEB |
201.00 |
72.00 |
42.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
Others |
91.00 |
239.00 |
128.00 |
53.00 |
0.00 |
0.00 |
0.00 |
0.00 |
Total |
7100.00 |
7826.00 |
8493.00 |
9762.00 |
9863.00 |
10324.30 |
10570.91 |
11133.95* |
* This includes purchase for sale to AP, CPPs and EOUs |
6.5.2
|
GRIDCO has stated that the power procurement plan has been developed based
on a monthly forecast of demand and supply to reflect the reality of load despatch and to
demonstrate merit order procurement.
|
6.5.3
|
GRIDCO has stated that the station wise procurement plan is determined by
the following factors.
-
Provisions of the Power Purchase Agreements and relevant Government of India
Notifications
-
For Hydro stations, current status of generating units, their performance and water
level in the reservoirs
-
Availability of generators, considering their maintenance schedules
-
Energy requirement of the DISTCOs for the month
-
Least cost order of all generators for determining station wise procurement for that
month
|
6.5.4
|
In its present form, the order on ABT causes a significant increase in
cost of power purchased from Central Generating Stations, due to their low PLF and high
availability. GRIDCO has further stated that this application does not consider the impact
of Availability Based Tariff (ABT) as it has been stayed by CERC.
|
6.5.5
|
Commission analyses purchase of power from the various generating stations
on the principle of economic load despatch, least cost ordering of generation, power
availability from the generating stations based on PPA, availability of thermal stations
for the year, analysis of generation for the past years and technical constraints, if any,
for drawal.
|
6.5.6
|
Generating stations of OHPC, OPGC and TTPS of NTPC are totally dedicated
for Orissa and GRIDCO has the contractual obligation for payment of the entire fixed cost
in respect of these stations along with the fixed share of Machhkund Hydro Electric
Project. Power purchased from Upper Indravati Hydro Electric Project for the year 2000-01
and from the captive power plants have been charged on the basis of single part tariff
that is, totally variable.
|
6.5.7
|
GRIDCO has also certain allocated percentage of share in three super
thermal stations of NTPC located in the eastern region namely Farraka (West Bengal),
Kahalgaon (Bihar), Talcher Super Thermal (Orissa). For the year 2000-01, the fixed cost of
these stations is payable in proportion to the power drawn along with the variable charge
which essentially works out to be a single part tariff that is, totally variable until the
issue of ABT is decided.
|
6.5.8
|
In examining the power purchase plan of GRIDCO, the Commission proposes to
assign highest priority to purchase from the generating stations which are dedicated for
Orissa and for which GRIDCO is obliged to pay the entire fixed cost. Only when the
requirement of power exceeds the availability from these stations, power will have to be
procured from other generating stations in the ascending order of their variable cost
otherwise known as merit order operation.
|
6.6
|
Quantum of Power Purchase
The procurement of power, generator wise, is discussed below :-
|
6.6.1
|
OHPC :
OHPC owns and operates the following power stations of the State :-
Hirakud
Balimela
Upper Kolab
Rengali
Upper Indravati Hydro Electric Project
OHPC also has a fixed share in Machhkund hydro electric project. |
6.6.2
|
Machhkund : This Hydro Power Station is a joint venture of Govt. of
Orissa and Govt. of Andhra Pradesh with a capacity of 114.5 MW. GRIDCO has projected a
drawal of 288.68 MU for the year 2000-01 based on actual generation for five months
(April-August, 2000) and forecast for balance period (September, 2000 - March, 2001)
considering the performance of the power stations during the same months for the year
1997-98.
|
6.6.2.1
|
Many of the objectors have suggested a drawal of 322 MU as the drawal from
Machhkund during the first six months has been 172.34 MU and the reservoir level of
Machhkund is comparable to earlier years.
|
6.6.2.2
|
The water level at Jalaput reservoir as on 01.12.2000 is 2743.15 ft. as
against 2746 ft. on 01.12.99. During the year 1999-00 GRIDCO had drawn 337.65 MU and has
drawn 123.73 MU during first five months of the year 2000-01. Since the water potential
for this year is lower than the previous year GRIDCO should endeavour to draw at least
Orissas full share from this generating station i.e. 302 MU.
|
6.6.3
|
Hirakud, Rengali, Balimela, Upper Kolab
|
6.6.3.1
|
GRIDCO had initially proposed (on
September, 2000) a total drawal of 2953.18 MU from Hirakud, Balimela, Upper Kolab and
Rengali power stations based on reservoir level of 31.8.2000. The proposed drawal
according to the plan submitted by GRIDCO, from the four power stations of OHPC has been
shown in Table : 13 (Page 16, 17 and Revised DF-14 of Main Text).
Table : 13
Hirakud
|
616.72 MU
|
Rengali
|
924.49 MU
|
Balimela
|
870.04 MU
|
Upper Kolab
|
541.94 MU
|
Total
|
2953.18 MU
|
|
6.6.3.2
|
GRIDCO had stated in para 2.3.1 of the main text that the year 2000-01 is
a poor monsoon year for Orissa with rains failing in catchment areas of reservoir. The
latest available data on reservoir levels as on 31st of August for five years
shows a significantly lower figure on 31.8.2000 compared to those of the previous years
(Ref. Table 9, Page 16 of main text). It has been observed that reservoir levels for
ensuing year are closest to FY 1997-98 in case of Balimela, FY 1998-99 in case of Rengali
and Upper Kolab and that Hirakud reservoir levels are one of the worst since 1996-97.
|
6.6.3.3
|
GRIDCO had stated that the generation plan for the year 2000-01
incorporates five months actual generation and for the balance period the generation for
various stations has been estimated using the correlation to the reservoir levels of
different years as indicated in para 6.5.2.4.
|
6.6.3.4
|
Objector like UCCI has stated that the procurement from the four above
mentioned hydro stations of OHPC should not be based on an annual estimation as
availability would depend on the inflow to reservoirs during monsoon months, reservoir
level of 31.3.2001 and the lowest drawal level to be reached during water year 01-02.
Therefore, they have suggested to take either design availability or average of eight
years availability from 1992-93 to 1999-00. Based on this, they project a figure of
3721 MU. CII projects a figure of 3200 MU based on the analogy given above. We find that
Shri R.P. Mohapatra in his written submission dtd.23.12.2000 has suggested a drawal of
2953.2 MU from OHPC.
|
6.6.3.5
|
GRIDCO in its rejoinder dtd.08.12.2000 has stated that the objectors have
objected to the tariff being set on low hydro procurement in FY 2001 on the ground that
the position of reservoir level in FY 2002 may be different. Last year under similar
circumstances the objectors had given the rational of high hydro availability on reservoir
levels and urged the Commission to accept the power procurement plan during 1999-00 which
the Commission had accepted. GRIDCO, therefore, requested that the Commission should base
the hydro procurement on the reservoir level on FY 2000 as it had done in December, 1999
order.
|
6.6.3.6
|
OHPC has submitted a revised generation plan for the above four stations
on 22.12.2000 showing a total generation of 2798.30 MU.
|
6.6.3.7
|
We find that GRIDCO had not agreed to the revised generation plan of OHPC
as submitted in its clarification dtd.23.12.2000. However, on 02.01.01 in a fresh filing
termed as revision to rejoinder to queries and objections raised during hearing on the BST
Application FY 2001 it has changed its stand and requests the Commission to approve
procurement as proposed by OHPC.
|
6.6.3.8
|
The Commission examined the generation plan
submitted by OHPC and the revised procurement plan proposed by GRIDCO for the year 2000-01
in its fresh filing on 02.01.01 as shown in Table : 14.
Table 14
Station
|
Old projection for FY 2001 MU
|
Current projection for FY 2001 MU
|
Hirakud
|
616.72
|
568.30
|
Rengali
|
870.04
|
714.65
|
Balimela
|
924.49
|
995.83
|
Upper Kolab
|
541.94
|
519.52
|
Sub-total
|
2953.19
|
2798.30
|
Indravati
|
1263.02
|
1710.44
|
Total
|
4216.21
|
4508.74
|
|
6.6.3.9
|
In view of the revised generation plan of OHPC being based on the
reservoir levels of 01.12.2000, the Commission thinks it prudent to accept the generation
plan as proposed by OHPC and GRIDCO i.e. 2798.30 MU from the four stations of OHPC.
Procurements from the four stations are discussed hitherto.
|
6.6.3.10
|
Hirakud : The combined installed capacity of Hirakud power system
i.e. Hirakud and Chiplima taken together, is 331.50 MW with an annual availability of 1174
MU. The Full Reservoir Level (FRL) is 630 ft. and the minimum draw down level is 590 ft.
GRIDCO states that the reservoir level of Hirakud is one of the worst this year. It has
also stated that based on the latest reservoir level, irrigation requirement, evaporation
losses and non-monsoon inflows, as projected by the Water Resources Dept., Govt. of Orissa
for the Hirakud Coordination Committee meeting on September, 2000 a generation of 197.41
MU is projected from Sept., 25, 2000 to March, 31, 2001. Taking the actual generation upto
24th September, 2000 during the current year the projected drawal would be
616.72 MU as initially proposed by GRIDCO.
|
6.6.3.11
|
OHPC in its various generation
plans has given the projections as below :-
February, 2000
|
1055 MU (OHPC letter No. 1917 dtd.02.02.2000)
|
October, 2000
|
619.66 MU (OHPC letter No. 14775 dtd.24.10.2000)
|
December, 2000
|
574.04 MU (OHPC letter No. 17221 dtd.22.12.2000)
|
|
6.6.3.12
|
OHPC has stated that there has been a generation of 505.635 MU from 4/2000
to 11/2000 and the anticipated generation during the four months from 12/2000 to 3/2001 is
68.45 MU and thus estimates the total generation at 574.04 MU. As this forecast has been
revised by OHPC based on the latest reservoir levels as on 01.12.2000 and this has been
accepted by GRIDCO, the Commission thinks it prudent to accept the generation figure given
by OHPC and, therefore, accepts the figure of 574.04 MU for the year 2000-01 and a drawal
of 568.30 MU (after accounting for auxilliary consumption).
|
6.6.3.13
|
Rengali : The installed capacity of this power station is 250 MW (5
X 50) with an annual energy availability of 86 MW or 750 MU. GRIDCO in para 2.3.1.2 of the
main text of the BST application has stated that they proposed to procure 924.49 MU during
the year 2000-01. This is also corroborated in the procurement plan given in DF 14. GRIDCO
has further stated that this projection is based on the generation achieved in 1998-99
when reservoir level is closest to current level. As on 31.8.1998 the reservoir level of
Rengali was 115.01 metres compared to 116.32 metres as on 31.8.2000. During the year
1998-99 there is a total drawal of 889.763 MU by GRIDCO from this power station. Going by
logic of GRIDCO power availability from this power station should be close to the figure
of 1998-99. GRIDCOs projection of 924.49 MU from this power station for the year
2000-01 appears to be erroneous and possibly it has been interchanged with that of figures
of Balimela Power Station. OHPC in three successive projections has given three different
figures as given below.
Feb., 2000
|
873 MU (OHPC letter No. 1917 dtd.02.02.2000)
|
Oct., 2000
|
733.01 MU (OHPC letter No. 14775 dtd.24.10.2000)
|
Dec., 2000
|
721.871 MU (OHPC letter No. 17221 dtd.22.12.2000)
|
|
6.6.3.14
|
An examination of the forecast made by OHPC on 22.12.2000 shows that
645.502 MU has been generated from 4/2000 to 11/2000. The anticipated generation from
12/2000 to 3/2001 is 76.369 MU. Thereby a total generation of 721.871 MU is expected to be
generated by 3/2001. As this forecast has been revised by OHPC based on the latest
reservoir levels as on 01.12.2000 and this has been accepted by GRIDCO, the Commission
thinks it prudent to accept the generation figure given by OHPC and, therefore, accepts
the figure of 721.871 MU for the year 2000-01 and a drawal of 714.65 MU.
|
6.6.3.15
|
Balimela : This is a 360 MW power station with availability of 135
MW or 1183 MU. GRIDCO in para 2.3.1.3 of the main text of the BST application has stated
that they proposed to procure 870.04 MU for the ensuing year. This assumption is based on
the actual generation for five months (April to August, 2000) and forecast for balance
period Sept. to Mar. 2001) which is based on that achieved for the same months till FY
1997-98, when the reservoir level is closest to the current level till 2000. As on 31.8.97
Balimela reservoir level was 1456.7 ft. compared to 1456.5 ft. as on 31.8.2000. During the
year 1997-98 GRIDCO had drawn 891.48 MU. GRIDCOs projection of 870.04 MU in DF 14
seems to have been interchanged with that of the generation figure of Rengali power
station. OHPC made three projections during the year 2000 about generation of this power
station as given below.
Feb., 2000
|
1100 MU (OHPC letter No. 1917 dtd.02.02.2000)
|
Oct., 2000
|
1070.135 MU (OHPC letter No. 14775 dtd.24.10.2000)
|
Dec. , 2000
|
1005.892 MU (OHPC letter No. 17221 dtd.22.12.2000)
|
|
6.6.3.16
|
An examination of the forecast made by OHPC on 22.12.2000 shows that
802.949 MU has been generated from April - November, 2000. The anticipated generation from
December, 2000 to March, 2001 is 202.943 MU. Thereby a total generation of 1005.892 MU is
expected to be generated by March, 2001. As this forecast has been revised by OHPC based
on the latest reservoir levels as on 01.12.2000 and this has been accepted by GRIDCO, the
Commission thinks it prudent to accept the generation figure given by OHPC and, therefore,
accepts the figure of 1005.892 MU for the year 2000-01 and a drawal of 995.83 MU.
|
6.6.3.17
|
GRIDCO does not seem to have exercised adequate caution while submitting
the estimate of generation from Rengali and Balimela power stations. The Commission has
noted with displeasure the indifferent attitude shown by GRIDCO in its filing in this
regard.
|
6.6.3.18
|
Upper Kolab : This power station located in Southern Orissa has an
installed capacity of 320 (4 X 80) MW and the annual energy availability is 95 MW or 832
MU. GRIDCO has made a projection of 541.94 MU for drawal of power from Upper Kolab for the
year 2000-01 based on actual generation for five months from April-August, 2000 and
forecast for the balance period (Sept. - March, 2001) which is based on that achieved for
the same months in FY 1998-99 when the reservoir levels were closest to current level. On
31.8.98 the reservoir level was 850.41 metres as against 849.10 metres on 31.8.2000. As on
01.12.2000 the reservoir level is 850.16 metres. Generation projection made by OHPC for
this power station on three different occasions is given below.
Feb., 2000
|
725 MU (OHPC letter No. 1917 dtd.02.02.2000)
|
Oct., 2000
|
518.81 MU (OHPC letter No. 14775 dtd.24.10.2000)
|
Dec. ,2000
|
518.81 MU (OHPC letter No. 14775 dtd.24.10.2000)
|
|
6.6.3.19
|
An examination of the forecast made by OHPC on 22.12.2000 shows that
402.218 MU has been generated from April - November, 2000. The anticipated generation from
December, 2000 to March, 2001 is 122.548 MU. Thereby a total generation of 524.766 MU is
expected to be generated by March, 2001. As this forecast has been revised by OHPC based
on the latest reservoir levels as on 01.12.2000 the Commission thinks it prudent to accept
the generation figure given by OHPC and this has been accepted by GRIDCO, therefore,
accepts the figure of 524.766 MU for the year 2000-01 and a drawal of 519.52 MU.
|
6.6.3.20
|
The total drawal from the four generating
stations of OHPC approved by the Commission is in Table : 15.
Table : 15
|
(Figures in MU) |
Hirakud
|
568.30
|
Rengali
|
714.65
|
Balimela
|
995.83
|
Upper Kolab
|
519.52
|
Total drawal
|
2798.30
|
|
6.6.3.21
|
Upper Indravati : The firm availability of Upper Indravati Hydro
Electric Project with a proposed installed capacity of 4X150 MW is 1942.38 MU. The first
and second units of the generating station were commissioned in 1999-00. The third unit
was commissioned during September, 2000 and the fourth unit is likely to be commissioned
in February, 2001. GRIDCO had initially proposed to procure 1263.02 MU in the ensuing year
and has explained that evacuation of Upper Indravati generation is constrained by the
single 315 MVA auto-transformer and the single 400 kV Rengali-Jeypore PGCIL feeder and
evacuation is also affected by shut down. The Commission in its BST order dtd. 30.12.99
(Case No. 12 of 99) had directed GRIDCO to concentrate on better evacuation facilities for
drawing more power from Indravati.
|
6.6.3.22
|
OHPC in its letter No. 1917 dtd.02.02.2000 had already indicated GRIDCO
its capability of supplying 1800 MU during 2000-01. Even in its latest generation plan
dtd. 22.12.2000 OHPC projects a generation of 1727.715 MU. Contrary to this, GRIDCO had
initially estimated only a drawal of 1263.02 MU from this power station for the year
2000-01 citing constraint in evacuation. In this connection, in response to
Commissions query GRIDCO has clarified that due to non-availability of towers,
conductors and due to right off way problem the 220 kV Indravati-Theruvali DC line (1st
line) could not be completed. GRIDCO has stated that every effort is being made to
complete this line within this Financial Year.
|
6.6.3.23
|
An examination of the forecast made by OHPC on 22.12.2000 shows that
994.64 MU has been generated from April - November, 2000. The anticipated generation from
December, 2000 to March, 2001 is 733.075 MU which is equivalent to 275 MW. Thereby a total
generation of 1727.715 MU is expected to be generated by March, 2001. In a fresh filing
made on 02.01.01 termed as Revision to rejoinder to queries and objections raised during
hearing on the BST Application FY 2001 GRIDCO has revised its procurement schedule from
Indravati as proposed by OHPC. As this forecast has been revised by OHPC based on the
latest reservoir levels as on 01.12.2000 and accepted by GRIDCO now, the Commission thinks
it prudent to accept the generation figure given by OHPC and, therefore, accepts the
figure of 1727.715 MU less auxilliary i.e. 1710.44 MU for the year 2000-01.
|
6.6.3.24
|
From the above analysis of hydro generation availability, it is estimated
that GRIDCO would be able to draw a total of 4810.74 MU of Hydro power within the State
during 2000-01 as detailed below :-
Four generating stations of OHPC
|
2798.30 MU
|
Machhkund
|
302.00 MU
|
Indravati
|
1710.44 MU
|
|
------------------------- |
|
4810.74 MU
|
|
6.6.3.25
|
Since the Commission has estimated the power requirement for 2000-01 at
11011.39 MU, the balance requirement i.e. (11011.39 - 4810.74) 6200.65 MU has to be
purchased from other sources.
|
6.6.4
|
Dedicated Thermal Power Stations
|
6.6.4.1
|
Talcher Thermal Power Station (TTPS) : This 460 MW generating
station located almost at the centre of the State is owned and operated by NTPC but fully
dedicated for the State. In terms of the PPA entered between GRIDCO (OSEB) and NTPC the
plant load factor of TTPS was to be maintained at 62.78% with an auxiliary consumption of
11.75% for 1999-00. Since TTPS is a dedicated power station of the State, its entire fixed
cost has to be paid by GRIDCO on account of contractual obligation. GRIDCO had prepared
the procurement plan for TTPS by considering the actual generation of past 5 months and
adopting for the balance forecast provided by NTPC and has arrived at the figure of
2108.72 MU for the year 01. During the year 1999-00 GRIDCO has drawn 2035.96 MU.
|
6.6.4.2
|
GRIDCO has submitted that NTPC in December99 proposed a generation
plan for TTPS indicating a station generation of 2538.65 MU (PLF - 63%). Subsequently NTPC
filed a petition before the CERC to approve TTPS tariff and provided GRIDCO the indicative
tariff computation for FY 01 to FY 05 which shows a generation of 2039 MU for FY 01 to 05
which corresponds to a PLF of 57.5%. NTPC has justified this reduction as the PLF was
57.25% for FY 00 and 55.9% in first 5 months of the year 2000-01. Further, NTPC has
increased the auxiliary consumption to 12% from 11.75%.
|
6.6.4.3
|
The PPA for TTPS was for a period of 5 years with effect from 08.03.95.
Clause 14 of the said PPA provides that the agreement shall continue to operate till the
agreement is formally reviewed, extended or replaced. On account of clause 14 of the PPA,
the Commission considers the quantum of generation should be calculated at a PLF of 62.78%
as was existing for the year 1999-00 until a final decision is taken on the matter by CERC
and a fresh PPA is signed with GRIDCO. Thus the Commission approves a drawal of 2232.53 MU
for the year 2000-01 which is within the target set by NTPC for TTPS in their generation
plan given in December, 1999.
|
6.6.4.4
|
Ib Thermal (OPGC) : Orissa Power Generation Corporation owns the
thermal generating stations at Ib with an installed capacity of 420 MW. The normative
availability at a plant load factor of 68.49% of Ib TPS is 380.10 MW i.e. 2280.57 MU.
During 1999-00, 2839.67 MU was drawn by GRIDCO from this station.
|
6.6.4.5
|
GRIDCO in para 2.3.5 of the main text of BST application has stated that
the procurement schedule of OPGC is based on actuals for five months and generation &
maintenance schedule provided by OPGC for the balance period.
|
6.6.4.6
|
OPGC in their generation plan of 25.01.2000 had projected station target
generation of 2900 MU with auxilliary consumption of 290 MU thereby showing a net
availability of 2610 MU at GRIDCO bus. As GRIDCOs projection of 2658.63 MU is close
to OPGCs generation schedule, the Commission accepts the figure of 2658.63 MU for
the year 2000-01 from this station.
|
6.6.5
|
Power Purchase from Central Power Stations
|
6.6.5.1
|
Central Generating Stations : GRIDCO has submitted that Orissa has
a share in NTPC stations located in the Eastern Region as well as Chukha Hydro Electric
Project of Bhutan and a share in Rangit Hydro Electric Project of Sikkim from which GRIDCO
is unwilling to procure power because of its high cost. The energy available to GRIDCO
depends on the generation and share in these stations in a month. GRIDCO has also
submitted a statement of energy drawal for the first five months of the FY 2001 in its
filing. The Commission considers that this drawal from Central Generating Stations should
be limited to the barest minimum in keeping with the concept of least cost combination of
power procurement, contractual obligation with the central generating station and
inadvertent power flow to the system. The Commission, therefore, decides to limit the
quantum of drawal from the central generating stations for the pooled power to the actual
quantity drawn during the first five months of FY 2001 only as more than that quantity
cannot be accommodated in the least cost combination of power procurement for consumers of
Orissa. Any extra purchase from central generating station can be made only for export
outside Orissa in a commercially remunerative arrangement.
|
6.6.5.2
|
Rangit : This is a 3X20 MW hydro station in Sikkim that commenced
generation from February, 2000. GRIDCO has been assigned a share of 10 MW by CEA on
17.4.2000 and booked on first charge basis on a provisional rate of 211 paise/unit for FY
2000-01 as approved by CERC. GRIDCO has stated that they have intimated Member Secretary,
EREB on 14.8.2000 about their unwillingness to procure this costly power from Rangit HEP
and has requested for no booking on account of this HEP from August, 2000. GRIDCO has not
considered any procurement from Rangit HEP for the current years application except
14.61 MU that was assigned to it for the period of April-July, 2000 as per actual drawal.
The Commission approves a drawal of 14.61 MU from Rangit for FY 2001.
|
6.6.5.3
|
Chukha : Orissa has a share of generation from Chukha Hydro Power
Station in Bhutan which is received through the Eastern Regional Electricity Grid. During
the year 1999-00 GRIDCO had drawn 148 MU from this station. GRIDCO has proposed a drawal
of 214.59 MU based on monthly share of 17.4% and actual drawal upto date of filing. Based
on the principle dealt in para 6.12.1 of this order Commission approves a drawal of 132.64
MU for the FY 2000-01.
|
6.6.5.4
|
Talcher Super Thermal Power Station (Kaniha) : This generating
station with an installed capacity 1000 MW (2 X 500) is owned and operated by the National
Thermal Power Station. Orissa has an allocated share of 26.2% in this generating station
which works out to 262 MW. During 1999-00, GRIDCO had drawn 495.681 MU. For the year
2000-01, GRIDCO proposes a drawal of 991.09 MU. The Commission approves a drawal of 309.69
MU.
|
6.6.5.5
|
Farakka Super Thermal Power Station (West Bengal) : This is another
generating station owned and operated by National Thermal Power Corporation with an
installed capacity of 1600 MW. Orissa has an allocated share of 14.69% i.e. 235 MW in this
generating station. During 1999-00, GRIDCO had drawn 238.307 MU and the proposed drawal
for the year 2000-01 is 432.32 MU. The Commission approves a drawal of 90.01 MU.
|
6.6.5.6
|
Kahalgaon Super Thermal Power Station (Bihar) : Installed capacity
of this generating station is 840 MW. Orissa has an allocated share of 16.07% i.e. 135 MW.
During 1999-00 Financial Year 5.875 MU were drawn from this station. Projection for the
year 2000-01 made by GRIDCO is 91.93 MU. As no energy has been drawn from this station
during the months April-August, 2000, the Commission, therefore, assigns nil drawal from
this station for the purpose of least cost combination of power procurement.
|
6.6.5.7
|
Captive Power Plants (CPPs) : The Captive Power Plants of the State
supplied 650.263 MU to GRIDCO in 1999-00. The power supply from these stations is not firm
in nature and is supplied to the system as and when available and required. GRIDCO has
stated that procurement from CPPs during the months May-July, 2000 was between 20 to 25 MU
per month. The procurement from CPPs for the balance months has been restricted to the
levels of May-July, 2000 considering substantial cut back in generation by NALCO. GRIDCO
has, accordingly proposed to draw 254.53 MU from the CPPs. Some of the objectors have
suggested that drawal from CPPs should be maximised. According to our analysis, the cost
of power of CPP is cheaper than the total cost/unit from the central stations including
Chukha Hydro Electric Project. This has been a poor hydrology year and Commission has
already advised the licensee to maximise drawal from CPPs for the FY 2000-01. After taking
into consideration the power availability from OHPC, OPGC, TTPS and Central Generating
Stations the balance requirement of power i.e. 762.53 MU should at least be drawn from the
CPPs within the State. Therefore, the Commission approves a drawal of 762.53 MU from the
Captive Power Plants.
|
6.6.5.8
|
A summary of GRIDCOs proposal for
purchase of power generating station wise and the Commissions approved quantum of
purchase is given in Table : 16.
Table : 16
Purchase of Power
|
GRIDCOs proposal for FY 00-01 (in MU)
|
Commissions approval for FY 00-01 (in MU)
|
OHPC (Hirakud, Balimela, Upper Kolab, Rengali)
|
2953.18
|
2798.30
|
Machhkund (OHPC)
|
288.68
|
302.00
|
Indravati (OHPC)
|
1263.02
|
1710.44
|
TTPS
|
2108.72
|
2232.53
|
OPGC
|
2658.63
|
2658.63
|
CPP
|
254.53
|
762.53
|
Total Orissa
|
9526.75
|
10464.43
|
Rangit
|
14.61
|
14.61
|
Chukha
|
214.59
|
132.64
|
TSTPS
|
991.09
|
309.69
|
FSTPS
|
432.32
|
90.01
|
KSTPS
|
91.93
|
0.00
|
Total EREB
|
1744.54
|
546.96
|
Total GRIDCO purchase
|
11271.29
|
11011.39
|
|
6.7
|
Cost of Power
|
6.7.1
|
GRIDCO in para 2.3 in the main text of the BST application have stated
that the procurement plan has been developed on a monthly forecast of demand and supply to
reflect the reality of load despatch and demonstrate merit order procurement. The cost of
procurement is not linear and depends on the magnitude of purchase in a month in respect
of central stations. Therefore, aggregation of power purchase will mean ignoring the
despatch order and the cost implication. GRIDCO, therefore, has proposed a monthly
forecast unlike annual aggregation to account for the seasonal availability of hydro power
and also to take care of scheduled maintenance of various generating stations.
|
6.7.2
|
The Commission has examined this suggestion of GRIDCO. It is observed that
GRIDCO is dependent on purchase of power from OHPC including Upper Indravati and
Machhkund, OPGC, TTPS, CPPs within the State and the central generating stations. Bound by
the PPAs, GRIDCO has to pay the fixed cost in respect of all the dedicated stations within
the State. Costing of power on monthly basis from the dedicated stations will not make a
difference at the normative level of operation as the fixed costs have to be paid
calculated on an annual basis.
|
6.7.3
|
An accurate level of monthly requirement is yet to be established through
a scientific method of load forecasting by distribution companies. As far as the central
generating stations are concerned, the cost per unit of these stations is variable in
nature and the rate of this power can be correctly ascertained only after the actual level
of generation is known at the end of the year. The Commission, for determination of the
cost of power of central generating station, has relied on the normative parameters
subject to adjustment at the end of the year. Keeping the above position in view, the
Commission has calculated the cost of power based on the annual requirement of GRIDCO for
the year 2000-01.
|
6.7.4
|
Implementation of the Availability Based Tariff (ABT) will require
accurate level of forecasting linked to financial penalty/incentive for over drawal and
under drawal. Unless correct load forecasting, generation scheduling, variation in load
pattern is communicated online enormous financial implications to the utilities will be
unavoidable. Keeping this object in view it is time that both the distribution licensee as
well as the Bulk Supply and Transmission licensee must prepare the ground work for
implementation of the scheme by having frequency related metering in position wherever
required along with communication links and load forecasting arrangements. Therefore, the
technique of annual aggregation now being followed will undergo a sea change once ABT in
place.
|
6.7.5
|
The cost of power in respect of generating companies and generating
stations, analysed and approved by the Commission in the following paragraphs, are best
estimates of the Commission based on extant rules and orders of appropriate authorities,
currently valid PPAs and other relevant factors. They do not supplant the jurisdiction of
other statutory authorities like Central Electricity Regulatory Commission to determine
the rate of power generated by central sector generating stations and transmission charges
payable to the central transmission utility, changes in statutory rates like income tax,
water cess and changes in contractual provisions.
|
6.7.6
|
OHPC
|
6.7.6.1
|
Machhkund : The cost of power from Machhkund is projected as 8
paise/unit as in the previous year 1999-00. This cost is accepted by the Commission for
the year 2000-01.
|
6.7.6.2
|
Hirakud, Rengali, Balimela and Upper Kolab : GRIDCO has submitted a
tariff calculation sheet prepared by OHPC for purchase of power from OHPC for the year
2000-01 (OERC Form TRT-1). The interim PPA for the Financial Year 1998-99 to FY 2000-01
between OHPC and GRIDCO has been separately submitted by GRIDCO to the Commission for
approval on dtd. 27.7.2000 (ED-8). This has been recorded as a proceeding by the
Commission vide Case No. 15/2000 and the matter is under process for finalisation. GRIDCO
in its application at para 2.4.1 has stated that the interim PPA submitted to the
Commission proposes rate of 50.07 paise/unit for energy supplied by these stations and is
adopted for this application. GRIDCO has further stated that OHPC cost is taken as
variable cost (given the provisions of the interim PPA) as against treating this cost as
fixed in the previous years BST application which reflected the then prevailing
arrangement. An examination of the bills (April-August, 2000) raised on GRIDCO shows that
OHPC is billing GRIDCO @ 49 paise/unit (Addl. ED-6). Clause 6 of the interim PPA is
reproduced below :-
"The provisional tariff for sale of energy from OHPC power stations to GRIDCO for
the year 1998-99, 1999-00 & 2000-01 shall be 49 paise/unit as indicated at Annex-I.
Energy supplied in shall be 49 paise/unit as indicated at Annex-I. Energy supplied in
committee will be treated as secondary energy, the cost of which will be paid in
accordance with OERC."
|
6.7.6.3
|
The rate of 50.07 paise/unit as proposed by GRIDCO is not acceptable to
the Commission as the parties in the interim agreement already agreed to a provisional
tariff of 49 paise/unit for the period of interim agreement. Since the power purchase
bills by OHPC are being raised @ 49 paise/unit, the Commission, therefore, approves a rate
of 49 paise/unit for 2000-01 subject to final approval of the PPA and adjustment of cost
of power, if any, at an appropriate date. OHPC being a dedicated station of the State, the
expenses on this account may be treated as a part of fixed cost even though the total cost
payable to OHPC is related to the quantum of energy supplied by OHPC which may be variable
in nature.
|
6.7.6.4
|
Upper Indravati Hydro Electric Project (UIHEP) : GRIDCO has
submitted that according to PPA 70% of the total fixed cost shall be charged on
commissioning of the first unit, 80% on commissioning of the second unit, 90% on
commissioning of the third unit and full capital cost recovery at commissioning of the
fourth unit. GRIDCO has also stated that until all four units come into operation, the PPA
proposes a single part tariff on energy sent out from this station for the year 2000-01.
|
6.7.6.5
|
The PPA for Upper Indravati was approved by OERC vide order dtd. 23.3.2000
(Case No. 17/99) wherein OERC directed exclusion of Rs.131.68 crores from the project
capital cost for computation of tariff. GRIDCO has stated that it has worked out a tariff
computation based on the reduced project cost. In its tariff computation statement
(TRT-11) the cost of procurement from Upper Indravati has been given as 97.09 paise/unit
for April-September, 2000, 109.23 paise/unit for September-January, 2001 and 121.37
paise/unit for February-March, 2001.
|
6.7.6.6
|
After examination of the proposed rate, the Commission sought
clarification from GRIDCO on the actual interest paid and the loan repayment schedule for
determining the tariff for different stages of the commissioning. In its clarification
dtd.28.10.2000 GRIDCO stated that it had not yet received the interest and loan repayment
schedule from OHPC and it shall be submitting on receipt of the same from OHPC.
|
6.7.6.7
|
This issue was raised again by Director
(Tariff) during the hearing dtd.15.12.2000 as the Commission had in the mean time received
the loan repayment and interest repayment schedule from OHPC. In its clarification to
Director (Tariff) dtd. 23.12.2000 GRIDCO has recalculated the Upper Indravati tariff
(Annex-I) and has revised the rates of Indravati for FY 2001 as given in Table : 17.
Table: 17
Indravati Unit commissioning
|
Percentage of tariff
|
Effective Tariff (paise/unit)
|
Applicable Months In FY 01
|
Unit I & II
|
80%
|
56.54
|
Apr.00 - Sep.00
|
Unit III
|
90%
|
63.61
|
Oct.00 - Jan.01
|
Unit IV
|
100%
|
70.68
|
Feb.01 - Mar.01
|
|
6.7.6.8
|
The rate recalculated by GRIDCO is examined at Commissions end.
Clause 9.3 of the schedule 5 of UIHEP PPA provides that "for calculation of tariff
the approved project cost will be apportioned as detailed below and the designed energy
will be taken as 1942.38 MU.
After commissioning of Unit I
|
70% of the Project Cost
|
After commissioning of Unit II
|
80% of the Project Cost
|
After commissioning of Unit III
|
90% of the Project Cost
|
After commissioning of Unit IV
|
100% of the Project Cost
|
|
6.7.6.9
|
OHPC has intimated that for 2000-01, a sum of Rs.34.93 crores has been
paid towards interest to PFC and Rs.1.6 crores towards guarantee commission. There has
been no payment to Government towards interest. Depreciation has been limited to Rs.30.61
crores which is linked to repayment of PFC loan.
|
6.7.6.10
|
Based on the aforesaid provision the rate re-calculated by GRIDCO in the
Table : 17 for different stages of commissioning is accepted. For the year 2000-01 due to
commissioning in stages the average rate works out to 63.27 paise/unit. The Commission
approves this average rate for the purpose of determination of cost of power from this
station.
|
6.7.6.11
|
With the approval of PPA, it is necessary that the tariff for the year
1999-00 be recalculated by the concerned authorities accordingly.
|
6.7.7
|
Talcher Thermal Power Station (TTPS) : GRIDCO has submitted that
the fixed cost of the station i.e. Rs.183.61 crores is based on a submission filed by NTPC
before CERC for the FY 2000-01. GRIDCO has also stated that NTPC has adopted different
parameters than that existing in the PPA as per the details given below :-
|
6.7.7.1
|
According to GRIDCO, NTPC has stated that the station parameters signed in
its earlier PPA could not be achieved and proposes what is an achievable target. In view
of this argument GRIDCO in its initial filing has adopted the NTPC tariff computation for
FY 2001 which gives a variable charge of 55.66 paise/unit. GRIDCO has proposed a variable
charge of 60.76 pause/unit based on the cost of fuel, (coal and oil) and its calorific
value of the latest bills for August, 2000.
|
6.7.7.2
|
During the course of the tariff hearing GRIDCO was asked to clarify why
the tariff of TTPS system has not been based on the existing PPA which provides for
continuation of the existing terms and conditions till the PPA is
rescinded/revised/renewed. In response to this GRIDCO has replied on 23.12.2000 that the
tariff for TTPS ended on 31.3.2000. As per the ERC Act NTPC has filed a petition before
CERC for approval of tariff as this station is owned by a Govt. of India undertaking i.e.
NTPC even though fully dedicated for the State. NTPC proposes a fixed cost of Rs.184.7
crores for TTPS. The tariff when approved will become effective from 01.4.2000. GRIDCO has
further suggested that if the Commission does not recognise the additional cost as the
tariff norms have not yet been approved by CERC then the additional cost may be allowed as
a surcharge from the effective date of the proposed BST FY 2001 consequent to CERC passing
the order.
|
6.7.7.3
|
After analysis of the proposal of GRIDCO the Commission feels that as CERC
has not yet revised the tariff norms of the extant PPA between NTPC (TTPS) and GRIDCO,
Commission has based its calculation for TTPS in terms of the various parameters for the
year 1999-00 as outlined in the said PPA. The significant parameters are :-
-
Station PLF of 62.78%
-
Auxilliary consumption of 11.75%
-
Heat rate of 3200 K. Cal./Kwh
-
Specific oil consumption 10 ml./Kwh
|
6.7.7.4
|
Fixed Cost : GRIDCO has initially
proposed a fixed cost of Rs.183.62 crores which has been revised to Rs.159.7 crores on
23.12.2000 which has been calculated as Rs.151.44 crores at the Commissions end as
analysed in Table : 18.
Table: 18
(Rs. in crores/Year)
|
|
GRIDCOs Proposal
|
Commissions Approval
|
O&M
|
55.6
|
50.52
|
Depreciation
|
24.5
|
24.48
|
Interest on Loan
|
10.8
|
13.20
|
Return on Equity
|
27.4
|
27.42
|
Interest on Working Capital
|
10.8
|
10.30
|
Addl. FC due to R&M
|
30.6
|
25.52
|
Total Fixed Cost
|
159.7
|
151.44
|
|
6.7.7.5
|
The Commission for the purpose of calculation of fixed cost has accepted
the norms as agreed in the PPA for the year 1999-00 between GRIDCO and NTPC. Hence there
is difference in figures in respect of Operation & Maintenance expenses and the
Interest on Loan calculated by GRIDCO. With regard to Renovation & Modernisation
expenses GRIDCO has considered Rs.150 crores upto FY 2001. But the expenditure towards
R&M for Phase-I and Phase-II upto March, 2000 was found to be Rs.125.09 crores. The
additional fixed cost for this station has been worked out on this investment of Rs.125.09
crores but adopting the norms fixed in the PPA i.e. @ Rs.1.7 lakhs/month for each crore of
additional investment.
|
6.7.7.6
|
Variable Charge : GRIDCO had initially proposed a variable charge
of 60.57 paise/unit as in DF-14 and a variable charge of 60.76 paise/unit was proposed in
Main Text. Subsequently, in its reply dtd. 23.12.2000 GRIDCO has revised the auxilliary
consumption to 11.75% and heat rate 3200 K. Cal/Kwh. On this basis the variable charge
proposed is 59 paise/unit.
|
6.7.7.7
|
Commission has based its calculation of variable cost on the cost of fuel
(coal & oil) and the calorific value has been averaged for a period of 12 months,
based on the cost of coal & oil and calorific value for the first five months of the
year 2000-01 and projection made for the rest of seven months based on the figures of the
months of August, 2000. Accordingly, the Commission approves the variable charge of 58.97
paise/unit.
|
6.7.7.8
|
Miscellaneous Charges : GRIDCO has proposed that as an year end
adjustment, water cess and water charges for the ensuing year are based on the actual
billing in the year 1999-00 and is estimated to be Rs.0.072 crores and Rs.0.569 crore
respectively. Income Tax is estimated at Rs.47.757 crores based on advance tax paid for
April, 99 to February, 2000 and annualised. The Commission approves the amount proposed by
GRIDCO on account of Water Cess and Water Charges and accordingly, approves a figure of
Rs.0.64 crores. The Commission calculated the tax and accepts a figure of Rs.47.76 crores
for the purpose of Income Tax as proposed.
|
6.7.7.9
|
The Commission, therefore, approves a total rate of 148.48 paise/unit as
against a rate of 170.51 paise/unit proposed by GRIDCO.
|
6.7.8
|
Orissa Power Generation Corporation (OPGC) plant at Ib Valley :
GRIDCO in its tariff computation has proposed the fixed cost charge for this plant as
Rs.251.82 crores. The fixed cost computation of GRIDCO as per ED-11 filed with the
Commission is Rs.251.78 crores which is the revised figure in accordance with terms of
PPA. Therefore, the Commission has accepted the figure of Rs.251.78 crores as submitted in
ED-11.
|
6.7.8.1
|
Variable Charge : GRIDCO has proposed the variable charge at 48.24
paise/unit based on the tariff computation in ED-11. The Commission accepts a rate of
48.24 paise/unit against variable charge.
|
6.7.8.2
|
Fuel Price Adjustment : GRIDCO has proposed a FPA of 4.52
paise/unit based on the fuel prices of August, 2000 in DF-14 and while in Main Text they
have proposed 4.46 paise/unit for FPA. This has been examined at the Commissions
end. The cost of fuel (coal & oil) and the calorific value has been averaged for a
period of 12 months, based on the cost of coal & oil and calorific value for the first
five months of the year 2000-01 and projection made for the rest of seven months based on
the figures of the months of August, 2000. Accordingly, the Commission approves the FPA of
4.51 paise/unit.
|
6.7.8.3
|
Miscellaneous Charges : GRIDCO has proposed as year end charges :
-
Incentive of Rs.21.52 crores computed on 87.82% availability
-
Land Tax and Water Cess of Rs.0.92 crores, which is the actual billing to GRIDCO in FY
2000
-
Extra oil consumption due to backing down/tripping of Rs.1.10 crores, which is the
actual billing to GRIDCO in FY 2000
-
Electricity Duty of Rs.0.08 crores, which is the actual billing to GRIDCO in FY 2000
|
6.7.8.4
|
This has been examined at the Commissions end. Incentive has been
taken as Rs.12.39 crores based on drawal of 2658.63 MU without taking deemed generation
into consideration. The other elements of miscellaneous charges of Rs.2.10 crores
comprising of Land Tax & Water Cess, Extra oil consumption and Electricity Duty have
been accepted by the Commission.
|
6.7.8.5
|
On the above basis, the Commission approves a rate of 152.91 paise/unit as
against a unit rate of 156.36 paise/unit proposed by GRIDCO.
|
6.7.9
|
Captive Power Plants (CPPs) : GRIDCO has submitted that the rate of
77 paise/unit for purchase of power from Nalco along with fuel price escalation was agreed
between Nalco, Govt. of Orissa and OSEB on 1st of June, 1994. GRIDCO has
proposed a rate of 93.76 paise/unit based on actual bills by Nalco for August, 2000. This
rate has been accepted by the Commission for power purchase from CPPs.
|
6.7.10
|
Central Power Stations
|
6.7.10.1
|
Transmission Loss : Transmission losses occurring in the central
lines are shared by the constituents of Eastern Region. This loss is calculated at 2.49%
by GRIDCO and accordingly the fixed charge and variable charges are adjusted to account
for the losses in the central transmission system. The losses calculated by the Commission
works out to 2.44% based on the global accounts of April to August, 2000.
|
6.7.10.2
|
Transmission Charge for PGCIL Lines : GRIDCO has stated that Govt.
of India Notification dtd. 04 December, 1998, 11 May, 1999, 14 May, 1999 together notified
tariffs of Farakka, Kahalgaon, Talcher and Chukha transmission system as well as
Rangit/Melli and Rangit/Raman lines. The CERC has passed interim orders for payment of
80%, 88% and 80% of the fixed cost indicated by PGCIL in their application for
Dehri-Karmanasha, Jeypore-Gazuwaka and Budhipadar-Korba transmission lines. PGCIL has
submitted application to CERC for tariff fixation for Rangit-Siliguri and Malda-Bongaigaon
transmission system. GRIDCO has considered the annual fixed charges for all the above
based on the order or application as applicable. GRIDCO has further stated that PGCIL is
eligible for incentive for availability of 95%. GRIDCO has assumed an availability level
of 99% for computation of incentive for the year 2000-01 based on their past performance.
GRIDCO has stated that income tax of Rs.9.413 crores payable by PGCIL based on the amount
paid by PGCIL for FY 2000 has been considered for the FY 2000-01.
|
6.7.10.3
|
GRIDCO has also reported that for recovery of annual maintenance cost of
special type energy meters for Rs.0.05 crores and foreign exchange rate variation of
Rs.5.18 crores is considered for the ensuing year by PGCIL. GRIDCO estimates its share of
transmission charges based on actual forecast drawal from EREB to be Rs.28.86 crores, out
of a total of Rs.314.58 crores as transmission charges for central generating stations in
the Eastern Region.
|
6.7.10.4
|
Computation of transmission charges proposed by GRIDCO was analysed by the
Commission. In their clarification dtd.13.11.2000 to the Commission GRIDCO stated that
towards Jeypore-Gazawaka line GRIDCO has admitted Rs.36.91 crores as per CERC order. In
response to Director (Tariff)s query raised during the hearing they have further
clarified in their rejoinder dtd.23.12.2000 that the Rangit-Siliguri and Malda-Bongaigaon
lines are under commercial operation since 12/98 and 4/2000 respectively. However, the
transmission charges for these two lines are yet to be approved by CERC. It is found from
the PGCIL bills that GRIDCO has been receiving bills on account of Rangit-Siliguri but
bills for Malda-Bongaigaon are yet to be received. It has been decided that for the year
2000-01 the transmission costs of Malda-Bongaigaon lines will not be considered.
Accordingly, as against the proposal of Rs.279.1 crores towards transmission costs for the
various PGCIL lines a total of Rs.219.98 crores is accepted by the Commission.
|
6.7.10.5
|
The proposal of GRIDCO on account of
miscellaneous charges is accepted by the Commission as in Table : 19.
Table : 19
(Rs. in crores)
|
Incentive
|
18.36
|
Income Tax
|
9.41
|
AMC for special type meter
|
0.05
|
Foreign Exchange Rate Variation
|
5.18
|
|
6.7.10.6
|
Therefore, a total of Rs.252.98 crores is accepted for the purpose of
determination of rate of transmission charges for the year 2000-01 to be payable by GRIDCO
on the energy drawn in PGCIL transmission lines, subject to further adjustment on account
of decision of CERC on various issues relating to transmission line costs. Accordingly, a
rate of 13.67 paise/unit is approved as transmission charges payable by GRIDCO for central
transmission system which is exclusive of central transmission loss and when adjusted for
central transmission loss the rate works out to 14.01 paise/unit.
|
6.7.11
|
Chukha : GRIDCO has stated that as per Govt. of India notification
dtd. August 26, 1999 the power purchase cost from Chukha Hydro electric station has been
taken
-
As 100 paise/unit for the period from June-September, 2000 and
-
150 paise/unit for balance period (April-May, 2000 and October, 2000 - March, 2001)
-
A further 5 paise/unit is added to the above rates based on PGCIL letter dtd.Nov.1999 to
the Eastern Region beneficiaries, levied for the Power Trading Corporation (PTC)
|
6.7.11.1
|
The effective procurement cost of GRIDCO is higher and it has to bear
PGCIL line losses and PGCIL transmission charges. The annual average rate/unit of Chukha
power thus has been proposed as 142.27 paise/unit inclusive of central line losses. The
Commission accepts the rates as proposed above as they are based on Govt. of India
notifications. A rate of 142.13 paise/unit is approved for 2000-01 inclusive of
transmission charges and central transmission losses.
|
6.7.12
|
Rangit : GRIDCO has proposed a rate of 233.4 paise/unit inclusive
of central transmission charges and central losses in Table-16 of Main Text for a total
drawal of 14.6 MU from this station. This has been calculated based on the provisionally
approved rate by CERC @ 211 paise/unit for the FY 2000-01. The Commission has based its
calculation on this approved rate and accordingly has worked out a total rate of 230.28
paise/unit inclusive of central transmission charges and central transmission loss.
|
6.7.13
|
Central Thermal Power Station : Under ERC Act, the tariff in
respect of the Central Power Stations will be determined by the Central Electricity
Regulatory Commission from 15.5.99 onwards.
|
6.7.13.1
|
The Ministry of Power, Govt. of India have notified the tariff in respect
of the Talcher Super Thermal Power Station Kaniha (Orissa), Farakka Super Thermal Power
Station (West Bengal), Kahalgaon Super Thermal Power Station (Bihar) under Section 43(A)
of The Act, 1948 prior to 15.5.99. This tariff is, therefore, current and has not been
replaced as yet.
|
6.7.13.2
|
The Commission has analysed the various
parameters for calculation of tariff payable by GRIDCO for drawal of power from Central
Thermal Stations.
Energy sent out ESO
Table : 20
(In MU)
|
Central Thermal Stations
|
Approved by MoP*
|
Actual in FY 00**
|
Forecast by EREB^
|
Proposed by GRIDCO**
|
Talcher STPS
|
5231.86
|
4904.8
|
5396.0
|
5182.6
|
Farakka STPS
|
8489.13
|
6126.8
|
8511.0
|
7628.6
|
Kahalgaon STPS
|
4259.52
|
3862.0
|
4485.0
|
4671.4
|
Total
|
17980.51
|
14893.6
|
18392.0
|
17482.6
|
* Vide letter dtd.9th June, 1999 (ED-23)
** Table-11, Page-19 of Main Text
^ ED-23 |
6.7.13.3
|
GRIDCO has made its ESO forecast for the Central Thermal Stations based on
actual data for five months and the load generation balance report of Eastern Region for
the remaining months of FY 2000-01. The Commission accepts the estimate of GRIDCO and has
based its tariff calculation on this ESO forecast.
|
6.7.13.4
|
Fixed Cost : The fixed cost
proposed by various central thermal stations based on Govt. of India notification is given
in Table : 21.
Table : 21
Central Thermal Stations
|
Fixed cost for FY 00-01 (Rs. crores)
|
Date of Notification
|
Effective till
|
Talcher STPS
|
644.99
|
May 7, 1999
|
March 31, 2000
|
Farakka STPS
|
668.33
|
May 5, 1999
|
March 31, 2002
|
Kahalgaon STPS
|
477.88
|
December 9, 1998
|
March 31, 2000
|
|
6.7.13.5
|
GRIDCO has considered the last available notification rate for the ensuing
year for Farakka and Kahalgaon.
|
6.7.13.6
|
Further in a rejoinder dtd.23.12.2000, GRIDCO has stated that the fixed
costs for Farakka and Kahalgaon have been determined on the basis of audited account of
1996-97 and audited accounts of 1997-98 for Talcher STPS. The impact of additional capital
expenditure capitalised in each FY during the tariff period from 01.7.96 to 31.3.2000 for
FSTPS, 01.8.96 to 31.3.2000 for KhSTPS and 01.7.97 to 31.3.2000 for FSTPS were to be
determined by Central Govt. immediately on finalisation of accounts. As provided in Govt.
of India notification the effect of the foreign exchange variation payable to NTPC were to
be determined by Govt. of India. A petition before CERC for determination of FERV and
expense on capitalisation has been filed by NTPC. Taking into account the recent petition
filed in CERC by NTPC for recovery of foreign exchange variation and capitalisation
expenses, the fixed cost has been calculated by GRIDCO and proposed to the Commission.
|
6.7.13.7
|
This has been examined at Commissions
end. In the absence of any order by CERC the Commission provisionally approves the fixed
cost as per the existing Govt. of India notification subject to final order of CERC.
Accordingly, the fixed cost as proposed by GRIDCO and as approved by the Commission for
the purpose of tariff calculation for 2000-01 is given in Table : 22
Table : 22
(Rs. in crores)
|
Central Thermal Stations
|
GRIDCOs Proposal
|
Commissions Approval
|
Talcher STPS
|
649.21
|
644.99
|
Farakka STPS
|
694.42
|
668.33
|
Kahalgaon STPS
|
492.55
|
477.88
|
|
6.7.13.8
|
GRIDCO has requested the Commission that as no order has been passed by
CERC the Commission should allow the recovery of additional cost as a surcharge from the
effective date of the proposed BST FY 2001 as and when CERC passes the order. The
Commission finds it proper that additional charges if any, on account of CERC order are
recovered by GRIDCO after finalisation of accounts of the corresponding year.
|
6.7.13.9
|
Variable Charge : GRIDCO has
proposed the variable cost charges for central thermal stations based on the prevailing
Govt. of India notification.
Table : 23
Central Thermal Stations
|
Variable charge for FY 00-01 (Paise/unit)
|
Date of Notification
|
Effective till
|
Talcher STPS
|
46.16
|
May 7, 1999
|
March 31, 2000
|
Farakka STPS
|
32.72
|
May 5, 1999
|
March 31, 2001
|
Kahalgaon STPS
|
50.86
|
December 9, 1998
|
March 31, 2000
|
|
6.7.13.10
|
The Commission has accepted the rates as
provided in Govt. of India notification as outlined above. The rates of variable charges
inclusive of adjustment for central line losses proposed by GRIDCO and accepted by the
Commission is given in Table : 24.
Table : 24
(Paise/unit)
|
Central Thermal Stations
|
GRIDCOs Proposal
|
Commissions Approval
|
Talcher STPS
|
33.56
|
33.54
|
Farakka STPS
|
47.34
|
47.32
|
Kahalgaon STPS
|
52.16
|
52.13
|
|
6.7.13.11
|
Fuel Price Adjustment : FPA has been calculated by GRIDCO on the
basis of actual bills for the period April to August, 2000. For the balance period the
parameters (cost and calorific value of coal and oil) as per bill of August, 2000 has been
adopted.
|
6.7.13.12
|
The Commission accepts this principle for
calculation of FPA. The rates of FPA as proposed by GRIDCO and as approved by the
Commission is given in Table : 25.
Table : 25
(Paise/unit)
|
Central Thermal Stations
|
GRIDCOs Proposal
|
Commissions Approval
|
Talcher STPS
|
9.16
|
8.74
|
Farakka STPS
|
39.60
|
38.76
|
Kahalgaon STPS
|
27.83
|
27.16
|
*As proposed in DF-14 given in Main Text. However,
these figures are at variance with figures given in para 2.4.9.3, page 25 of Main Text. |
6.7.13.13
|
Miscellaneous Charges (Income Tax, Incentive, Water Cess and Water
Charges) :
GRIDCO has projected the year-end adjustment for water cess, water charges, incentive and
income tax. All year end charges are based on actual bills of NTPC received by GRIDCO
during FY 1999 and FY 2000. GRIDCO has stated that year-end charges adjusting for the
central line losses for FY 01 is 27.87 paise/unit for TSTPS, 30.46 paise/unit for FSTPS
and 26 paise/unit for KSTPS (para 2.4.9.4 of Main Text).
|
6.7.13.14
|
The Commission has analysed the various charges as below :-
|
6.7.13.15
|
Income Tax has been estimated for all the
three stations based on actual amount paid towards income tax for April, 99 to February,
2000 and annualised as in Table : 26.
Table : 26
(Rs. in crores)
|
Station
|
Paid for Apr.,99 to Feb.00
|
Annualised
|
Talcher STPS
|
95.17
|
103.82
|
Farakka STPS
|
152.27
|
166.11
|
Kahalgaon STPS
|
79.94
|
87.21
|
Total
|
327.38
|
357.14
|
|
6.7.13.16
|
The Commission approves an amount of Rs.357.14 crores towards income tax
for 2000-01 for all these stations which is as proposed by GRIDCO.
|
6.7.13.17
|
In respect of water cess and the
calculations based on the bills of FY 1999-00 for Farakka and Kahalgaon and in respect of
TSTPS it is based on the actuals of FY 2000 (DF-19). A comparative picture of the proposal
of GRIDCO and approval of the Commission in respect of each station is given in Table :
27.
< Table
: 27
(Rs. in crores)
|
Central Thermal Stations
|
GRIDCOs Proposal
|
Commissions Approval
|
Talcher STPS
|
0.09
|
0.09
|
Farakka STPS
|
1.38
|
1.19
|
Kahalgaon STPS
|
0.19
|
0.18
|
|
6.7.13.18
|
Incentive payable to CGS for FY 2001 is
computed on an availability of 90% (PLF + deemed generation) by GRIDCO. For the purpose of
calculation of incentive estimated deemed generation in respect of these stations have
been considered by the Commission based on the performance of first six months i.e. April,
99 to September, 99 as per bills given by NTPC for incentive. According to that
consideration the availabilty in respect of these three stations are given in Table : 28.
Table : 28
Station
|
Income Tax
|
Talcher STPS
|
90.05%
|
Farakka STPS
|
76.12%
|
Kahalgaon STPS
|
83.03%
|
|
6.7.13.19
|
Incentive is payable @ one paise/unit for
PLF exceeding for each percentage rise over the normative PLF of 68.49%. Therefore,
incentive payable for FY 2000-01 in respect of each of the stations approved by the
Commission is in Table : 29.
Table : 29
(Rs. in crores)
|
Central Thermal Stations
|
GRIDCOs Proposal
|
Commissions Approval
|
Talcher STPS
|
40.53
|
42.06
|
Farakka STPS
|
64.85
|
7.94
|
Kahalgaon STPS
|
34.05
|
15.35
|
|
6.7.13.20
|
The rate of miscellaneous charges inclusive
of central line losses as proposed by GRIDCO and as approved by the Commission is in Table
: 30.
Table : 30
(Paise/unit)
|
Central Thermal Stations
|
GRIDCOs Proposal*
|
Commissions Approval
|
Talcher STPS
|
28.58
|
28.87
|
Farakka STPS
|
31.23
|
23.55
|
Kahalgaon STPS
|
26.66
|
22.54
|
*As proposed in DF-14 given in Main Text. However these figures are at
variance with the figures shown in in para 2.4.9.4, page-25 of Main Text. |
6.7.13.21
|
Commission approves a figure of Rs.1164.56
crores towards total cost of power. GRIDCOs proposed cost of power from various
generating stations and the Commissions approved cost in respect of each station is
summarised in Table : 31.
Table : 31
Comparison of Power Purchase Costs for 2000-01
GRIDCOs Proposal
Source |
Require-ment (MU) |
Fixed Cost aise/unit |
Misc.(Intt. W.Cess I.T., etc.) Paise/unit |
Trans. Charge Paise/unit |
Variable Cost Paise/unit |
FPA Paise/unit |
Total Unit Cost Paise/unit |
Total Cost Rs. in crores |
OHPC |
2953.18 |
50.07 |
|
|
|
|
50.07 |
147.87 |
Machhkund |
288.68 |
|
|
|
8.00 |
|
8.00 |
2.31 |
Indravati |
1263.02 |
|
|
|
106.88 |
|
106.88 |
134.99 |
Ib TPS |
2658.63 |
94.72 |
8.88 |
|
48.24 |
4.52 |
156.36 |
415.70 |
TTPS |
2108.72 |
87.08 |
22.86 |
|
60.57 |
|
170.51 |
359.55 |
CPPs |
254.53 |
|
|
|
77.00 |
16.76 |
93.76 |
23.86 |
Chukha |
214.59 |
|
|
16.69 |
125.57 |
|
142.27 |
30.53 |
Rangit |
14.61 |
|
|
17.00 |
216.39 |
|
233.39 |
3.41 |
TSTPS |
991.09 |
128.47 |
28.58 |
16.63 |
33.56 |
9.16 |
216.40 |
200.65 |
FSTPS |
432.32 |
93.35 |
31.23 |
16.07 |
47.34 |
39.60 |
227.59 |
92.38 |
KhSTPS |
91.93 |
108.13 |
26.66 |
17.35 |
52.16 |
27.83 |
232.13 |
21.0 |
Total |
11271.29 |
|
|
|
|
|
127.07 |
1432.23 |
Note : (Central transmission loss of 2.49% for central stations
included) Commissions Approval
Source |
Require-ment (MU) |
Fixed Cost Paise/unit |
Misc.(Intt. W.Cess & I.T., etc.)
Paise/unit |
Trans. Charge Paise/unit |
Variable Cost Paise/unit |
FPA Paise/unit |
Total Cost Paise/unit |
Total Cost Rs. in crores |
OHPC |
2798.30 |
49.00 |
|
|
|
|
49.00 |
137.12 |
Machhkund |
302.00 |
|
|
|
8.00 |
|
8.00 |
2.42 |
Indravati |
1710.44 |
|
|
|
63.27 |
|
63.27 |
108.22 |
Ib TPS |
2658.63 |
94.70 |
5.45 |
|
48.24 |
4.51 |
152.91 |
406.52 |
TTPS |
2232.53 |
67.83 |
21.68 |
|
38.19 |
20.78 |
148.48 |
331.49 |
CPPs |
762.53 |
|
|
|
77.00 |
16.76 |
93.76 |
71.49 |
Chukha |
132.64 |
|
|
14.01 |
128.12 |
|
142.13 |
18.85 |
Rangit |
14.61 |
|
|
14.01 |
216.27 |
|
230.28 |
3.37 |
TSTPS |
309.69 |
127.56 |
28.87 |
14.01 |
33.54 |
8.74 |
212.72 |
65.88 |
FSTPS |
90.01 |
89.80 |
23.55 |
14.01 |
47.32 |
38.76 |
213.42 |
19.21 |
KhSTPS |
|
104.85 |
22.54 |
14.01 |
52.13 |
27.16 |
220.70 |
|
Total |
11011.39 |
|
|
|
|
|
105.76 |
1164.56 |
Note : (Central transmission loss of 2.44% for central stations
included) |
6.8
|
Rebate for Prompt Payment from the Generators
The PPA between the generators and GRIDCO provides for a rebate of 2.5% on the gross power
bill if payment is made through Letter of Credit. 1% rebate on the billed amount is
allowed when payment is made within 30 days. In case of payment beyond the due date,
delayed payment surcharge @ 2% per month on the billed amount is payable by GRIDCO to the
generators.
|
6.8.1
|
GRIDCO has proposed interest on working capital to meet the expenses in
connection with payment of dues of the power bill to the generators. The Sixth Schedule to
The Act, 1948, allows an amount of working capital on items other than the cost of
generation and purchase of energy. The Commission is of the view that unless a reasonable
amount of working capital is allowed to the licensee, it may be difficult on its part to
meet the interest expenses on short term borrowings made to pay for the cost of power in
time to avail the rebate and avoid delayed payment surcharge.
|
6.8.2
|
While the DISTCOs can access the security deposit of the consumers on
which they do not pay any interest to the consumers, they do not pay any security deposit
to GRIDCO for their power purchase. GRIDCO, therefore, does not have any resources to
clear its dues in time if the DISTCOs do not make payment to GRIDCO in time. Considering
the above, the Commission has decided that for the purpose of calculation of revenue
requirement, the cost of power should be calculated at its gross value and not after
excluding rebate. This will offset the shortfall on account of interest on working capital
utilised to pay power dues which is not permitted under the Sixth Schedule of the Act,
1948.
|
6.9
|
Transmission Cost
|
6.9.1
|
The operating expenditure on bulk supply and transmission of energy
excluding cost of power procurement has been grouped under the head Transmission Cost.
|
6.9.2
|
The anticipated expenditure projected by GRIDCO under various components
of the transmission cost has been carefully examined with a view to determine the
expenditure which can be considered to be properly incurred for pass through in tariff for
2000-01. The prudence of expenditure for 2000-01 has been examined with reference to the
audited accounts of GRIDCOs transmission licence for the year 1998-99 as GRIDCO has
not yet submitted the audited accounts for the year 1999-00 due by September, 2000.
|
6.9.3
|
As per licensee condition No.7.2 (d) "the licensee shall, in respect
of each separate business (whether or not held by or carried out through a separate
company) deliver to the Commission, a copy of each interim profit and loss account not
later that three months after the end of the period to which it relates and copies of the
accounting statement and the auditors report not later than six months after the end of
the financial year to which they relate".
|
6.9.4
|
GRIDCO was holder of both the Transmission and Bulk Supply License and
Distribution and Retail Supply Licensee for the year 1998-99. Further as per the transfer
notification No.16019 dt.15.11.1998. GRIDCO is under obligation to finalise the accounts
of Distribution Companies for the year ending 31st March, 1999.
|
6.9.5
|
The accounts of GRIDCO for the year 1998-99 has not been properly
segregated and separate accounts for the Distribution Business have not been submitted.
|
6.9.6
|
The Commission in its letter dt.24.03.2000 did not agree for extension of
time for submission of Annual Audited Accounts for financial year 1998-99, for it did not
find it appropriate to do so.
|
6.9.7
|
The Commission is very much concerned that in spite of the above, the
licensee has failed to submit the audited accounts in time.
|
6.9.8
|
Orissa Small Scale Industries Association, in their written submission
stated that the licensee have not maintained their Annual Accounts properly and correctly.
Hence, the licensee should be directed to produce their Annual Accounts prior to
submission of their application and more particularly, GRIDCO should be directed to
produce copies of annual audited accounts from 1995-96 to 1999-00 and serve a copy on the
objector.
|
6.9.9
|
Countering the objection GRIDCO replied that the audited accounts for
financial year 1998-99 has been made available to OERC. The accounts for the year
financial 1999-00 is being compiled.
|
6.9.10
|
Non-submission of accounts by the licensee as prescribed under para 7.2 of
the licensee is a contravention of the license condition and as provided in condition
24.1, the licensee is liable for penal action under the relevant provisions of the Act.
|
6.9.11
|
The Commission directs GRIDCO to make available, the duly segregated and
audited accounts of transmission and distribution business for the year 1998-99, and
Annual Audited Accounts for the year 1999-00 and also file an explanation separately
defending why action as per law should not be initiated for non-submission accounts for
the year 1998-99 and 1999-00 in time.
|
6.9.12
|
Based on the available information as filed and subsequent clarifications
submitted by GRIDCO, the transmission costs are analysed by the Commission as under :
|
6.10
|
Employees Cost
|
6.10.1
|
GRIDCO in OERC form TRF-13(a) has submitted detailed item wise expenditure
under the head of "Employees Cost" for the year FY 1998-99 (Audited Actuals),
provisional actual for FY 2000 and estimates for FY 2001. According to this estimate
GRIDCO has projected an expenditure of Rs.81.17 crores for the purpose of revenue
requirement excluding an amount of Rs.12.22 crores towards expenses capitalised. The
estimate of FY 2000-01 is based on an annual rise of 3% for basic pay, 10% rise for DA
over the previous year and 6% annual rise in respect of other allowances, bonus, Medical
Allowance, LTC and Misc. expenses. GRIDCO has also estimated an annual rise of 31% on
interim relief of Staff and encashment of EL, staff welfare expenses over the previous
year.
|
6.10.2
|
The data and figure submitted by GRIDCO has duly been examined with the
audited actuals of 1998-99. In respect of pay a rise @ 3% per annum over the base is
considered to determine the basic pay for FY 2000-01. In respect of Dearness Allowance the
10% rise on basic projected by GRIDCO is without any reason. The Commission took into
consideration the prevailing rate of DA of 38% effective from 1st of July, 2000
and has accordingly estimated expenditure for FY 2001. In respect of medical expenses,
reimbursement of house rent, encashment of EL, GRIDCO had estimated certain percentage of
annual rise over the previous year. The Commission considers that these expenses are
related to the basic pay/DA of the employees concern. Keeping these objective in view,
expenses on these heads have been recalculated and indicated in Table : 32.
|
6.10.3
|
Terminal Benefits : GRIDCO has claimed a sum of Rs.27.36 crores in
the revenue requirement towards terminal benefit for the FY 2000-01 as against Rs.11.68
crores allowed in the tariff of 1999-00. During the course of the hearing it was raised by
the Director (Tariff) to indicate the actual amount of terminal benefit granted to the
employees during 1999-00 and the status of accounts of the Pension Trust Fund. GRIDCO in
its clarification has submitted that :
-
The actual amount of terminal benefit granted to the employees during 1999- 00 is
Rs.31.87 crores.
-
Accumulated balance of employers contribution towards Employees Provident Fund in the PF
Trust will be transferred to the Pension Trust after the accounts of 1998-99 and 1999-00
are audited and getting the necessary approval from concerned authorities. The audited
accounts of PF Trust 1997-98 has been attached as ED-9.
-
The transfer of funds from RPFC had been pending before the Hon'ble High Court for a
long time. The judgement in favour of GRIDCO was delivered on 19.12.2000. GRIDCO is in
process of lodging its claim for the transfer of accumulated balance of funds to it. The
same will be transferred to the Pension Trust Funds after its receipt.
-
Rs.150 crores of bonds will be issued by GRIDCO to the Pension Fund as a part of the
transfer scheme, 1996 after finalisation of Pension Trust Account 1998-99 and 1999-00 and
approval of guarantee of state government.
|
6.10.4
|
GRIDCO in clarification to the queries on BST Application for FY 2001 at
para 3.13 has stated that as per the transfer scheme GRIDCO inherited all existing
pensioners of OSEB. Further as per the second transfer scheme GRIDCO is liable for payment
of terminal liabilities for all employees retiring on or before 31st March,
1999. Besides, there has also been revision on minimum basic pension and family pension
drawn from Rs.260/- to Rs.1275/-. All these had significant impact on the payment of
terminal benefits of GRIDCO and are estimated at Rs.25 crores for FY 2000. The same has
been projected on pro-rata basis of for FY 2001 and stands at Rs.27.36 crores.
|
6.10.5
|
The report of the Actuarial Valuer has been submitted to the Commission.
As stated earlier GRIDCO has projected a pro-rated figure for the provision of terminal
benefits considering the basic pay and DA as the base. The Commission agrees to the
concept proposed by GRIDCO and recalculates the provision relating to terminal benefit due
to the change in DA for the year FY 2001. The Commission provisionally accepts the
terminal benefits for Rs.25.22 crores subject to final adjustment as per the audited
accounts for the year 2000-01.
|
6.10.6
|
In the light of above observation, the
relevant figures on Employees Cost and related expenses are reflected in Table : 32.
Table : 32
Details of Employee Cost (Rs. in crores)
Sl No |
Particulars |
Audited account of 1998-99 |
Approved by Commission 1999-00 |
Prop. by Licensee 2000-01 |
Basis assumed by Licensee |
Approved by Commission 2000-01 |
Basis assumed by the Commission |
1
|
Salaries
|
35.15 |
22.08 |
37.28 |
3% Annual rise |
37.28 |
3% Annual rise |
2
|
Over time
|
0.01 |
0.01 |
0.01 |
|
0.01 |
|
3
|
Dearness Allowance
|
13.73 |
27.85 |
18.47 |
10% Rise on basic |
14.17 |
38% of salary |
|
SUB TOTAL
|
48.89 |
49.94 |
55.76 |
|
51.46 |
|
4
|
Other Allowance
|
0.51 |
0.57 |
0.55 |
6% Annual rise |
0.55 |
6% |
5
|
Bonus
|
0.21 |
0.46 |
0.23 |
6% Annual rise |
0.23 |
6% |
6
|
Total Emoluments (1 to 5)
|
49.61 |
50.97 |
56.54 |
|
52.24 |
|
|
Other Staff Cost
|
|
|
|
|
|
|
7
|
Reimbursement of Medical Expenses
|
1.45 |
0.88 |
1.59 |
6% Annual rise |
1.12 |
3% of Basic |
8
|
Leave Travel Concession
|
0.88 |
0.42 |
1.02 |
6% Annual rise |
1.02 |
6% |
9
|
Reimbursement of H.R.
|
3.87 |
2.58 |
4.11 |
3% Annual rise |
5.22 |
14% of Basic Pay |
10
|
Interim Relief of Staff
|
0.30 |
0.00 |
0.34 |
3% Annual rise |
0.34 |
3% |
11
|
Encashment of earned leave
|
- |
- |
- |
|
- |
|
12
|
Honorarium
|
0.08 |
0.06 |
0.08 |
|
0.08 |
|
13
|
Payments under Workmen Compen-sation Act
|
0.02 |
0.05 |
0.02 |
|
0.02 |
|
14
|
Ex-gratia
|
1.10 |
0.16 |
1.28 |
6% Auunal rise |
1.28 |
6% |
15
|
Other Staff Cost
|
0.43 |
- |
0.50 |
|
0.50 |
|
16
|
Total Other Staff Cost (7-15)
|
8.13 |
4.15 |
8.94 |
|
8.09 |
|
17
|
Staff Welfare Expenses
|
0.69 |
0.30 |
0.56 |
10% Annual rise |
0.56 |
|
18
|
Terminal Benefits
|
39.07 |
11.68 |
27.36 |
Pro-rated |
25.22 |
Pro-rated |
19
|
Total (6+16+17+18)
|
97.50 |
67.10 |
93.40 |
|
87.60 |
|
|
Less : Employees Expenses Capitalised
|
12.21 |
9.23 |
12.23 |
|
11.29 |
Pro-rated |
|
Net Employee Cost
|
85.29 |
57.87 |
81.17 |
|
76.31 |
|
|
6.10.7
|
The total Employees Cost chargeable to
revenue is Rs.76.31 crores. A comparative table showing the Employees Cost from 1998-99
onwards is given in Table : 33.
Table : 33
(Rs. in crores)
|
Source |
1998-99 (Audited actual) |
1999-00 (Approved by OERC) |
2000-01 (Proposed by GRIDCO) |
2000-01 (Approved by OERC) |
Employees cost |
97.50 |
67.10 |
93.40 |
87.60 |
Less : Employees expenses capitalised |
12.21 |
9.23 |
12.23 |
11.29 |
Total |
85.29 |
57.87 |
81.17 |
76.31 |
|
6.11
|
Repair & Maintenance Expenses
|
6.11.1
|
GRIDCO has proposed an amount of Rs.23.74 crores towards R&M expenses
for the year 2000-01 (TRF-14). The Commission in its order dtd.30.12.99 had allowed an
amount of Rs.19.84 crores towards R&M expenses, being 1.5% of the gross fixed asset at
the beginning of the year. In the disaggregated audited accounts for the year 1997-98,
expenditure on this head was only Rs.9.65 crores.
|
6.11.2
|
In the tariff order dated December 30, 1999, the requirement
of R&M for 1999-00 was calculated assuming a normative of 1.5% of the
gross fixed asset of the company, a practice followed in PGCIL who also
operate a transmission system like GRIDCO. This normative percentage was
being applied on the re-valued assets of GRIDCO as on 01.04.1996 with
subsequent additions. Applying this percentage on the fixed asset of
Rs.1322.00 crores at the beginning of the year, a sum of Rs.19.84 crores
was allowed for R&M expenses for 1999-00 against Rs.17.36 crores
approved by the Commission for the year 1998-99. Actual R&M
expenditure as revealed from the audited accounts is Rs.12.36 crores for
1998-99 and provisional figure for the year 1999-00 is Rs.13.46 crores.
GRIDCO has stated that the R&M programme suffered during 1999-00 on
account of cyclone and subsequent shift in efforts to rehabilitation of
affected lines and sub-station. The material meant for R&M in FY 2000
have been procured and its utilisation is under progress due to above
delay.
|
6.11.3
|
Higher provision in the previous tariff orders towards R&M expenses
entitled licensee to recover more than what they actually spent. As stated earlier the
material procured in the year 1999-00 is under the process of utilisation. The expected
rise in expenditure as shown above for the year 1999-00 is 9% over 1998-99. Accordingly a
percentage rise of 9% is considered prudent for estimating the requirement towards R&M
expenses over the provisional figure of 1999-00. Hence the Commission approves an amount
of Rs.14.67 crores as reasonable for the financial 2000-01.
|
6.11.4
|
A comparative picture of R&M expenses
is given in Table : 34.
Table : 34
(Rs. in crores)
|
1998-99 Commissions Approval |
1998-99 Actuals |
1999-00 Commissions Approval |
1999-00 Provisional |
2000-01 Gridcos Proposal |
2000-01 Commissions
Approval |
17.36 |
12.36 |
19.84 |
13.46 |
23.74 |
14.67 |
|
6.12
|
Administration & General Expenses
|
6.12.1
|
A&G expenses include expenses on property related expenses,
communication expenses, professional charges, other expenses including expenses on
auditing, advertisement, materials related expenses and licensee fees. GRIDCO proposes an
amount of Rs.19.85 crores towards A&G expenses for the FY 2000-01 excluding expenses
capitalisation of Rs.1.47 crores. The actuals as per audited accounts of 1998-99 and
provisionals for 1999-00 is of the order of Rs.18.28 crores and Rs.18.05 crores
respectively. GRIDCO in its application while projecting an annual growth forecast of 4.2%
has stated that cost control measures has helped contain the rise in A&G expenses.
Commission does not find any perceptible austerity measures and obviously no reduction of
cost. Moreover the earlier order of the Commission has not been adhered to as the licensee
has spent Rs.19.38 crores against Commissions approval of Rs.11.91 crores. The
Commission, therefore, considers an annual increase of 8% towards inflation over the
previous years approved figure of Rs.10.88 crores excluding Rs.1.03 crores as
expenses to be capitalised. In addition to above an amount of Rs.50 lakhs is allowed
towards licence fee. The Commission accordingly approves an amount of Rs.12.25 crores
towards A&G expenses excluding capitalisation expenses of Rs.1.47 crores for 2000-01.
Any expenditure on A&G expenses incurred over and above the approved figure without
proper justification cannot be allowed to be passed on to the consumers.
|
6.13
|
Approved Investment for Restoring Damages
|
6.13.1
|
The Commission in its order dtd.13.7.2000 has approved Rs.13.27 crores
towards restoration of damages caused by cyclone in 1999 and directed GRIDCO to treat the
same as deferred revenue expenditure for recovery over a period of three years.
Accordingly, GRIDCO has proposed to recover an amount of Rs.4.42 crores for the FY
2000-01.
|
6.13.2
|
Some of the objectors objected to the inclusion of expenditure on
restoration damages due to cyclone in revenue requirement. Orissa Grahak Mahasangha has
stated that as per the press note, the Govt. of India as well as the State Govt. have
advanced funds to GRIDCO for restoration of damages. More over GRIDCO must have insured
its installations and got compensated by the insurer. Any part of the expenditure towards
restoration of cyclone damage should not be reflected in the BST. Similarly,
representatives of UCCI & CII stated that the expenditure on accounts of restoration
of damage due to cyclone should not be passed on to the revenue account but may be treated
as a part of capital expenditure. CII has stated that due to cyclone damage lot of major
maintenance work will be charged to capital expenditure. An amount of Rs.4.42 crores
towards restoration of cyclone damage is for a special repair and hence is to be charged
to capital account. However, if OERC has agreed earlier for this provision in revenue
account this may need reconsideration.
|
6.13.3
|
Some of the objectors have also stated that GRIDCO should itself bear the
cost of damage if no insurance has been done by them and if at all the provision of
Rs.4.42 crores is included it should be considered for interest only and not for capital
base determination as it does not add to any additional capital benefit.
|
6.13.4
|
The Commission has taken into consideration the objections raised by
various objectors about the treatment of expenditure for restoration of damages due to
cyclone. GRIDCO stated in their clarification dtd.08.01.2001 that they have received a sum
of Rs.4.00 crores as grant from Govt. of Orissa.
|
6.13.5
|
Regarding objectors view of treating this capital expenditure or
revenue expenditure have been examined. The Commission did not consider the expenditure on
account of restoration of damage due to cyclone as capital expenditure as it is of revenue
nature. Such expenditure were intended for restoring the assets to its original level of
use and therefore, it did not add to the asset base of the company. Passing of the
expenditure considered reasonable in the revenue requirement in one go would have burdened
the consumers and given a rate shock. The Commission therefore, vide its order
dtd.13.7.2000 directed that expenditure of Rs.13.27 crores is allowed as expenditure for
this purpose of restoration of cyclone damage. The allowed expenditure of Rs.13.27 crores
shall be treated as deferred revenue expenditure to be recovered through tariff amortised
over a period three years. Interest obligation if any accrued for the purpose of funding
the aforesaid service, R&M shall be eligible for recovery through tariff. Hence,
Rs.4.42 crores is accepted as an expenditure for calculation of revenue requirement the
year 2000-01.
|
6.14
|
Interest on Loan
|
6.14.1
|
In para 3.1.6 of its application, GRIDCO has under the head "Interest
on Long Term Liabilities" proposed interest expense chargeable to revenue account at
Rs.173.48 crores excluding interest during construction of Rs.63.92 crores for the year
2000-01 totalling to Rs.237.40 crores. The total loan liability of GRIDCO estimated to be
Rs.2192.89 crores as on 31.3.01.
Item wise analysis of loans are made hereafter.
|
6.14.2
|
Securitisation of power purchase dues :
The interest claimed relate to Govt. Guaranteed bonds amounting to Rs.667.56 crores
(Addl. DF-24) raised during the financial year 1997-98 and 1998-99 to meet the current
liabilities for payment to the various generating agencies towards cost of power purchase.
Due to the failure of GRIDCO to make payment to the generators for outstanding dues, bonds
were issued with the guarantee of the State Government for securitising the dues of the
generators. The details submitted by GRIDCO with regard to various bonds issued by them
were provided in Addl. DF-24 in the clarification to queries in October, 2000. The same is
reproduced in Table : 35.
Table : 35
(Rs. in crores)
|
Particulars of Bond |
15% Bond I/98 (Pvt.Placement) allotted on 20.03.98
|
15.25% Bond II/98(Pvt.
Placement) allotted on 20.10.98 |
15% Bond III/98
(NTPC) allotted on 1.4.98 |
15% Bond IA/98
(OPGC) allotted on 1.4.98 |
15% Bond IB/99
(OHPC) allotted on 1.2.99 |
15% Bond IC/99
(NALCO) allotted on 1.2.99 |
Total GRIDCO issued Bond |
Principal Amount o/s as on 1.4.96
|
|
|
|
|
|
|
|
Principal Amount o/s as on 1.4.97
|
|
|
|
|
|
|
|
Principal Amount o/s as on 31.3.98
|
109.48 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
109.48 |
Principal Amount o/s as on 31.3.99
|
109.48 |
198.08 |
200.00 |
60.00 |
50.00 |
50.00 |
667.56 |
Principal Amount o/s as on 31.3.00
|
109.48 |
198.08 |
200.00 |
60.00 |
50.00 |
50.00 |
667.56 |
Principal Amount o/s as on 31.3.01
|
109.48 |
198.08 |
200.00 |
60.00 |
50.00 |
50.00 |
667.56 |
Yr. of Redemption
|
|
|
|
|
|
|
|
Dt. of Redemption
|
|
|
|
|
|
|
|
Rate of Interest
|
|
|
|
|
|
|
|
Interest for the year 98-99
|
16.42 |
13.41 |
30.00 |
9.00 |
1.21 |
1.21 |
71.25 |
Interest for the year 99-00
|
16.42 |
30.21 |
30.00 |
9.00 |
7.50 |
7.50 |
100.63 |
Interest for the year 00-01
|
16.42 |
30.21 |
30.00 |
9.00 |
7.50 |
7.50 |
100.63 |
|
6.14.3
|
The bonds intended for securitisation of Rs.667.56 crores are the
continuation of balance since 31.3.99 as indicated in the table above. Other than
providing a statement about bonds and about acceptance of the entire loan liability GRIDCO
has not made any specific request in this years application for consideration of
interest on bonds even though the same was explicitly disallowed by the Commission in the
tariff order 1999-00. It is also to be stated here that the issue of securitisation of
dues for the year 1999-00 is before the Commission as a separate filing. The interest on
these bonds for Financial Year 2000-01 is Rs.100.63 crores.
|
6.14.4
|
GRIDCO received a loan of Rs.120 crores on 27.3.99 from Govt. of Orissa
for payment to OPGC (Addl. DF-23). The interest on account of this Govt. loan for the FY
2001 is Rs.15.60 crores calculated @ 13%. Thus the total interest on account of
securitisation of dues and Govt. loan towards meeting the power purchase liability of
GRIDCO works out to Rs.116.63 crores.
|
6.14.5
|
In this connection, Shri R.C. Padhi, Chief Engineer -Electrical (Retd.) in
his objection had stated that interest on bonds towards arrear energy dues and interest on
loans not for capital formation should not be allowed. Shri R.P. Mohapatra, Chief Engineer
Electrical & Member (Retd.), OSEB also objected to the passing of interest on GRIDCO
bonds amounting to Rs.100.63 crores to revenue requirement. He has stated that the
Commission has already disallowed it in the last tariff order of GRIDCO. In spite of cash
flow problem, GRIDCO has not taken effective steps to recover its energy bills. In this
connection he stated that the amount payable by DISTCOs as per bills for August, 2000 was
Rs.968.52 crores. The consumers cannot bear the interest cost on account of non-payment of
current liabilities.
|
6.14.6
|
Conversion to bonds became necessary due to the inability of GRIDCO to
realise its receivables from the consumers. Passing on such a burden attributable to the
past action of GRIDCO which should have realised its receivables from the consumers in
time will result in rate shock and will retared the reform process. The logic given by the
licensee that higher financial burden has been avoided by securitisation does not appeal
to us because it is not reasonable to burden the present consumers on account of the past
and present inefficiency of the Licensee in realising its dues. Bonds amounting to
Rs.667.56 crores and the Govt. loan of Rs.120.00 crores for payment of OPGC dues are not
meant for creation of assets or improvement of efficiency or for expenses in respect of
its licensed activity for the current year. Notwithstanding the fact that the petition of
the licensee for securitisation of dues is pending before the Commission, it is decided
that the interest attributable to conversion of bonds and interest on loan against
overdues of power purchase payables are disallowed for the purpose of calculation of
revenue requirement for the FY 2001.
|
6.14.7
|
World Bank Loan
|
6.14.8
|
Loan from HIW
The loan balance for HIW works for construction of 400 kV line from Meramundali to
Mendhasala will be Rs.82.54 crores as on 31.3.2001. Interest including ICICI bill
discounting is claimed @ 15% per annum. Total interest on this account is estimates to be
Rs.6.51 crores (ADF-22).
|
6.14.9
|
State Govt. Loan
The Govt. of Orissa has given a loan of Rs.185.42 crores to GRIDCO for payment of dues of
OPGC towards energy bills and construction of transmission lines. Out of Rs.185.42 crores
GRIDCO utilised Rs.120 crores towards payment of energy bills which has been treated in
para 6.14.4 under securitisation of power purchase dues. Balance amount of Rs.65.42 crores
has been utilised for construction of transmission lines the interest burden on which is
calculated as Rs.8.50 crores @ 13% per annum.
|
6.14.10
|
GRIDCO in their clarification dtd.03.10.2000, stated that Rs.120 crores of
loan taken on 27.3.99 is having a moratorium period upto 27.3.02 and payable thereafter in
twelve equal installments ending on 27.3.14. Repayment terms for balance amount of loan
are yet to be finalised.
|
6.14.11
|
Zero Coupon Bond
GRIDCO had issued a Bond to State Govt. for an amount of Rs.400 crores as per Transfer
Notification dt.01.04.1996. This bond does not carry any interest for the first five
years. FY 2000-01 being fifth year as per Govt. Notification referred above. No interest
is accrued for the financial year 2000-01 on Zero Coupon Bond.
|
6.14.12
|
Loan from Central Govt.
An amount of Rs.11.26 crores was drawn in 87-88 from Central Govt. for transmission
network on which an interest of Rs.1.01 crores for the FY 01 payable has been calculated @
9.25% (TRF-16).
|
6.14.13
|
Loan from PFC
For the purpose of construction of EHT line and sub-stations loan receipt of GRIDCO from
PFC, will be Rs.253.35 crores including working capital loan of Rs.19.43 crores by
31.03.2001 at an interest rate of 16.5% (ADF-25). The interest on PFC loan for the
financial year 2000-01 will be Rs.26.37 crores.
|
6.14.14
|
Loan from REC
The loan receipt from REC Ltd. by GRIDCO for construction of EHT line and sub-station will
be Rs.147.92 crores by 31.3.01 on which an interest of Rs.20.37 crores is payable
(ADF-26).
|
6.14.15
|
LIC Loan
LIC loan of Rs.140.66 crores drawn during the period from 1981 to 1996 carries an interest
rate of 14% per annum. No amount has been drawn after 01.4.96 and no repayment has been
done after 01.4.96. The interest on this account for the year FY 2001 is claimed as
Rs.28.53 crores which includes a compound interest of Rs.12.12 crores and interest of
Rs.33 crores over and above the normal interest of Rs.16.07 crores payable by 31.3.2001.
GRIDCO was asked to clarify why the compound interest of Rs.12.12 crores should be allowed
to be charged to revenue. It is pertinent to note that due to compounding of interest, the
average interest rate goes up to 20.3% from simple rate of interest of 14% (ADF-27).
|
6.14.16
|
GRIDCO in their clarification submitted on 23.12.2000 stated that pending
the settlement of dispute regarding the mortgage of assets the repayment plan is not
finalised.
|
6.14.17
|
OSEB Bonds
GRIDCO inherited public bonds issued by OSEB during 1981 to 1989 to the tune of Rs.109
crores for meeting working capital expenses repayable between FY 1997 to FY 2010 with
varying rates of interest from 7.25% to 11.5%. Interest payable on this account for the
year FY 2001 is Rs.2.44 crores on an outstanding balance of Rs.20.13 crores. As this loan
pertains prior to incorporation of GRIDCO, the Commission considers the interest on this
loan allowable for the purpose of revenue requirement.
|
6.14.18
|
Pension Trust Bond
GRIDCO has claimed an interest of Rs.4.53 crores for the FY 01 for bonds for pension trust
of Rs.30.20 crores. In the note to the account of 1998-99 at para 11 under the heading of
Retirement Benefit it is stated that the bonds to the pension trust fund are yet to be
issued. The audit certificate to the accounts has been issued on 28.9.2000. Since the
bonds are yet to be issued the Commission does not consider it appropriate to allow an
expenditure of Rs.4.53 crores for recovery from the revenue requirement chargeable to the
consumers.
|
6.14.19
|
Short term loan & Cash Credit
GRIDCO has shown a balance of Rs.28.75 crores as short-term loan from bank and Rs.5.26
crores as cash credit for meeting short term working capital needs on which an interest of
Rs.3.51 crores and Rs.0.71 crores has been claimed.
|
6.14.20
|
Capitalisation of Interest
Analysis of the capital expenditure schedule of major investments (in TRF-2), indicated
that a sum of Rs.737 crores excluding interest during construction has been planned for
execution of various transmission projects during 1998-99 to 2000-01.
|
6.14.21
|
Interest during Construction has been projected at Rs.63.92 crores for the
purpose of capitalisation for financial year 2000-01. While examining OERC form TRF-2, it
is revealed that an amount of Rs.12.85 crores has been considered as interest of OECF
Funded Project. But the said loan has not been included in the loan statement (TRF-16 and
TRF-3). Therefore, the Commission is convinced that the sum of Rs.12.85 crores does not
constitute a part of the interest capitalised. As such, the projected estimate of Rs.63.92
crores should be reduced by Rs.12.85 crores. Hence the Commission allows Rs.51.07 crores
towards capitalisation of interest.
|
6.14.22
|
A statement of loans of GRIDCO since the
year ending 1998-99 upto FY 01 is given in Table : 36.
Table : 36
(Rs. in crores)
|
Source |
Closing balances at the end of
FY 97-98 |
Closing balances at the end of
FY 98-99 |
Receipt during the FY 99-00 |
Repayment during the FY 99-00 |
Closing balances at the end of
FY 99-00 |
Estimates of Receipt during FY
00-01 |
Estimates of Repayment during
FY 00-01 |
Closing balances at the end of
FY 00-01 |
LIC
|
|
140.66 |
- |
- |
140.66 |
- |
- |
140.66 |
Central Govt.
|
|
11.26 |
- |
- |
11.26 |
- |
- |
11.26 |
State Govt.
|
|
153.71 |
31.71 |
- |
185.42 |
- |
- |
185.42 |
World Bank
|
|
30.78 |
36.07 |
- |
66.85 |
153.00 |
- |
219.85 |
Commerrcial Bank-W.C. Demand Loan
|
|
10.35 |
- |
10.35 |
- |
- |
- |
- |
Short Term Loan from Banks
|
|
54.67 |
|
40.92 |
13.75 |
25.00 |
10.00 |
28.75 |
Cash Credit
|
|
8.90 |
|
5.64 |
3.26 |
5.00 |
3.00 |
5.26 |
PFC
|
|
205.25
|
42.09 |
0.86 |
246.48 |
6.87 |
- |
253.35 |
REC
|
|
84.53 |
35.19 |
2.28 |
117.44 |
38.58 |
8.11 |
147.92 |
Public Bonds
|
|
27.16 |
- |
4.31 |
22.86 |
- |
2.73 |
20.13 |
Bonds to GoO
|
|
400.00 |
- |
- |
400.00 |
- |
- |
400.00 |
Bonds for Pension Trust
|
|
30.20 |
- |
- |
30.20 |
- |
- |
30.20 |
GRIDCO Bonds
|
|
667.56 |
- |
- |
667.56 |
- |
- |
667.56 |
HIW Loan
|
|
21.07 |
40.46 |
- |
61.54 |
21.00 |
- |
82.54 |
IDBI Bill Discounting
|
|
0.58 |
- |
0.58 |
- |
- |
- |
- |
Total
|
|
1846.68 |
185.53 |
64.93 |
1967.27 |
249.45 |
23.84 |
2192.89 |
|
6.14.23
|
After analysis of facts and figures of the
preceeding paragraph the Commission approves the interest expenses chargeable to revenue
for the year 2001 as Rs.65.51 crores as against Rs.173.48 crores proposed by GRIDCO as in
Table : 37.
Table : 37
Loan and Interest Liability of GRIDCO (Rs. in crores)
Source
|
GRIDCOs proposal |
Commissions
approval |
Average rate |
LIC Loan
|
28.53 |
28.53 |
20.3% |
Loans from Central Government
|
1.01 |
1.01 |
9.0% |
Loans from State Government
|
24.10 |
8.50 |
13.0% |
World Bank Loan
|
18.6 |
18.63 |
13.0% |
PFC Loan
|
26.4 |
26.37 |
10.6% |
REC Loan
|
20.4 |
20.37 |
15.4% |
Public Bonds
|
2.4 |
2.44 |
11.3% |
Bonds for Pension Trust
|
4.5 |
0.0 |
12.0% |
Gridco Bonds
|
100.6 |
0.0 |
15.1% |
HIW Loan
|
6.5 |
6.51 |
9.0% |
ZCB
|
- |
- |
0% |
Short-term Loans from Banks
Cash Credit |
4.2 |
4.22 |
16.5% |
Total in TRF-16
|
237.4 |
116.58 |
|
Less interest capitalised
|
63.92 |
51.07 |
|
Interest charge to revenue
|
173.48 |
65.51 |
|
|
6.14.24
|
An year wise analysis of interest approved
by OERC is given in Table : 38.
Table : 38
Year wise Analysis of Interest (Rs. in crores)
Year |
Total interest |
Interest during construction |
Interest charged to revenue |
1997-98 |
71.83 |
38.12 |
33.71 |
1998-99 |
125.20 |
48.80 |
76.40 |
1999-00 |
132.35 |
60.82 |
71.53 |
2000-01 |
116.58 |
51.07 |
65.51 |
|
6.15
|
Depreciation
GRIDCO has proposed Rs.78 crores towards depreciation expenses for the year 2000-01
computed on the basis of the rates notified by the Ministry of Power. It has also
furnished an asset wise calculation of depreciation from the FY 1999 upto the FY 2001.
GRIDCO has stated that it began its operation with transferred assets on 01.4.96.
Depreciation is charged based on audited annual accounts of FY 1997 and FY 1998 on the
transferred value and addition and deletion thereafter. None of the major assets of GRIDCO
could therefore, be depreciated in excess of 90%. However, GRIDCO would be in a position
to furnish the exact details of assets only after the asset registers are prepared for the
field units.
|
6.15.1
|
As GRIDCO inherited many of the assets which has been in the system for a
very long time and might have exhausted their economic life they were asked to reflect
such of the assets which have completed their asset life in form No. TRF-23. In response
to that GRIDCO clarified that GRIDCO has been vested with a net fixed useful asset of
Rs.1957.7 crores as on 01.4.96. GRIDCO has charged the depreciation on this value of
assets at the rate notified by GoI from time to time irrespective of the depreciation
charges prior to the date of transfer. Further, GRIDCO has expressed its inability to
provide information as required in Form No. TRF-23 due to lack fixed asset register.
|
6.15.2
|
GRIDCO further insist that as it has inherited all its assets on 01.4.96
and that the highest rate of depreciation of the transmission asset being 7.8%, none of
the transmission asset of GRIDCO can be depreciated in excess of 90% by FY 01. In other
words, GRIDCO wants to establish that as far as GRIDCO is concerned irrespective of the
age of assets for the purpose of calculation of depreciation the assets are being treated
as new.
|
6.15.3
|
The issue of depreciation and asset register as stated earlier has been
raised by number of objectors. Some of the objectors have agreed that the provision of
Rs.78 crores as requested by GRIDCO may be allowed but the depreciation recovered till
31.3.96 are to be identified on different blocks of assets. Recovery of depreciation must
stop once 90% of original cost is recovered.
|
6.15.4
|
Shri R.C. Padhi, Retd. C.E. stated that no depreciation recovery after
recovery of 90% of the original cost of the particular asset should be made. If such
accepted norms as per statutory provisions are to be violated there has to be a special
justification for the same should be on record. Shri R.P. Mohapatra has stated that
depreciation should be calculated on the basis of notification Ministry of Power, Govt. of
India dtd. March, 1994. He also stated that asset being second hand the rate of
depreciation has to be determined by the competent Govt. in each case "having regard
to the nature, age and conditions of the assets at the time acquisition". He had also
made a point that in case of 30-40% of the total assets procured by OSEB depreciation upto
90% of asset value must have been recovered on which no depreciation should be charged.
|
6.15.5
|
The Commission, therefore, may allow depreciation for assets created
before March, 94 at the earlier rates pending notification by Govt. of Orissa for 60% of
the assets pending creation of the asset register. The amount of depreciation allowable to
the licensee shall be less than 50% of the amount claimed in the revenue requirement.
|
6.15.6
|
Shri B.N. Das, Retd. Member (TDC), OSEB appearing on behalf of UCCI stated
that correct calculation of depreciation as per Govt. of Indias circular should be
made after dividing the assets into blocks at the time of revision of percentage of
depreciation, if it is not possible for OERC to deviate from Govt. of India norms.
Depreciation already collected and balance to be collected for each block of assets should
be exhibited in a register by GRIDCO and DISTCOs within a time frame to be fixed by OERC.
The issue of revaluation of assets and consequent depreciation calculation on assets
received at the time of transfer have been raised in earlier tariff orders and have been
disposed of by us. However, we may briefly deal with it again to reiterate
Commissions finding.
|
6.15.7
|
The Commission in its conceptual issues on tariff paper in Issue No. 6 has
stated that "tariff will be based on depreciated book value as set out in the
transfer scheme adjusted for subsequent addition and depreciation." The Commission in
its previous tariff order has already accepted the transfer value of assets appearing in
the Transfer Scheme notification by Govt. of Orissa for determination of the book value
assets. Obviously the base line for calculation of fixed assets has been the Transfer
Scheme Notification dt.01.04.96 which has been sanctified by legislation and therefore,
beyond scrutiny of the Commission. In view of this we are unable to sustain the objections
raised in this regard.
|
6.15.8
|
The auditors of GRIDCO in the audit report dtd. 28.9.2000 have stated that
the company has not maintained Fixed Assets register showing quantitative details and
situation of the Fixed Assets. Further, the company has not carried out physical
verification of Fixed Assets during the year and the properties of the company have not
been insured.
|
6.15.9
|
The Commission, therefore, directs GRIDCO to make good the deficiencies
noted by the statutory auditors before 30th of September, 2001 i.e. well before
the filing of revenue requirement (15th December to 31st December, 2001) for the year
2002-03. Once the asset register is built recovery upto 90% of the asset value can be
monitored.
|
6.15.10
|
According to the
provisions of the Electricity (Supply) Act, 1948, depreciation for the year should be
calculated on the gross fixed asset existing at the beginning of the year. Audited
Accounts of GRIDCO for the year 1998-99 revealed that the gross fixed asset of
transmission as on 31.3.99 is Rs.1175 crores. During 1999-00 an amount of Rs.102 crores is
transferred to asset in use. Thus total gross fixed asset as on 31.3.2000 is Rs.1277
crores on which depreciation for the year 2000-01 has been calculated. The Commission
accordingly approves an amount of Rs.78 crores for depreciation for the year FY 2001 as
shown in Table : 39.
Table : 39
Calculation of depreciation (Rs. in crores)
Opening balance of fixed assets as on
01.4.99 |
1175.17 |
Addition during 1999-00 |
101.70 |
Gross assets as on 01.4.2000 |
1276.87 |
Depreciation on the asset of Rs.1277
crores Applying the rates applicable |
78.00 |
|
6.16
|
Contribution to Contingency Reserves
GRIDCO has proposed Rs.6.38 crores towards contribution to contingency reserve under
Para-IV of Sixth Schedule of the Act, 1948. As per provision of Para-IV of the Sixth
Schedule, such contingency reserve amount should not be less than one quarter of 1% not
more than one-half of 1% of the original cost of fixed assets. One-half of the 1% of
Rs.1277 crores works out to Rs.6.38 crores. Thus, the Commission considers the provision
of Rs.6.38 crores proposed by the licensee as reasonable.
|
6.17
|
Capital Base
|
6.17.1
|
Original Cost of Fixed Asset
For the purpose of calculation of original cost of fixed assets, GRIDCO has proposed a
figure of Rs.1586.77 crores as on 31.3.2001 (TRF-23).
|
6.17.2
|
The gross value of asset as on 31.3.99 in the audited accounts of 1998-99
is Rs.1175.17 crores. The addition to fixed assets in the years 1999-00 and 2000-01 are
Rs.101.70 crores and Rs.309.90 crores respectively (TRF-23). Consumers contribution
for deposit work is to be deducted from the original cost of fixed assets for the purpose
of determination of capital base as per para XII of Sixth Schedule of The Act, 1948.
GRIDCO in its clarification to queries of OERC submitted in form TRF-25 that there is no
contribution on capital account from the consumers. As verified from Audited Accounts of
the year 1998-99 under Schedule-2 Reserves Surpluses, the consumer contribution as on
31.3.99 stands at Rs.15.77 crores. Therefore, the original cost of fixed assets less
contribution for deposit work works out to Rs.1571.00 crores from the figure of Rs.1586.77
crores proposed by GRIDCO.
|
6.17.3
|
The asset position including year to year
addition as given by GRIDCO is reflected in Table : 40 which is accepted by the
Commission.
Table : 40
(Rs. in crores)
|
Year |
1997-98
(Audited) |
1998-99
(Audited) |
1999-00
(Proposed) |
2000-01 |
Opening balance |
1076.50 |
1117.60 |
1175.17 |
1276.87 |
Asset addition |
41.10 |
57.57 |
101.70 |
309.90 |
Closing balance |
1117.60 |
1175.17 |
1276.87 |
1586.77 |
|
6.17.4
|
In this connection, the asset position as
estimated by the Commission on the basis of submission made by GRIDCO in the tariff filing
1999-00 is reproduced below (Para 6.25.1.3, OERC Case No. 12/99).
Table : 41
(Rs.in crores)
|
Year |
1997-98
(Audited) |
1998-99
(proposed) |
1999-00 |
Opening balance |
1076.50 |
1117.60 |
1322.10 |
Asset addition |
41.10 |
204.50 |
107.80 |
Closing balance |
1117.60 |
1322.10 |
1429.90 |
|
6.17.5
|
It may be observed that for the purpose of calculation of
capital base the closing balance for the year 1999-00 was accepted as Rs.1429.90 crores
which stands modified to Rs.1276.87 crores after finalisation of the accounts for the year
1998-99. This discrepancy is on account of a much lower level of asset addition i.e.
Rs.57.57 crores compared to the projection of Rs.204.50 crores for the year 1998-99. The
effect of this has been enhancement of the capital base and enhanced depreciation
expenses. Its effect is also to be felt in calculation of interest/return. Benefits
availed by the licensee on account of this inflated capital base resulting in higher BST
for FY 2000 need to be adjusted against the losses if any incurred by the company within
the performance parameters fixed by the
Commission. Similarly surplus if any determined after finalisation of accounts will be
adjusted against the revenue requirement of the succeeding year.
|
6.18
|
Original cost of work-in-progress
|
6.18.1
|
The original cost of works in
progress projected by GRIDCO would be Rs.718.32 crores on 31.3.01. Table-42 shows the
opening balance of WIP, Capital expenditure, Interest during construction, Transfer to
fixed asset and closing balance of WIP as projected by GRIDCO.
Table : 42
(Rs. in crores)
|
|
1997-98 |
1998-99 |
1999-00 |
2000-01 |
A.Opening balance of WIP |
174.64 |
254.63 |
393.04 |
566.17 |
B. Capital expenditure during the year |
121.06 |
195.98 |
274.88 |
389.05 |
C. (A+B) |
295.70 |
450.61 |
667.92 |
956.22 |
D. Transfer to fixed asset |
41.07 |
57.57 |
101.75 |
309.92 |
E. Closing Balance |
254.63 |
393.04 |
566.17 |
646.30 |
F. Advance pending allocation to
Capital Works
|
19.37 |
25.72 |
25.72 |
25.72 |
G. Stores |
|
|
|
46.30 |
H. Closing balance of WIP (C to F) |
274.00 |
418.76 |
591.89 |
718.32 |
|
6.18.2
|
The position of cost of WIP as approved in
the tariff order for the FY 1999-00 vide Case No.12/99 dtd.30.12.99 is reproduced in Table
: 43.
Table : 43
(Rs. in crores) |
|
1997-98 |
1998-99 |
1999-00 |
A. Opening balance of WIP |
174.64 |
274.00 |
234.51 |
B. Capital expenditure during the year |
140.43 |
164.99 |
321.90 |
C. (A+B) |
315.07 |
438.99 |
556.41 |
D. Transfer to fixed asset |
41.07 |
204.48 |
107.79 |
E. Closing balance of WIP (C+D) |
274.00 |
234.51 |
448.62 |
|
6.18.3
|
The Commissions observation is that the original cost of WIP is on
the rise from year to year and likely to reach a figure of Rs.718.32 crores as projected
by GRIDCO for the year ending 2000-01 which brings no immediate tangible benefit to the
consumers. The planning of works should have been carried out in a manner so as to get the
benefits of investment early. It seems that large number of projects have been taken up
simultaneously and kept incomplete resulting in far too much of unproductive assets. The
licensee should have done well to identify and arrange the projects in order of priority
so that system could improve and consumers could get the benefit of investments made in
completed works. The licensee cannot achieve financial viability unless asset management
and inventory control are prudently taken up as in case of private sector companies. And
in any case the burden of unproductive investment and avoidable excessive inventory cannot
be passed on to the consumer.
|
6.18.4
|
Even the DISTCOs have questioned the capability and prudence of GRIDCO in
carrying out the capital works as projected in the tariff application. These expenses have
been incurred in addition to the expenditure proposed for repair and maintenance works.
DISTCOs have urged that tangible benefit in terms of reduction of transmission losses and
improvement in system reliability due to this massive expenditure should be brought out by
GRIDCO as the financial impact in servicing the capital cost would be a burden on the
consumers. Even though the funding is done through borrowings which may not affect the
capital base, the cost of these borrowings has an impact on the revenue requirement and
tariff.
|
6.18.5
|
GRIDCO in its rejoinder has stated that all the capital works have been
undertaken by GRIDCO after careful evaluation of the necessity to carry out such works.
The existing network is not capable of meeting the operating standards prescribed by OERC
at all points of supply. The proposed capital works will strengthen the existing network
to comply with the operating standards of OERC to a great extent and to meet the future
load growth to some extent.
|
6.18.6
|
GRIDCO in clarification to the Director (Tariff)s query regarding
stock of Rs.46.3 crores for carrying out capital construction work clarified that the
aforesaid store are maintained at the project site, controlled by the EHT Construction
Divisions and are incorporated as a part of capital work in progress. Since both in spirit
and practice these are part of CWIP under the provisions of the Act, 1948 and rules framed
thereunder it is included in this BST Application. The source of funding is same as that
of the schemes undertaken from CWIP.
|
6.18.7
|
The Commission after examination of the figures comes to the conclusion
that the advance pending allocation to capital works to the tune of Rs.25.71 crores
continuing since FY 1998-99 should not be allowed to earn a return to the licensee as it
is not adding directly to the construction work in progress. Therefore, for the purpose of
calculation of capital base the Commission disallows this amount of Rs.25.71 crores and
accepts an amount of Rs.692.61 crores as CWIP. The Commission also observes that the
legitimacy of an advance to the tune of Rs.25.71 crores pending allocation over years is
doubtful.
|
6.19
|
Intangible Assets
|
6.19.1
|
GRIDCO proposes a sum of Rs.6.12
crores towards intangible assets. In para 3.2.3 of the main text of the application it has
stated that the figure for the year as per the audited accounts of 1997-98 is Rs.2.70
crores and that for the year 1998-99 is Rs.8.60 crores. In response to the
Commissions query GRIDCO has furnished the details of intangible assets comprising
of preliminary expenses and deferred revenue expenditure cuased for raising finance which
are amortised over the life of the bonds. GRIDCO has furnished the details given in Table
: 44.
Table : 44
Intangible Assets
Intangible Assets
|
Rs. Crores |
Preliminary Exp at beginning of FY00 as per Annual Accounts
of GRIDCO for FY99 (Sch 13)
|
0.72 |
|
Less Exp. Charged to revenue (at the same rate as in FY99
Sch 13)
|
(0.03) |
0.69 |
Deferred Exp for raising finance at beginning of FY00 as per
Annual Accounts of Gridco for FY99
|
7.90 |
|
Less Exp. Charged to revenue (at the same rate as in FY
1999 Sch 13)
|
(1.22) |
6.68 |
Total for FY 2000 |
|
7.37 |
Preliminary Exp. at beginning of FY 2001
|
0.69 |
|
Less Exp. Charged to revenue
|
(0.03) |
0.66 |
Deferred Exp. For raising finance at beginning of FY 2001
|
6.68 |
|
Less Exp. Charged to revenue
|
(1.22) |
5.46 |
Total for FY 2001 |
|
6.12 |
|
6.19.2
|
The Commission approves a sum of Rs.6.12 crores as intangible assets for
the year 2000-01.
|
6.20
|
Compulsory Investment under Sixth Schedule
|
6.20.1
|
GRIDCO in its application has stated that the compulsory investment in
accordance with the Sixth Schedule of the Act, 1948 for the year 2000-01 is Rs.11.30
crores. The investment proposed on the basis of appropriation approved Rs.4.96 crores for
the current year and Rs.6.40 crores for the ensuing year 2001.
|
6.20.2
|
In this connection it is pertinent to mention that as per IV(2) of the
Sixth Schedule of the Act, 1948, the sums appropriated to contingency reserve should be
invested in securities authorised under the Indian Trust Act, 1882 (2 of 1882) and such
investment should be made within a period of six months of the close of year of account in
which appropriation is made. In other words, funds accumulated under the head Contingency
Reserve upto FY 1999-00 should have been invested by September, 2000. The Licensee has not
produced any evidence of any investment in the scheduled securities as prescribed in the
Sixth Schedule of the Act, 1948. Therefore, while calculating the capital base, the
Commission cannot allow inclusion of the said amount of compulsory investment proposed by
GRIDCO for purposes of calculating capital base. It is pertinent to mention here that the
Commission in its order dtd.30.12.99 in Case No. 12/99 at para 6.28.2 had disallowed the
proposed investment as the licensee then also did not produce any proof of investment for
the FY 1998-99 to be invested by September, 1999. The licensee does not seem to have taken
note of this observation of the Commission while making this BST application for the year
2000-01. It is also important that the licensee should take note of the legal provision as
provided the Sixth Schedule of the Act, 1948 and made investment in specified security to
meet contingency requirement. The Commission also directs that the licensee should take
appropriate steps for making compulsory investment and produce proof of such investment
during the next tariff hearing.
|
6.21
|
Working Capital
|
6.21.1
|
Average cost of stores
According to para XVII(e)(i) of the Sixth Schedule to the Act, 1948, a sum equal to of
one-twelfth of the sum of book cost of stores, materials and supplies including fuel on
hand at the end of each month of the year of account should be taken into account as
working capital for calculating the capital base. GRIDCO has proposed Rs.30.80 crores.
GRIDCO has stated that the stores indicated above are O&M stores for use as current
assets in repairs and maintenance of the system. GRIDCO has also stated that capital
stores are maintained at the project sites controlled by the EHT Construction Divisions
and are incorporated within capital work in progress. GRIDCO has stated that the capital
and O&M stores as per GRIDCO are estimated for the year FY 01 is Rs.77.10 crores of
which capital stores (recorded as stores only at year end and only in books) are Rs.46.30
crores. Therefore, they have requested for provision of Rs.30.80 crores as the value of
stores for the purpose of calculation of capital base.
|
6.21.2
|
The Commission examined the proposal of GRIDCO. A stock of three
months consumption of materials at any particular point of time can be considered
reasonable. Accordingly the Commission approves one-forth of the total annual consumption
of materials i.e. Rs.3.67 crores as reasonable for the purpose of working capital for
stores to be included in the capital base.
|
6.22
|
Average Cash and Bank Balance
|
6.22.1
|
GRIDCO has proposed Rs.20.20 crores for the FY 2000-01 based on the actual
out turn for the year 1999-00 computed on the basis of the provisions laid down in Sixth
Schedule of the Act, 1948. GRIDCO in form TRF-11 has given the provision of monthly cash
balance from October, 99 to March, 2000. GRIDCO submits that for the FY 2001 that the same
average monthly balance to be considered for inclusion in capital base. GRIDCO has also
stated that it would be in a position to provide this detail for all three previous years
and for FY 1999-00 in the next tariff application. As stated in para XVII(1)(e)(ii) of the
Sixth Schedule of the Act, 1948, an amount equal to 1/12 of the sum of cash & bank
balances and call and short term deposits at the end of each month of the year of account,
not exceeding the sum specified therein can be included in capital base.
|
6.22.2
|
The Commission feels that liquid funds are needed for the payment of
Employees' Cost and Administrative & General Expenses pending collection of
receivables from the consumers. The normative lead time between the supply of electricity
to the consumers and collection of tariff is considered two months. Hence, the fund
requirement for two months payment of Employees Cost and Administrative &
General Expenses would be appropriate for meeting working capital requirement in the form
of cash and bank balance. Calculated on the aforesaid basis, the amount works out to
Rs.14.76 crores. The Commission, therefore, approves a sum of Rs.14.76 crores as cash and
bank balance for meeting working capital requirements.
|
6.23
|
Loan
|
6.23.1
|
GRIDCO has stated that its loan liability as on 31.3.01 will be Rs.2192.89
crores (TRF-16) but for the purpose of calculation of capital base Rs.1245.10 crores has
been considered for the FY 2000-01. GRIDCOs Justification of accepting the figure of
Rs.1245.10 crores has been given by in Table-7 of the clarification to queries
dtd.30.10.2000 which is also exhibited in Col. 1 & 2 of the below.
|
6.23.2
|
In light of the proposal of GRIDCO, the
Commission examined the suitability of various loans for the computation of Capital Base.
The Commission considers that out of the above loans, loans mentioned below have not been
utilised for capital formation.
Loans not considered for calculation of capital base
.
|
|
(Rs. in Crores) |
|
Loan from State Govt
|
120.00
|
|
GRIDCO bond
|
667.56
|
|
Bonds for pension trust
|
30.20
|
|
Total
|
817.76
|
|
6.23.3
|
GRIDCO has obtained loan of Rs.185.42 crores out of which Rs.120 crores
has been utilised for meeting the power purchase liability of OPGC as explained in para
6.14.4 of this order. GRIDCO bonds of Rs.667.56 crores were issued for meeting unpaid dues
to generating as detail in para 6.14.3 of this order. Bonds for pension of Rs.30.20 crores
has been explain in para 6.14.18 of this order.
|
6.23.4
|
Zero coupon bonds of Rs.400 crores issued
to Govt. of Orissa forms a part of the asset base of GRIDCO as per the Transfer Scheme
Notification dated 01.4.96 has to be deducted. Therefore, this bond of Rs.400 crores
should also be deducted from the asset base for the purpose of computation of Capital
Base. The loan details for the computation of Capital Base as proposed by GRIDCO and
approved by the Commission is given in Table : 45.
Table : 45
(Rs. in crores)
|
Source
|
GRIDCOs Proposal
|
Commissions approval |
LIC Loan
|
140.66 |
140.66 |
Loans from Central Government
|
11.26 |
11.26 |
Loans from Statement Government
|
185.42 |
185.42 |
World Bank Loan
|
219.85 |
219.85 |
PFC Loan
|
253.35 |
253.35 |
REC Loan
|
147.92 |
147.92 |
Public Bonds
|
20.13 |
20.13 |
Bonds for Pension Trust
|
30.20 |
30.20 |
Gridco Bonds
|
667.56 |
667.56 |
HIW Loan
|
82.54 |
82.54 |
ZCB
|
400.00 |
400.00 |
Short-term Loans from Banks
|
28.75 |
28.75 |
Cash Credit
|
5.26 |
5.26 |
Total in TRF-16
|
2192.89 |
2192.89 |
Less : Bonds towards power purchase payables
|
(360.00) |
667.56 |
50% of Rs. 307 cr (Public Bonds) towards working capital
requirements
|
(153.78) |
|
Short-term borrowings
|
(33.11) |
|
ZCB sought to be converted to equity
|
(400.00) |
|
Loans from Statement Government
|
- |
120.00 |
Bond for Pension Trust
|
- |
30.20 |
Total for Capital Base
|
1245.1 |
1375.13 |
|
6.23.5
|
The Commission, therefore, approves the amount of Rs.1375.13 crores to be
deducted from the total assets for determination of Capital Base.
|
6.23.6
|
Based on the forgoing observations, the Commission finds that capital base
for 2000-01 for the purpose of Sixth Schedule of the Act, 1948 has to be taken as
Rs.566.73 crores (vide Annex-II to this Order) against Rs.782.04 crores proposed by
GRIDCO.
|
6.24
|
Reasonable Return
|
6.24.1
|
GRIDCO has calculated the reasonable
return by multiplying the standard rate of 13% (8% bank rate plus 5%) on capital base as
on 31.3.99. One half of one percent on the amount borrowed from organisations or
institutions has also been added to this amount. Thus, GRIDCO has proposed an amount of
Rs.107.89 crores towards reasonable return. We are unable to accept this figure as we have
not approved the base figure of capital base. Reasonable return calculated in accordance
with Govt. of India, Ministry of Power notification dated 5th May, 1999 works out to
Rs.80.55 crores on a capital base of Rs.566.48 crores as in Table : 46.
Table : 46
(Rs. in crores)
|
Source |
Proposed
by GRIDCO |
Commissions
calculation |
98-99 |
99-00 |
00-01 |
98-99 |
99-00 |
00-01 |
Capital base |
503.92 |
597.76 |
782.04 |
279.51 |
235.27 |
566.54 |
Reasonable return 16% on
investment made after 31.3.99 |
|
15.01 |
0.00 |
|
NIL |
NIL |
13% on investment made upto
31.3.99 |
|
65.51 |
101.67 |
|
30.59 |
73.67 |
0.5% of loan outstanding as
at the end of year 1999-00 |
|
5.34 |
6.23 |
|
6.93 |
6.88 |
Total |
|
85.86 |
107.89 |
|
37.52 |
80.55 |
|
6.24.2
|
Thus the total reasonable return approved by the Commission is Rs.80.55
crores.
|
6.25
|
Miscellaneous Receipt
|
6.25.1
|
The Licensee had proposed an amount
of Rs.37.90 crores as miscellaneous receipt for the year 2000-01. The break up is in Table
: 47.
Table : 47
|
Quantity
In MU
|
Rate
Paisa/unit
|
Amount
Rs. Crore
|
Wheeling to CPPs
|
300.00 |
44.50 |
13.40 |
Wheeling to other States
|
2875.30 |
17.50 |
50.30 |
Less: 4% loss on wheeling to other states (MP)
|
115.00 |
230.50 |
(26.50) |
Sale to CPPs
|
3.36 |
2.31 |
0.80 |
Total
|
|
|
37.90 |
|
6.25.2
|
The Commission has considered the miscellaneous receipts as proposed by
GRIDCO. The figure of Rs.50.30 crores proposed on account of wheeling charges for power
outside the State is accepted. The Commission in para 6.32.9 of this Order has decided on
transmission tariff at 31 paise/unit for wheeling power inside the State. Based on this,
the receipts on this account comes to Rs.9.00 crores.
|
6.25.3
|
GRIDCO had initially indicated a sum of Rs.25.90 crores as deductible from
miscellaneous receipt due to 4% loss for wheeling of power to MP. GRIDCO was asked to
clarify why the loss of Rs.25.9 crores has been shown as deductible from miscellaneous
revenue.
|
6.25.4
|
GRIDCO in clarification to queries stated
that energy wheeled to MP for FY 2001 is taken at the same level as FY 2000 at 2875.3 MU.
This includes transmission loss at 4% i.e. 115 MU. Since the power procurement for
inclusion in GRIDCOs revenue requirement has been computed only for sale to DISTCOs
the cost of power for this 115 MU is deemed to be recovered from MP within the levy of
17.5 paise/unit which is the wheeling charge payable by MP. MP is provided with power from
NTPC stations of EREB and the loss of 115 MU is thus priced at an average of NTPC rate of
230.5 paise/unit (Revised from 225.4 P/U) which amounts to Rs.26.51 crores (Revised from
Rs25.9 crores). GRIDCO has suggested that the receipt on this account of loss of Rs.26.51
crores has to be deducted from the miscellaneous receipt since the equivalent cost of
power purchase has not been considered in the revenue requirement. Since the Commission
has accepted the gross principle of determination of loss of Orissa system cost of lost
units on account of wheeling of power States outside Orissa is considered deductible from
miscellaneous receipt for the year 2000-01. Accordingly a modified table regarding
composition of miscellaneous receipt is given in Table : 48 considering transmission loss
of 3.7% and transmission tariff of 31 paise/unit. The Commission approves a total of
Rs.35.87 crores as miscellaneous receipt.
Table : 48
Composition of Miscellaneous Receipts
|
Quantity In
MU |
Rate
Paisa/unit |
Amount Rs
Crore |
Wheeling to CPPs
|
300.00 |
31 |
9.30 |
Wheeling to other States
|
2875.30 |
17.5 |
50.32 |
Less: 3.70% loss on wheeling to other states
(MP)
|
106.90 |
230.5 |
(24.52) |
Sale to CPPs
|
3.36 |
231.0 |
0.78 |
Total
|
|
|
35.87 |
|
6.25.5
|
The Commission approves GRIDCOs expenditure for the purpose of
revenue requirement for the year 2000-01 as Rs.1415.72 crores as against the proposal of
Rs.1812.85 crores. The Commission has considered a provision of Rs.6.38 crores for
contribution to contingency reserve as proposed by GRIDCO. The Commission has approved
reasonable return of Rs.80.55 crores against Rs.107.89 crores proposed by GRIDCO. The Net
Revenue Requirement is as below :-
|
(Rs. in crores) |
Expenditure for the year 2000-01 (Annex-I)
|
1415.72
|
Contribution to contingency reserve
|
6.38
|
Reasonable return (Annex-II)
|
80.55
|
Total Revenue Requirement |
1502.65
|
Less Miscellaneous Revenue
|
35.87
|
Net Revenue Requirement
|
1466.78
|
|
6.25.6
|
The expected revenue from the DISTCOs based on the rates approved by the
Commission is Rs.1466.78 crores over a 12 months period. Considering the aforesaid
observations, clear profit for the full year works out to Rs.80.55 crores (Annex-III).
The reasonable return permissible to the licensee is Rs.80.55 crores. There is no excess
or deficit of clear profit over reasonable return.
|