6.8
|
Method of determination of Power Purchase
|
6.8.1
|
The power purchase by the DISTCOs are metered at various
grid sub-station’s end and the DISTCOs are billed according to the meter
reading at these points. Actual figures of billing raised by GRIDCO to the
DISTCOs for the past 10 months of the year 2001-02 are already available.
This can be prorated for a period of another two months for the financial
year 2001-02. This will go a long way in determining a realistic cost of
power purchase. In stead of going for any other method of energy
assessment, the Commission decides to adopt the principle of actual cost
of power purchase from the transmission company as the base for
determination of the cost of power purchase for the year 2001-02.
|
6.8.2
|
As far as the FY 2002-03 is concerned, the Commission will go
by the growth rate projected for the various classes of consumers by the DISTCOs at
different voltage level viz. LT, HT & EHT and calculate the incremental power
requirement over and above the FY 2001-02.
|
6.9
|
Determination of expected revenue
|
6.9.1
|
The quantum of energy to be sold will be determined after
deducting the units deemed to have been lost in distribution applying the bench-mark loss
level adopted by Kanungo Committee and accepted by the Commission. On the quantum of
energy to be purchased by the DISTCOs the percentage of distribution loss as approved by
the Commission shall be applied to determine the quantity to be sold during the financial
year. From the saleable energy for the year, units estimated to be sold at EHT i.e. zero
loss energy would be deducted to arrive at the quantum of energy to be sold at HT and LT
combinely. The expected revenue from sale of power shall be calculated separately for EHT
and combinely for HT & LT. EHT revenue shall be calculated by multiplying the EHT rate
with the EHT units. The revenue from HT and LT sale shall be calculated by multiplying the
average rate of HT and LT rate with the number of units to be sold combinely at HT and LT.
Thereafter, revenue at EHT and from HT and LT consumption will be added to determine the
total expected revenue for the year. The gap between the estimated revenue requirement and
the expected revenue will represent the deficit in revenue which need to be funded through
interim financing or through tariff.
|
6.9.2
|
SOUTHCO in the format T-6 of its RST
application for the year 2001-02 has furnished the average rate per unit billed to various
classes of consumer based on the billing of the first six months of the FY 2001-02 the
extract of which is given in the table.
Table : 13 : 13 : 13 : 13
Average Revenue based on actual billing of 1st six months of 2001-02 submitted by the
licensees
|
WESCO
|
NESCO
|
SOUTHCO
|
CESCO
|
Category of Supply
|
Average Revenue (Rs/Unit)
|
Average Revenue (Rs/Unit)
|
Average Revenue (Rs/Unit)
|
Average Revenue (Rs/Unit)
|
L T
|
2.49
|
2.37
|
2.42
|
2.53
|
HT
|
3.84
|
3.52
|
3.67
|
3.79
|
LT & HT Total
|
2.89
|
2.79
|
2.74
|
2.83
|
EHT
|
3.60
|
3.15
|
3.90
|
4.64
|
GRAND TOTAL
|
3.17
|
2.86
|
2.89
|
3.05
|
Table-14
Average Revenue as per the (format T-7) estimated sale to various consumers for 2001-02
submitted by the licensees
|
WESCO
|
NESCO
|
SOUTHCO
|
CESCO
|
Category of Supply
|
Average Revenue (Rs/Unit)
|
Average Revenue (Rs/Unit)
|
Average Revenue (Rs/Unit)
|
Average Revenue (Rs/Unit)
|
LT
|
239
|
221
|
228
|
251
|
HT
|
360
|
316
|
304
|
363
|
LT & HT Total
|
275
|
253
|
247
|
274
|
EHT
|
362
|
270
|
353
|
297
|
GRAND TOTAL
|
303
|
256
|
263
|
276
|
|
6.9.3
|
The average rate projected by the distribution companies in
the tariff filing for the year 2001-02 and 2002-03 obviously does not present the correct
picture of the per unit rate as by their own admission (Table 13) the average per unit
rate is much higher compared to their estimate given in Table 14. It is appropriate to
take into consideration the average rate per unit as reported by them based on their
billing of the first six months of the year 2001-02 given in Table 13 rather than accept
the average rate based on estimates furnished in form T-7 of this tariff filing.
|
6.9.4
|
Collection efficiency of DISTCOs
|
6.9.4.1
|
For the purpose of determination of expected revenue, the sale
figure will be determined assuming an overall loss percentage for the year 2001-02 as per
para 6.9.5.2.
|
6.9.4.2
|
Since the FY 2001-02 has come to an end, the Commission this
year shall only determine the revenue gap, if any, for recovery during the future years.
The Committee of Independent Experts had also recommended that the reality in the level of
billing and collection in the present Orissa situation by the distribution companies be
recognized. For this purpose, they had suggested that 78% should be accepted as the
collection efficiency for the base year 2001-02 going upto 95% by the year 2005-06. The
Committee had recommended that the cash gap be funded by interim financing other than
debt.
|
6.9.4.3
|
The Commission considers that the level of collection of 78%
is no means satisfactory as there is a huge backlog of Government dues to be received by
the DISTCOs. The Commission considers that with receipt of Government dues the collection
efficiency will increase to 85% for the year 2001-02. In the neighbouring states the
collection efficiency of the utilities is above 95% so also is the position in
Rajasthan,
Andhra Pradesh and Karnataka. The Commission also recognizes that the entire amount on
account of non-collection should not be treated as bad debt as this will further raise the
revenue requirement. Acceptance of the entire uncollected dues of a particular year
therefore cannot be written off as bad and doubtful debt and cannot be treated as a pass
through for next year tariff. This will accentuate the burden on the paying consumers of
the state. The distribution companies have to bolster their machinery for improving
collection of revenue for which they need State Government support for law and order
issue. To translate this into action, the Commission fixes a yardstick for collection
efficiency 85 %for the year 2001-02 and 87.5 % for the year 2002-03.
|
6.9.4.4
|
The shortfall in revenue collection for the FY 2002-03
calculated at collection efficiency level of 87.5% works out to Rs.268.75 crore on an
expected revenue of Rs.2150.04 crore (Table-16). On the other hand the receivables against
energy charges from the various departments of the Government and State PSUs has piled up
to more than Rs.230 crore within a period of three years of operation of the DISTCOs since
01.04.1999. The Government Departments and State PSUs should clear up the outstanding dues
of DISTCOs by routing the payment through GRIDCO. This shall be adjusted against the power
purchase and loan liabilities of DISTCOs due to GRIDCO which will improve the liquidity of
the power sector in Orissa.
|
6.9.5
|
Summary of revenue requirement of DISTCOs for FY 2001-02
& 2002-03
|
6.9.5.1
|
For the FY 2002-03, the Commission will consider the cost of
power purchase on a realistic basis as projected by the distribution companies and
calculated the expected revenue to be calculated assuming a loss reduction of 5% from year
to year i.e. from 42.21% in 2001-02 to 37.21% in 2002-03 though the figures will be
varying across the four zones. Similarly, the level of collection efficiency should be
considered at the level of 85%. All other terms and conditions with regard to the method
of determination of expected revenue as explained on the para above for the year 2001-02
shall apply for year 2002-03 also.
|
6.9.5.2
|
Accordingly, a summary of purchase sale and expected revenue
for the year 2001-02 & 2002-03 is approved as per the details below. Table-15
FY 2001-02
PURCHASE & SALES BY DISTCOs BASED ON 10 MONTHS
(ACTUAL) |
|
Purchase (MU)
|
Loss (%)
|
Sale (MU)
|
Av. Rate Rs/kwh
|
Rev. (Rs. Crs.)
|
CESCO
|
4167.77
|
40.94%
|
2461.485
|
3.05
|
744.70
|
NESCO
|
2253.62
|
46.98%
|
1194.8693
|
2.86
|
341.95
|
WESCO
|
2980.64
|
41.08%
|
1756.1931
|
3.17
|
549.15
|
SOUTHCO
|
1525.07
|
40.89%
|
901.46888
|
2.89
|
260.90
|
TOTAL
|
10927.10
|
42.21%
|
6314.02
|
3.02
|
1896.70
|
Table-16
FY 2002-03
EXPECTED PURCHASE & SALES BY DISTCOs BASED ON 10
MONTHS ACTUAL |
|
Purchase (MU)
|
Loss (%)
|
Sale (MU)
|
Av. Rate Rs/kwh
|
Rev. (Rs. Crs)
|
CESCO
|
4321.00
|
35.94
|
2768.03
|
3.05
|
841.55
|
NESCO
|
2291.20
|
41.98
|
1329.36
|
2.86
|
381.26
|
WESCO
|
3066.54
|
36.08
|
1960.13
|
3.17
|
616.66
|
SOUTHCO
|
1682.39
|
35.89
|
1078.58
|
2.89
|
310.57
|
TOTAL
|
11361.13
|
37.21
|
7136.10
|
3.02
|
2150.04
|
|
6.9.5.3
|
The Commission does not accept the figure of expected revenue
calculated by the DISTCOs for the FY 2001-02 as well as for the FY 2002-03 and determines
the expected revenue for various DISTCOs for the aforesaid period as indicated in Table-15
and Table-16 respectively for the FY 2001-02 and 2002-03 subject to any variation on
account of change in direct sale to consumers at EHT.
|
6.10
|
Operating Expenses
|
6.10.1
|
The operating expenses for distribution and retail supply may
be considered under the following heads :-
-
Employees Cost
-
Administration & General Expenses
-
Repair and Maintenance Expenses
-
Less Expenses Capitalized
|
6.10.2
|
CESCO in OERC Form No.TRF-21 of the 02-03 filing has
submitted various components covered under employees cost for the FY 00-01 on the basis of
audited accounts and have made projection up to the FY 02-03. The employees cost
chargeable to revenue was Rs.89.95 crore as per the actuals (provisional) for the FY 00-01
which has been projected to go up to Rs.94.44 crore and Rs.104.07 crore during FY 01-02
and FY 02-03. Projection for FY 02-03 is based on compounded annual growth rate of 10.19%
over the period FY 01-02 which is less than the combined annual enhancement in basic pay @
3%, CESCO stated he number of personnels in CESCO is 8081.
|
6.10.3
|
CESCO has not produced its audited account for the FY 1998-99
onwards i.e. from its inception. Without audited accounts for the period under review, for
the purpose of tariff fixation and calculation of annual revenue requirement, the
Commission has taken the approved figures of the FY 00-01 as the base and estimated the
expenditure for the FY 01-02 and 02-03.
|
6.10.4
|
The Commission had approved an amount of Rs.89.37 crore for
the year 2000-01 towards employees cost. The provisional figures of 00-01
as submitted by the licensee in F-21 is of the order of Rs.89.95 crore
which is close to the Commission’s approved figure towards employees
cost. The Commission considers it appropriate to give 3% rise on the basic
pay per annum over the provisional figure of FY 00-01 to determine the
basic pay for the year 01-02 as well as 02-03.
|
6.10.5
|
As regards DA, Commission is aware of the fact that the rate
of DA allowed by GOO is 41% with effect from July, 2000. This rate is continuing now and
no increase in DA rate has been announced by the State Government. Commission, in view of
the above, decides to consider the prevailing rate of 41% for calculation of DA for the FY
01-02 and 02-03. However, any increase in rate of DA in future will be allowed to be
recovered through tariff with retrospective effect.
|
6.10.6
|
All other allowances as claimed by the licensee are found
reasonable and accepted. Keeping these observations in view the Employees costs have been
recalculated as indicated in the Table : 17. Table : 17
Details of Employees Cost
(Rs. in crore)
Sl. No.
|
Particulars
|
Prop. by licensee 2001-02
|
Approved by Commission 2001-02
|
Prop. by licensee 2002-03
|
Approved by Commission 2002-03
|
1
|
Salaries
|
50.34
|
49.39
|
54.37
|
50.87
|
2
|
Over time
|
0.01
|
0.01
|
0.01
|
0.01
|
3
|
Dearness Allowance
|
18.76
|
20.25
|
20.26
|
20.86
|
|
Sub-Total
|
69.11
|
69.65
|
74.64
|
71.74
|
4
|
Other Allowance
|
1.54
|
1.10
|
1.25
|
1.10
|
5
|
Bonus
|
4.43
|
4.22
|
4.79
|
4.22
|
6
|
Total Emoluments (1 to 5)
|
74.70
|
74.96
|
80.68
|
77.05
|
|
Other Staff Cost
|
|
|
|
|
7
|
Reimbursement of Medical Expenses
|
1.55
|
1.47
|
1.67
|
1.47
|
8
|
Leave Travel Concession
|
0.33
|
0.31
|
0.35
|
0.31
|
9
|
Reimbursement of H.R.
|
7.77
|
7.40
|
8.39
|
7.40
|
10
|
Interim Relief of Staff
|
.01
|
0.01
|
0.01
|
0.01
|
11
|
Encashment of Earned Leave
|
3.92
|
2.90
|
4.32
|
2.99
|
12
|
Honorarium
|
0.00
|
0.00
|
0.00
|
0.00
|
13
|
Payments under Workmen Compensation Act
|
.06
|
0.06
|
0.06
|
0.06
|
14
|
Ex-gratia
|
0.07
|
0.07
|
0.07
|
0.07
|
15
|
Other Staff Cost
|
0.00
|
0.00
|
0.00
|
0.00
|
16
|
Total (Other Staff Cost) (7 to 15)
|
13.70
|
12.22
|
14.80
|
12.31
|
17
|
Staff Welfare Expenses
|
|
|
|
|
18
|
Terminal Benefits (PF)
|
6.04
|
6.09
|
85.93
|
6.27
|
19
|
Gratuity
|
0.00
|
|
|
|
|
Total (6+16+17+18)
|
94.44
|
93.27
|
104.07
|
95.63
|
|
Less : Employees Expenses Capitalised
|
0.00
|
0.00
|
0.00
|
0.00
|
|
Net Employee Cost
|
94.44
|
93.27
|
104.07
|
95.63
|
|
6.10.7
|
Commission approves Rs.93.27 crore and Rs.95.63 for the FY
2001-02 and 2002-03 respectively towards employees cost.
|
6.11
|
Repair & Maintenance Expenses
|
6.11.1
|
CESCO has proposed an expenditure of Rs.25.75 crore in its RST
application for the FY 01-02 and Rs.30.38 crore in the ARR for the FY 02-03 towards repair
and maintenance expenses.
|
6.11.2
|
As per the provisional figure for the year 00-01, the total
R&M expenses was Rs.24.52 crore and CESCO estimated that the R&M expenses will go
up to Rs.30.38 crore in the year 02-03 which is about 17.95% higher over the projected
figure of Rs.25.75 crore for the year 01-02. CESCO attributed the increase in the
expenditure to inflationary trend and damage caused due to flood.
|
6.11.3
|
The Commission examined the licensee’s proposal on
R&M expenses and considers it reasonable to allow 5.4% of gross fixed
assets as at the beginning of the year 00-01. As per RST and ARR filings
the gross fixed asset as on 31st March, 2001 and 2002 would be Rs.433.82
crore and Rs.486.60 crore respectively. Accordingly, the Commission
approves Rs.23.43 crore and Rs.26.28 crore for the year 01-02 and 02-03
respectively towards R&M expenses which is 5.4% of the gross fixed
assets at the beginning of the financial year. Table : 18
(Rs. in crore)
2000-01
|
2001-02
|
2002-03
|
Commission’s Approval
|
CESCO’s Proposal
|
Commission’s Approval
|
CESCO’s Proposal
|
Commission’s Approval
|
19.57
|
25.75
|
23.43
|
30.38
|
26.28
|
|
6.12
|
Administration & General Expenses
|
6.12.1
|
CESCO has proposed Rs.11.16 crore for the year 01-02 and
Rs.12.06 crore for the year 02-03 towards A&G expenses in its RST and ARR applications
respectively. These expenses include expenses on communication, professional charges,
property related expenses, conveyance and travelling, training, other expenses and
material related expenses. A&G expenses are said to be based on actual expenses
incurred during current year and budget estimate for ensuing year.
|
6.12.2
|
CESCO in its ARR filing stated that total A&G expenses
during the year 02-03 has been estimated to be Rs.12.14 crore which is 8.4% higher than
the amount projected for the year 01-02. The increase of 8.4% has been considered only
after taking into account the increase of normal price index due to inflation.
|
6.12.3
|
The Commission has examined the licensee’s proposal on
A&G Expenses. A&G expenses as per the provisional figure for 00-01
submitted by CESCO was Rs.9.82 crore. The Commission in its last tariff
order of 2000-01 approved Rs.7.78 crore towards A&G expenses,
considering 8% increase over the approved figure of 1999-00 to take care
of inflation.
|
6.12.4
|
Objectors in general expressed concern about rising trend in
A&G expenses and requested that this expenditure should be kept under control.
|
6.12.5
|
The Commission finds the projected A&G expenses rather
excessive with reference to earlier expenditure and volume of transaction which has not
increased.
|
6.12.6
|
The Commission considers it reasonable to allow an
increase of 5% per annum over the approved figure of 00-01 to factor in
inflation and approves an amount of Rs.8.17 crore and Rs.8.58 crore for
the year 01-02 and 02-03 towards A&G expenses. Table : 19
(Rs. in crore)
2000-01
|
2001-02
|
2002-03
|
Commission’s Approval
|
CESCO’s Proposal
|
Commission’s Approval
|
CESCO’s Proposal
|
Commission’s Approval
|
7.78
|
11.16
|
8.17
|
12.06
|
8.58
|
|
6.13
|
Interest on Loan
|
6.13.1
|
CESCO has proposed an amount of Rs.70.74 crore for the year
01-02 and Rs80.29 crore for the year 02-03 towards interest on loans taken from GRIDCO and
World Bank to be charged to revenue. The interest amount on the loan from GRIDCO has been
calculated as per the loan agreement with CESCO. The interest amount on loan from World
Bank has been calculated @ 13% per annum as per the subsidiary loan and project
implementation agreement with Government of Orissa. No interest has been claimed for the
deferred credit extended by GRIDCO to CESCO.
|
6.13.2
|
CESCO has stated that only the interest on loan drawn during
the current year for capital works has been capitalized. CESCO proposes receipt of loan of
Rs.45 crore and Rs.80 crore from World Bank during the year 01-02 and 02-03. The interest
on this loan is proposed for capitalization in the respective years.
|
6.13.3
|
The Commission examined the submission of CESCO in respect of
interest on loans. CESCO proposed a gross amount of interest for Rs.84.76 crore for the
year 01-02 out of which Rs 14.02 crore is to be capitalised and balance Rs 70.74 crore is
to be charged to revenue. Similarly, for the year 02-03 out of gross interest of Rs.91.30
crore, CESCO proposed Rs.11.01 crore of interest to be capitalised and balance of Rs.80.29
crore to be charged to revenue. The details of loans and average rate of interest as on
31.03..2002 and 31.03.2003 are given hereafter: Table -20
Source
|
Balance as on 31.03.01
|
Balance as on 31.03.02
|
Balance as on 31.03.03
|
Average rate of Interest
|
GRIDCO Loan (long term)
|
205.63
|
205.63
|
205.63
|
13.84%
|
GRIDCO Loan (deferred credit)
|
178.44
|
171.15
|
162.73
|
Not Mentioned
|
IBRD
|
72.69
|
117.69
|
197.69
|
13%
|
|
6.13.4
|
The Commission examined the calculation given in the Format
F-3 and F-27 of the tariff filing 01-02 and ARR filing 02-03. As the claim of interest in
the revenue requirement is not in agreement with the interest calculated in the respective
formats the Commission does not accept the same. The interest on loan given by GRIDCO has
been calculated @ 13.84% i.e. as per the subsidiary loan agreement which works out to
Rs.28.45 crore for 01-02 & 02-03.
|
6.13.5
|
The Commission has advised Government of Orissa for treatment
of World Bank loan in terms of the original sanction. Thus, for FY 01-02 & 02-03 the
World Bank loan has been treated as 30% grant and 70% loan. Interest has been calculated
accordingly on 70% of the average amount of loan. Thus the interest burden on World Bank
loan has been worked out to Rs.8.66 crore for the year 2001-02 and Rs.14.35 crore for
2002-03.
|
6.13.6
|
No interest on deferred credit has been allowed as it was not
claimed.
|
6.13.7
|
Interest Capitalised For the
year 01-02, CESCO has deducted Rs.14.02 crore towards interest capitalised from the gross
interest claim of Rs 84.76 crore to arrive at the figure of Rs.70.74 crore to be
chargeable to revenue. Similarly, Rs.11.01 crore has been proposed for the year 02-03
towards interest capitalised against gross interest claim of Rs 91.30 crore. As mentioned
earlier the total calculation of gross interest and interest capitalised has not been
supported by evidence and as such the Commission does not agree with the figure. Going by
the principles followed by CESCO only the interest on loans drawn for capital purpose for
a particular year is to be capitalised. CESCO proposes to draw Rs.45 crore and Rs.80 crore
from the World Bank during the year 01-02 and 02-03 on which interest would accrue to the
tune of Rs.2.05 crore and Rs.3.64 crore respectively. Hence, the Commission approves
Rs.2.05 crore for the year 01-02 and Rs.3.64 crore for the year 02-03 towards interest
capitalised.
Table : 21
(Rs. in Crore)
Loans
|
2001-02
|
2002-03
|
|
CESCO’s
Proposal
|
Commission’s
Approval
|
CESCO’s
Proposal
|
Commission’s
Approval
|
With correctives
|
Without correctives
|
With correctives
|
Without correctives
|
Gross Interest
|
84.76
|
37.13
|
41.83
|
91.30
|
42.80
|
48.95
|
Less interest capitalised
|
14.02
|
2.05
|
2.93
|
11.01
|
3.64
|
5.20
|
Interest chargeable to revenue
|
70.74
|
35.07
|
37.90
|
80.29
|
39.16
|
43.75
|
|
6.13.8
|
The Commission while considering the capital base as provided
in the Sixth Schedule of the Act, 1948 made provision towards working capital on which the
licensee is entitled to get reasonable return. Moreover, the licensee can get rebate on
prompt payment from GRIDCO @ 2% per month which will reduce its power purchase liability.
The licensee should arrange working capital from the commercial and financial institutions
to save DPS as well as earn rebate from GRIDCO, which will compensate the interest on
working capital, and CESCO may earn some revenue. Hence, the Commission does not consider
it proper to allow any interest on working capital other than the amount specified in the
Schedule-VI.
|