6.52
|
Expected Revenue from charges
|
6.52.1
|
GRIDCO in its rejoinder dated 30
March 2002, has submitted a revised estimate for expected revenue for Rs.1721 crore after
taking into consideration the revenue from export of power as well as sale to CPPs for the
FY 2001-02. This has been examined at the Commissions end and the expected revenue
is calculated for the FY 2001-02 on the basis of Bulk Supply Tariff in force since
01.02.2001 and is given in Table-50. Table : 50
Expected revenue from charges
Sl.No. |
CATEGORY |
UNIT |
DISTCOS |
|
|
|
|
CESCO |
NESCO |
WESCO |
SOUTHCO |
TOTAL |
1 |
VOLTAGE OF
SUPPLY |
KV |
|
|
|
|
|
2 |
ANTICIPATED
SALE DURING THE ENSUING YEAR TOTAL |
MU |
4,167.77 |
2,253.62 |
2980.64 |
1525.07 |
10,927.10 |
3 |
CONTRACT
DEMAND TOTAL |
MVA |
663.91 |
365.35 |
504.45 |
265.21 |
1,798.92 |
4 |
DEMAND
CHARGE |
Rs./KVA |
200.00 |
200.00 |
200.00 |
200.00 |
|
5 |
ENERGY
CHARGE |
P/Kwh |
99.00 |
100.00 |
101.74 |
90.00 |
|
6 |
REVENUE FROM
DEMAND CHARGE |
Rs. Cr. |
159.34 |
87.68 |
121.07 |
63.65 |
431.74 |
7 |
REVENUE FROM
ENERGY CHARGE |
Rs. Cr. |
412.61 |
225.36 |
303.25 |
137.26 |
1078.48 |
8 |
TOTAL |
|
571.95 |
313.05 |
424.32 |
200.91 |
1510.22 |
9 |
REVENUE SALE
FROM EXPORT AND SALE TO CPP |
Rs. Cr. |
|
|
|
|
172.86 |
10 |
GROSS TOTAL
REVENUE |
Rs. Cr. |
571.95 |
313.05 |
424.32 |
200.91 |
1683.08 |
11 |
NET TOTAL
REVENUE |
Rs. Cr. |
|
|
|
|
1683.08 |
|
6.52.2
|
The above amount does not include
wheeling charges of Rs.37.57 crore in 2001-02 considered separately as miscellaneous
revenue. As the revenue requirement is Rs.1639.49 crore and expected revenue is Rs.1683.08
crore the year may end with a surplus of Rs.43.59 crore, which will be dealt in accordance
with the provisions of the Sixth Schedule to the Supply Act, 1948.
|
6.52.3
|
For the purpose of Bulk Supply
Tariff 2001-02, GRIDCO has proposed a demand charge of Rs.250/KVA/month and Rs.156.10
paise/unit as energy charge.
|
6.52.4
|
In Table-48 the revenue requirement
has been calculated by applying necessary correctives to power and transmission cost.
Based on that, the approved revenue requirement does not call for any change in the
existing Bulk Supply Tariff applicable for all the four DISTCOs for the year 2001-02. We,
therefore, direct that energy charges and demand charges as applicable to the various
DISTCOs effective since 01.02.2001 and approved by the Commission in order dt.19.01.2001
shall continue upto the date of new tariff for 2002-03 comes into force as determined in
later part of this order. Any revision of tariff in accordance with the OER Act, 1995 can
be applied prospectively. The reason is that a seven clear days notice before its
implementation is necessary under Sec. 26(5) of the OER Act, 1995. Revision of tariff
cannot be done in case of the FY 2001-02 which is already over. This situation arose
because of deficiencies on the part of the licensees to submit the revenue requirement and
tariff application in complete shape in time. As such, the tariff revision proposal for
the year 2001-02 submitted by the licensee is rejected.
|
6.52.5
|
As observed in para 6.51.10 if the
decision of the Government of Orissa goes contrary to the recommendations made by
Commission the revenue requirement for the year 2001-02 as determined in this order
without applying the correctives shall be due for recovery. Since the FY 2002 is already
over and no fixation of tariff is possible with retrospective effect, the Commission will
treat the gap between the revenue requirement and expected revenue for the FY 2001-02 as a
regulatory gap for recovery at a future date.
|
6.52.6
|
In as much as tariff proposals for
FY 2001-02 have been rendered infructuous, GRIDCO and DISTCOs propose that the Commission
proceed under Section 26 (6) of the OER Act, 1995 to determine tariff for FY 2002-03 on
the basis of revenue requirement for that year as approved by the Commission. Hence the
Commission has proceeded under section 26(6) to determine tariff under section 26(6) of
the OER Act, 1995 for the FY 2002-03.
|
6.53
|
Bulk Supply Tariff for FY 2002-03
|
6.53.1
|
Zonal variations like difference in
load factor, unequal volume of energy consumption, difference in the time of occurrence of
the peak demand from utility to utility, wide variation in HT and EHT loads across the
four distribution utilities are endemic to the power system of Orissa.
|
6.53.2
|
Condition 8.2 of the Bulk Supply and
Transmission (2/97) licensee as amended by OERC order dated 31.03.1999 in Case No.21/98
issued to GRIDCO provides for use of system services to any user on price or other terms
which materially differ from those offered to other users, where such differences reflect
different circumstances of service including load factor, power factor, level and timing
of peak demand and any other relevant factors.
|
6.53.3
|
It is also a fact that some amount
of cross-subsidy through a higher BST will be available from one utility to the consumers
of other utility with lower BST to maintain uniform retail tariff through out the State.
|
6.53.4
|
Based on the aforesaid
considerations the Commission deems it desirable to continue with differential Bulk Supply
Tariff for the four distribution companies and uniform retail tariff through out the
State.
|
6.53.5
|
Determination of Demand
and Energy Charge
|
6.53.5.1
|
Demand Charge is levied in
consonance with the philosophy of realisation of cost in proportion to the capacity
requirement of the utilities. Energy charge is recovered in proportion to the actual
quantum of energy consumed by the utilities.
|
6.53.5.2
|
After taking into consideration the
revenue requirement for the FY 2002-03, the Commission does not consider it necessary to
revise the existing rate of demand charge upwards to Rs.250/KVA/month as proposed by
GRIDCO. Therefore, the existing demand charges for 2002-03 is approved at Rs.200/KVA/month
which is the prevailing rate. The expected revenue from the demand charge based on the
maximum demand for the various distribution companies approved by the Commission for the
FY 2002-03 is given in Table 51. Table : 51
Annual Demand Charges (Estimated)
|
FY 2002-03 (MVA) |
Demand Charge (Rs./KVA/month) |
Expected annual Revenue from
Demand charges (Rs. Crs.) |
CESCO
|
683.25 |
200 |
163.98 |
NESCO
|
378.85 |
200 |
90.92 |
WESCO
|
503.32 |
200 |
120.80 |
SOUTHCO
|
275.40 |
200 |
66.10 |
TOTAL
|
1840.83 |
|
441.80 |
|
6.53.5.3
|
Taking into account the facts
presented to the Commission, it now approves the following energy charges applicable to various distribution
licensees after expiry of seven days of the publication by the licensee under section
26(5) of the OER Act, 1995.
|
|
|
Existing
|
Revised
|
CESCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
99 paise/unit
|
92.00 paise/unit
|
WESCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
101.74 paise/unit
|
96.50 paise/unit
|
NESCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
100 paise/unit
|
86.00 paise/unit
|
SOUTHCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
90 paise/unit
|
84.00 paise/unit
|
|
6.53.5.4
|
Based on the aforesaid rates the
revenue as estimated from the energy charges determined on the quantum of energy approved
for the different distribution companies is given in Table-52. Table
: 52
Energy Charges
Name of the Company |
Estimated 2002-03
(MU) |
Energy Charge
(In p/u) |
Revenue from energy
charges
(Rs. in Cr.) |
CESCO |
4321.00 |
92.00 |
397.53 |
NESCO |
2291.20 |
86.00 |
197.04 |
WESCO |
3066.54 |
96.50 |
295.92 |
SOUTHCO |
1682.39 |
84.00 |
141.32 |
Total |
11361.13 |
|
1031.82 |
|
6.53.5.5
|
As against GRIDCOs total
revenue requirement of Rs.1796.98 crore, it will recover Rs.441.80 crore through demand
charge and Rs.1031.82 crore from energy charge meeting its revenue requirement of
Rs.1473.62 crore for the year 2002-03 from the DISTCOs and the company will earn an amount
of Rs.323.40 crore on account of export of power outside the State and sale to Captive
Power Plants.
|
6.54
|
Over
drawal Charges
|
6.54.1
|
GRIDCO follows the principle of
least cost procurement of power to minimize the total cost of generation. Any excess
drawal from the annual procurement plan provided by the DISTCOs will require procurement
of power from the costlier sources not covered in the revenue requirement of GRIDCO.
GRIDCO has drawn the attention of the Commission to the BST approval order for the 2000-01
where the Commission had approved that higher cost resulting from any drawal in excess of
the projected requirement by DISTCOs to be charged as a year end adjustment to cover the
marginal cost of power purchase plus transmission charges and transmission losses. GRIDCO
has sought for approval of the same in their tariff application of 2001-02 with a rider
that GRIDCO may be allowed to raise the bill for overdrawal automatically.
|
6.54.2
|
This issue of overdrawal charges has
been fully discussed in order 27 dtd.19.01.2001 in para 6.29.4 which has also been quoted
by GRIDCO in its BST application of FY 2001-02. As far as the financial year 2001-02 is
concerned, the Commission has taken into consideration the total cost of power purchase on
the basis of latest available billing figures of generators raised on GRIDCO for the
purpose of determination of the revenue requirement for this year. Therefore, it leaves no
scope or opportunity for any kind of adjustment for the year 2001-02 on account of
overdrawal as the entire cost of GRIDCO is supposed to have been allowed for recovery in
the present tariff order. Therefore, there would not be any necessity on the part of
GRIDCO to raise the bills for overdrawal automatically. This, however, excludes some
additional expenditure that may be required to be met by GRIDCO on account of orders of
Central Electricity Regulatory Commission or on account of any revision of billing based
on subsisting power purchase agreements which has to be dealt in accordance with
appropriate legal orders. Likewise for the FY 2002-03, the Commission has gone on the
basis of the data submitted to it both by GRIDCO and DISTCOs to determine the demand
charge and energy charge. Therefore, it is decided that any excess drawal over the
approved quantum for the year 2002-03 should be billed by GRIDCO at the actual cost of
power purchase plus transmission charges and transmission losses, and payable as an year
end adjustment.
|
6.54.3
|
GRIDCO in its rejoinder has stated
that it is not supposed to submit the certified and complete set of bills of DISTCOs but
shall submit the same to the Commission for the purpose of levy of overdrawal charge. The
Commission would like to clarify that the claim of GRIDCO has to be supported by the
auditors certificate and objections, if any, to that may be raised before the
Commission by the DISTCOs by following the appropriate procedure of law for settlement of
disputes between the licensees.
|
6.55
|
Rebate
|
6.55.1
|
The proposal submitted by GRIDCO was
examined at the Commissions end. The Commission approves that on payment of the
monthly bill, the Retail and Distribution Licensees shall be entitled to a rebate of
-
Two percent (2%) of the amount of the monthly bill (excluding arrears), if full payment
is made within 48 hours of the presentation of the bill.
-
One and half percent (1.5%) of the amount of the monthly bill (excluding arrears), if a
minimum of 85% of the whole amount (excluding arrears) is paid within 48 hours of the
presentation of the bill and one percent (1%) on the balance amount if paid in full within
15 days from the date of the presentation of the bill.
-
One percent (1%) on the amount of the monthly bill (excluding arrears), if full payment
is made within 15 days from the date of the presentation of the bill.
|
6.56
|
Delayed
Payment Surcharge
|
6.56.1
|
GRIDCO in para 4.5 of its BST
application for 2001-02 has submitted that the surcharge for delayed payment for bulk
supply bills i.e. payment after the period of 30 days from the date of submission of bill
may be retained at 2% per month. As indicated in para 3.7.1 of this order, GRIDCO proposes
continuance of the existing provisions relating to DPS as approved by the Commission in
its order dated 19.01.2001.
|
6.56.2
|
The Commission directs that monthly
charges as calculated with other charges and surcharge on account of delayed payments, if
any, shall be payable by the Retail and Distribution Licensee within 30 days from the date
of bill. If payment is not made within the said period of 30 days, delayed payment
surcharge at the rate of 2% (two percent) per month shall be levied pro-rata for the
period of delay from the due date, i.e. from the 31st day of the bill, on the amount
remaining unpaid (excluding arrears on account of delayed payment surcharge).
|
6.57
|
Transmission
Tariff
|
6.57.1
|
The proposal of GRIDCO with regard
to the transmission tariff as given in para 3.10 of this order is repeated for
convenience.
GRIDCO has estimated that the full cost of transmission including reasonable return
will come to Rs.621.73 crore. On the basis of its cost estimate, the calculation of
transmission tariff proposed by GRIDCO is given below: Table :
53
Transmission Tariff
Transmission Cost with
Reasonable Return less revenue from interstate wheeling (a)
|
Rs.621.73 Cr |
Total Units Sold to Distcos (b)
|
11,439.58 MU |
Total Units Wheeled (c)
|
345 MU |
Transmission Tariff (a/(b+c))
per/ Unit
|
52.8 paise |
|
6.57.2
|
GRIDCO has proposed that fixation of
transmission tariff for the CPPs at 52.8 paise per unit will defeat the very purpose of
setting up of CPPs which are considered as second cheapest source of power to GRIDCO at
present. Hence, for encouraging installation of more number of CPPs in the State, the
wheeling charges to the CPPs for transportation of power to their sister units may be
fixed at 17.5 paise per unit in line with the wheeling charge being levied for MPSEB and
other states for wheeling of power through interstate transmission lines.
|
6.57.3
|
In this connection, the Commission
sought clarification from GRIDCO as to why GRIDCO has proposed wheeling charges for
utilisation of its transmission system @17.5 p/u apparently to encourage growth of more
CPPs for availing cheap power. On the other hand, the actual drawal from the CPPs is very
dismal. At the present juncture, the logic of charging a rate lower than the cost of
transmission calculated at 52 p/u leading to loss of miscellaneous revenue need to be
adequately justified.
|
6.57.4
|
In response to the aforesaid
queries, GRIDCO has replied that it had proposed to charge 17.5 p/u as wheeling charge in
place of 52.80 p/u as calculated. In the past years the tariff applications contained a
contention that the wheeling charges should be at par with per unit cost of transmission
considering the over all power transmitted.
|
6.57.5
|
After detailed examination of facts
and figures, the Commission approves a total transmission cost of Rs.363.42 crore for the
year 2001-02 and Rs.376.39 crore for 2002-03. As the FY 2001-02 is already over the
Commission would not like to change the existing rate of 31 paise/unit for the year
2001-02.
|
6.57.6
|
The Commission has approved the sale
figure of 11361.13 MU for the DISTCOs and wheeling of 300 MU to CPPs for the year 2002-03.
Applying the principle of embedded cost, the transmission tariff per unit works out to
32.27 paise/unit which is rounded to 32 paise per unit. When a CPP is located away from an
industrial unit the energy utilised by the industrial unit is deemed to have been
transmitted over GRIDCOs transmission system from the CPP wherever agreement exists.
This rate shall be applicable on the quantum of energy consumed by such industrial units.
This rate shall also be applicable for transmission of power from outside the State to an
industry located inside the State through the use of GRIDCOs EHT transmission
system.
|
6.58
|
Transmission loss for wheeling
|
6.58.1
|
GRIDCO has proposed that out of the
energy supplied to transmission and bulk supply licensee, 4.6% shall be deducted towards
transmission loss and balance is liable to be delivered at delivery point at 220/132 kV.
Based on the facts and figures submitted to the Commission, it is observed that the
transmission loss for the FY 2001-02 works out to 4.18%. However, for the purpose of
billing the transmission loss shall remain unchanged i.e. @3.7% as approved by the
Commission in its order dated 19.01.2001 till the new tariff hereunder comes into force.
|
6.58.2
|
For the year 2002-03, the loss is
fixed at a level of 3.88%. It is, therefore, decided by the Commission that the energy
consumed by an industry supplied by a CPP situated at a distant location or wheeling of
power from outside the State to an industry within the State, 3.88% of the energy will be
deemed to have been lost in transmission on which also transmission charges shall be
levied for 2002-03.
|
6.59
|
Delayed Payment
Surcharge (For transmission charges) GRIDCO has proposed delayed
payment surcharge for delay in payment of transmission charges as detailed in modified
DF-20 (Clarification to queries on BST FY 2001). The Commission approves that the monthly
charges as calculated with other charges and surcharge on account of delayed payments, if
any, shall be payable within 30 days from the date of bill. If payment is not made within
the said period of 30 days, delayed payment surcharge at the rate of 2% (two percent) per
month shall be levied pro-rata for the period of delay from the due date, i.e. from the
31st day of the bill, on the amount remaining unpaid (excluding arrears on account of
delayed payment surcharge). |
6.60
|
Duty
and Taxes
|
6.60.1
|
The Commission approves that the
electricity duty levied by the Government of Orissa and any other statutory
levy/duty/tax/cess/toll imposed under any law from time to time shall be charged over and
above the tariff.
|
6.60.2
|
The Commission has approved
GRIDCOs revenue requirement for 2002-03 at Rs.1796.98 crore (applying all
correctives) which GRIDCO is allowed to recover at an approved tariff over a period of 12
months. Until the revised tariff comes into force GRIDCOs BST rate till the date of
implementation of the new tariff hereunder will be higher than the new rate being fixed.
For this GRIDCO will be making an excess recovery over the revenue requirement calculated
for the period of 2002-03 which can be adjusted against the past dues of DISTCOs.
|
6.60.3
|
In calculating the expected
aggregate revenue for 2002-03, the revenue earning by GRIDCO from export of power to APSEB
has also been taken into account. The rate at which this power has been sold being higher
than the procurement cost of GRIDCO, this will benefit the consumers of the State in the
form of reduction of Bulk Supply Tariff. It is needless to emphasize that the extra
revenue earned due to export of power will reduce the burden of the consumers of the
State.
|
6.60.4
|
The Commission have made several
recommendations to the Government of Orissa for their implementation w.e.f. 01.04.2001.
Accordingly the Commission have determined the Bulk supply Tariff and Transmission Tariff
applying all correctives based on its recommendations to the Government. If a decision to
the contrary is taken by the Government the revenue requirement for the FY 2002-03 as
determined without applying the correctives
shall be due for recovery from the consumers. It will raise the revenue requirement by
Rs.387.69 crore on the basis of our present estimate which shall be as follows.
CESCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
142.13 paise/unit
|
WESCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
146.70 paise/unit
|
NESCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
135.25 paise/unit
|
SOUTHCO
|
Demand charge
|
:
|
Rs.200/KVA/month
|
|
Energy charge
|
:
|
135.75 paise/unit
|
This is based on the assumption that the tariff approved in para 6.53.5.3 is effective
from 01.05.2002 to 31.07.2002 and the above rate shall be valid from 01.08.2002 to
31.03.2003 provided the recommendation as indicated earlier are not accepted by the
Government by 31.07.2002.
This tariff effective from 01.08.2002 shall be subject to such proportionate reduction as
may be necessary to the extent the Government accepts the recommendation made by the
Commission. The reductions being purely arithmatical in nature shall take effect without
any further proceeding for amendment under section 26(6) of the OER Act 1995. However it
is made clear that in case of such reduction a fresh notification under section 26(5) of
the OER Act will be made by the licensees with the approval of OERC. |
6.60.5
|
Finally, the Commission orders as
follows with reference to the prayers of the applicant. The Commission does not approve
the transmission and bulk supply charges as proposed by GRIDCO for 2001-02 and rejects the
tariff revision proposal.
|
6.60.6
|
The Commission also does not approve
the revenue requirement for the FY 2002-03 as proposed by GRIDCO and directs for
implementation of Bulk Supply Tariff, Transmission charges and other charges as determined
by the Commission in this order to be effective after expiry of seven days of the
publication by the licensee under section 26(5) of the OER Act 1995.
|
6.60.7
|
In case the recommendations made by
the Commission for necessary correctives for determination of revenue requirement are
accepted in toto by the Government, the tariff determined in para 6.53.5.3 shall continue
unchanged after 31.07.2002.
|
6.60.8
|
Pursuant to order dated 19.04.2002
of the Honble High Court of Orissa the order is not being notified to the licensee
in terms of section 26(6) but is filed in sealed cover in the Honble High Court of
Orissa. The application of M/s GRIDCO is disposed off accordingly.
Sd/-
(B.C. JENA)
MEMBER
|
Sd/-
(H. SAHU)
MEMBER
|
Sd/-
(D. C. SAHOO)
CHAIRMAN
|
|