5.0
|
GRIDCO's RESPONSE TO OBJECTIONS
|
5.1
|
Demand estimation
|
5.1.1
|
Energy requirement GRIDCO
has also submitted that the power procurement proposed by GRIDCO is based on the proposals
submitted to it by DISTCOs. Some discrepancy has been noticed in power procurement
projection given by DISTCOs to GRIDCO and projection given in their tariff application.
DISTCOs need to explain the discrepancy. |
5.1.1.1
|
GRIDCO has rejected the alternative
demand forecast made by some objectors by stating that the assumptions behind these
forecasts have not been explained. The transmission loss calculation is incorrect in some
cases.
|
5.1.2
|
Simultaneous Maximum
Demand, Contract Demand and Billing Demand GRIDCO has replied that there is
no justification for changing the method of computation of measurement of SMD because
ultimately GRIDCO's revenue from such charges has to match its revenue requirement. The
method of computation of SMD has little bearing on the whole issue. GRIDCO does not find
the proposal of DISTCO's for reducing demand charges to be reasonable. |
5.1.3
|
Levy of Overdrawal charge GRIDCO
is not supposed to submit the certified and complete set of bills to DISTCOs but shall
submit the same to the Commission. |
5.1.4
|
Transmission losses There
is no problem in metering the activities of GRIDCO and the transmission loss based on
actual figures and not assumptive ones. GRIDCO considers that the transmission loss cannot
be substantially reduced. GRIDCO also requested the Commission to ignore the loss figure
suggested by some DISTCOs, as this is based on one month's data. GRIDCO also replied that
the revision of tariff is not dependent only on a single parameter and objection to the
tariff revision proposal for not achieving desired loss level does not appear to be
logical and judicious. |
5.1.4.1
|
GRIDCO has also submitted that the
increase in transmission loss from 4% to 4.6% is due to exclusion of energy flow in
IB-Budhipadar-Korba line connected to the western grid. GRIDCO has submitted a business
plan to reduce the transmission loss by 0.2% every year and the transmission loss will
come down to 3.7% by 2006-07. The request made by objectors for allowing 3.5% transmission
loss is not supported with evidential documents and, therefore, should be accepted.
|
5.1.5
|
Power procurement: Least
cost drawal GRIDCO replied that its power procurement plan is based on
least-cost combination of power to be procured from various generating stations. Hence,
GRIDCO has no plan for purchase of high cost power when low cost power is available in the
State. GRIDCO is making all efforts to draw maximum power from OHPC and during FY 2001-02,
the drawal will be more than the estimated volume. GRIDCO is making every endeavour to
draw maximum power from CPP as well. |
5.1.6
|
Power procurement costs The
existing PPA between GRIDCO and OPGC has been approved by GOO and the same has been
submitted to OERC for approval. OERC has initiated the required proceedings. GRIDCO has
received a proposal for two-part tariffs relating to Rengali and Upper Kolab stations of
OHPC. GRIDCO is scrutinising the proposal. |
5.1.6.1
|
GRIDCO has also rejected the cost
estimates proposed by some objectors and stated that GRIDCO has considered station-wise
cost of power based on the energy bills, year-end adjustment bills, tariff notifications
and PPA. Continuance of rates approved by the Commission last year will put GRIDCO into
loss in power procurement and will increase its overall loss.
|
5.1.6.2
|
GRIDCO has pointed out that the case
on CERC order on tariff norms is pending in the Hon'ble High Court of Delhi and,
therefore, the argument that the fixed costs should be reduced is premature. Till orders
are passed by the appropriate authority, the change in the tariff of generating stations
cannot be considered.
|
5.1.6.3
|
GRIDCO has requested the courts to
implement ABT on prospective basis and not on retrospective basis. In case GRIDCO's prayer
is not acceded to by the courts, GRIDCO may incur losses for which it has prayed the
Commission to pass the loss in the next BST.
|
5.1.7
|
Transmission costs
|
5.1.7.1
|
Employee cost, A&G,
R&M expenses GRIDCO is taking utmost care for incurring judicious
expenditure on employees cost, O&M cost and A&G expenses. GRIDCO has denied that
the increase in administrative and operational expenses is significant and unnecessary.
Because of increase in cost of operation and cost of material, these costs are bound to
increase. Increase in R&M expenses is due to additional repair and maintenance
expenses needed for upkeep of system and restoration after flood damage during 2001-02.
A&G expenses for FY 2002 include the stamp duty payable on bonds payable to
generators. |
5.1.7.2
|
GRIDCO has also refuted the
allegation that it is disobeying the Commission's order. The Commission allows certain
normative amounts under different heads for passing on to the tariff proposal and the
actual expenditure can be different due to a number of factors.
|
5.1.7.3
|
GRIDCO has informed that while
DISTCOs are paying pension to their employees who have retired after 01.4.99, GRIDCO is
discharging the liability of those retired before 01.4.99 and, therefore, comparison of
pension liabilities of GRIDCO vis-a-vis DISTCOs is irrelevant.
|
5.1.7.4
|
GRDICO has also rejected the
alternative cost proposals suggested by the objectors.
|
5.1.8
|
Depreciation and absence
of asset register Pre-1992 rates of depreciation should not apply as the
assets have been revalued and transferred to GRIDCO under Transfer Scheme Rules, 1996 |
5.1.9
|
Interest on long term
liabilities GRIDCO has stated that it has filed a petition before the
Commission regarding interest on bond issued to power suppliers and the decision is
awaited. The LIC loan is disputed regarding mortgage of assets only. The calculation of
interest is according to the existing loan agreement and the Commission approved the same
in its Tariff Order in case no. 27/2000. |
5.1.9.1
|
GRIDCO is contributing towards the
pension trust and GRIDCO is required to recover at least the interest for such huge
investment made towards pension trust in its Tariff. GRIDCO has requested the state
Government to convert ZCB to equity, which is under consideration of the government. A
part of ZCB is due for conversion during this year. Hence, GRIDCO has requested the
Commission to consider such conversion while calculating tariff for FY 2002.
|
5.1.10
|
Capital Base
|
5.1.10.1
|
Original cost of fixed
assets GRIDCO replied that the Commission has decided the issue of
revaluation of assets in its earlier orders. As this is in pursuance of Transfer Scheme
Rules, 1996 neither OHPC nor GRIDCO has any control over the same. |
5.1.11
|
Capital expenditure GRIDCO
replied that no specific example of delay in execution of PMU projects has been cited.
Accordingly, the contention of the objector not to allow interest on loan component is not
acceptable. Investment made by GRIDCO mostly accounts for improvement in the system
voltage reliability of power supply while simultaneously reducing the transmission loss to
some extent. |
5.1.12
|
Calculation of capital
base Objectors have argued that like previous years, zero coupon bonds
should be excluded from the capital base calculation. |
5.1.13
|
Reasonable return Some
objectors have pleaded that the Commission should follow GOI notification in 1999 on
reasonable return and calculate return based on vintage of the assets. |
5.1.14
|
Miscellaneous receipts SOUTHCO
and WESCO requested GRIDCO to furnish bills for power wheeled to other states and alleged
that the entire power from OPGC was being injected to MP. Such miscellaneous income should
be excluded from the revenue requirement. |
5.1.15
|
Transmission tariffs GRIDCO
maintained that the method of billing for power transmitted through displacement has been
approved by OERC. The question of availability of cheaper power at Choudwar grid and
billing at higher tariff to consumers of Choudwar has no relevance to the subject. |
5.1.15.1
|
As ICCL is using the transmission
system of GRIDCO, they are required to pay the necessary wheeling charges/transmission
tariff as approved by the Commission.
|
5.1.15.2
|
GRIDCO also maintained that no
agreement/contract excepting enforceable agreement/contract is valid under OER Act, 1995.
Therefore, the contention that GRIDCO cannot levy transmission tariff because of the
existing agreement is incorrect. The Policy Guidelines of development of micro/ mini/
small hydro electric projects issued by Government of Orissa is not a policy directive and
is not applicable to the present proceedings.
|
5.1.15.3
|
GRIDCO has objected to comparison of
its transmission charges with that of PGCIL as the basis of calculation is different. It
is also factually incorrect to state that PGCIL is charging 10 p/u, as the rate varies
from month to month and does not include transmission loss.
|
5.1.15.4
|
GRIDCO has reiterated that the
proposed wheeling charge is to encourage the CPPs to give additional power to GRIDCO, as
the power from CPP is very cheap. Besides, CPPs have helped in stabilising the power
supply for improvement of voltage at load centres where CPPs are located. It cannot be
compared to the situation of power wheeling from Kaniha to Meramundali or from Farakka to
State of Orissa.
|
5.1.16
|
Legal sanctity of
transmission tariff GRIDCO replied that fixation of wheeling charge at 10
paise/unit is conditional and is subject to transfer of power to western region. The
matter is to be taken up by CEA/MoP with Government of Orissa and hence, CEA's
recommendation is not in the final stage and not applicable. Moreover, CERC orders are
applicable to inter-state wheeling of power from Orissa to MP and not for intra-state
wheeling. CERC order on wheeling to MP has been contested in the Orissa High Court by
GRIDCO and the case is pending final disposal. |
5.1.17
|
Export of power GRIDCO
has taken up the matter of sale of surplus power to AP, Karnataka, Delhi and other states.
APTRANSCO is not willing to enter into long term PPA, as AP is going to be power surplus
with commissioning of Simadri power and BSES thermal power station. AP may not purchase
any power from GRIDCO on expiry of the present agreement on 31.3.2002. GRIDCO is in
constant dialogue with EREB and CEA to sort out the technical constraints for evacuation
of power from GRIDCO system. |
5.1.17.1
|
GRIDCO refuted the allegation that
it procured costly power and sold cheap power from Machkund. GRIDCO replied that it
procured power from TSTPS and FSTPS at an average rate of 191.73 paise/unit, which is less
than the rate at which power is sold to APTRANSCO.
|
5.1.18
|
Other issues It
would not be proper to await the decision of the state government on the Kanungo Committee
as appropriate tariff is required for improvement of financial health of GRIDCO. |
5.1.18.1
|
The proposed increase in tariff is
46% and not 60% claimed by the objectors.
|
5.1.18.2
|
GRIDCO has completed its audited
accounts for 1998-99 and submitted the same before OERC. The audited accounts for 1999-00
and 2000-01 are likely to be completed and filed with the Commission soon. The application
for FY 2002 is based on the management account and there is no bar in accepting the
management account for the purpose of revenue requirement.
|
5.1.18.3
|
GRIDCO is investing in new lines and
substations to ensure improved reliability of power supply. In fact, the outage rate has
been reduced considerably and reliable, uninterrupted power supply is generally available
from GRIDCO's EHT substations.
|
5.1.18.4
|
The OER Act specifically provides
that no rating committee shall be formed. Hence, the provision Section 57 A(2) of the
Electricity (Supply) Act, 1948 is not applicable.
|
5.1.18.5
|
GRIDCO is agreeable to pay the
escalation on landed cost of coal and fuel oil to NALCO. GRDICO has received the revised
escalation claim by NALCO without any supporting details. GRIDCO will consider the request
on receipt of the documents.
|
5.1.18.6
|
NALCO's establishments at
Bhubaneswar fall under the command area of CESCO and GRIDCO cannot wheel power from
NALCO's CPP to above places.
|
5.1.18.7
|
The Commission in every order in the
past has considered various objections and recorded them either for rejection or
acceptance as the case may be. Hence the question of throwing the objection to dustbin
after receipt does not arise.
|
5.1.18.8
|
As the Commission is bound to decide
the tariff within 90 days as per provision contained in the OER Act. Hence, time specified
by the Commission in the process of tariff proceedings appears to be reasonable.
|
5.1.18.9
|
Function of the Commission has been
clearly defined in the OER Act and the proposal of the objector that the Commission should
directly procure power is totally untenable.
|
5.1.18.10
|
It is not clear how a single-part or
two-part tariff does affect GRIDCO.
|
5.1.18.11
|
Electricity tariff is not the only
consideration for an unit to remain economically viable.
|