| 5.0 | GRIDCO's RESPONSE TO OBJECTIONS | 
  
    | 5.1 | Demand estimation | 
  
    | 5.1.1 | Energy requirement GRIDCO
    has also submitted that the power procurement proposed by GRIDCO is based on the proposals
    submitted to it by DISTCOs. Some discrepancy has been noticed in power procurement
    projection given by DISTCOs to GRIDCO and projection given in their tariff application.
    DISTCOs need to explain the discrepancy. | 
  
    | 5.1.1.1 | GRIDCO has rejected the alternative
    demand forecast made by some objectors by stating that the assumptions behind these
    forecasts have not been explained. The transmission loss calculation is incorrect in some
    cases. | 
  
    | 5.1.2 | Simultaneous Maximum
    Demand, Contract Demand and Billing Demand GRIDCO has replied that there is
    no justification for changing the method of computation of measurement of SMD because
    ultimately GRIDCO's revenue from such charges has to match its revenue requirement. The
    method of computation of SMD has little bearing on the whole issue. GRIDCO does not find
    the proposal of DISTCO's for reducing demand charges to be reasonable. | 
  
    | 5.1.3 | Levy of Overdrawal charge GRIDCO
    is not supposed to submit the certified and complete set of bills to DISTCOs but shall
    submit the same to the Commission.  | 
  
    | 5.1.4 | Transmission losses There
    is no problem in metering the activities of GRIDCO and the transmission loss based on
    actual figures and not assumptive ones. GRIDCO considers that the transmission loss cannot
    be substantially reduced. GRIDCO also requested the Commission to ignore the loss figure
    suggested by some DISTCOs, as this is based on one month's data. GRIDCO also replied that
    the revision of tariff is not dependent only on a single parameter and objection to the
    tariff revision proposal for not achieving desired loss level does not appear to be
    logical and judicious. | 
  
    | 5.1.4.1 | GRIDCO has also submitted that the
    increase in transmission loss from 4% to 4.6% is due to exclusion of energy flow in
    IB-Budhipadar-Korba line connected to the western grid. GRIDCO has submitted a business
    plan to reduce the transmission loss by 0.2% every year and the transmission loss will
    come down to 3.7% by 2006-07. The request made by objectors for allowing 3.5% transmission
    loss is not supported with evidential documents and, therefore, should be accepted. | 
  
    | 5.1.5  | Power procurement: Least
    cost drawal GRIDCO replied that its power procurement plan is based on
    least-cost combination of power to be procured from various generating stations. Hence,
    GRIDCO has no plan for purchase of high cost power when low cost power is available in the
    State. GRIDCO is making all efforts to draw maximum power from OHPC and during FY 2001-02,
    the drawal will be more than the estimated volume. GRIDCO is making every endeavour to
    draw maximum power from CPP as well. | 
  
    | 5.1.6 | Power procurement costs The
    existing PPA between GRIDCO and OPGC has been approved by GOO and the same has been
    submitted to OERC for approval. OERC has initiated the required proceedings. GRIDCO has
    received a proposal for two-part tariffs relating to Rengali and Upper Kolab stations of
    OHPC. GRIDCO is scrutinising the proposal. | 
  
    | 5.1.6.1 | GRIDCO has also rejected the cost
    estimates proposed by some objectors and stated that GRIDCO has considered station-wise
    cost of power based on the energy bills, year-end adjustment bills, tariff notifications
    and PPA. Continuance of rates approved by the Commission last year will put GRIDCO into
    loss in power procurement and will increase its overall loss. | 
  
    | 5.1.6.2 | GRIDCO has pointed out that the case
    on CERC order on tariff norms is pending in the Hon'ble High Court of Delhi and,
    therefore, the argument that the fixed costs should be reduced is premature. Till orders
    are passed by the appropriate authority, the change in the tariff of generating stations
    cannot be considered. | 
  
    | 5.1.6.3 | GRIDCO has requested the courts to
    implement ABT on prospective basis and not on retrospective basis. In case GRIDCO's prayer
    is not acceded to by the courts, GRIDCO may incur losses for which it has prayed the
    Commission to pass the loss in the next BST. | 
  
    | 5.1.7 | Transmission costs | 
  
    | 5.1.7.1 | Employee cost, A&G,
    R&M expenses GRIDCO is taking utmost care for incurring judicious
    expenditure on employees cost, O&M cost and A&G expenses. GRIDCO has denied that
    the increase in administrative and operational expenses is significant and unnecessary.
    Because of increase in cost of operation and cost of material, these costs are bound to
    increase. Increase in R&M expenses is due to additional repair and maintenance
    expenses needed for upkeep of system and restoration after flood damage during 2001-02.
    A&G expenses for FY 2002 include the stamp duty payable on bonds payable to
    generators. | 
  
    | 5.1.7.2 | GRIDCO has also refuted the
    allegation that it is disobeying the Commission's order. The Commission allows certain
    normative amounts under different heads for passing on to the tariff proposal and the
    actual expenditure can be different due to a number of factors. | 
  
    | 5.1.7.3 | GRIDCO has informed that while
    DISTCOs are paying pension to their employees who have retired after 01.4.99, GRIDCO is
    discharging the liability of those retired before 01.4.99 and, therefore, comparison of
    pension liabilities of GRIDCO vis-a-vis DISTCOs is irrelevant. | 
  
    | 5.1.7.4 | GRDICO has also rejected the
    alternative cost proposals suggested by the objectors. | 
  
    | 5.1.8 | Depreciation and absence
    of asset register Pre-1992 rates of depreciation should not apply as the
    assets have been revalued and transferred to GRIDCO under Transfer Scheme Rules, 1996 | 
  
    | 5.1.9 | Interest on long term
    liabilities GRIDCO has stated that it has filed a petition before the
    Commission regarding interest on bond issued to power suppliers and the decision is
    awaited. The LIC loan is disputed regarding mortgage of assets only. The calculation of
    interest is according to the existing loan agreement and the Commission approved the same
    in its Tariff Order in case no. 27/2000. | 
  
    | 5.1.9.1 | GRIDCO is contributing towards the
    pension trust and GRIDCO is required to recover at least the interest for such huge
    investment made towards pension trust in its Tariff. GRIDCO has requested the state
    Government to convert ZCB to equity, which is under consideration of the government. A
    part of ZCB is due for conversion during this year. Hence, GRIDCO has requested the
    Commission to consider such conversion while calculating tariff for FY 2002. | 
  
    | 5.1.10 | Capital Base | 
  
    | 5.1.10.1 | Original cost of fixed
    assets GRIDCO replied that the Commission has decided the issue of
    revaluation of assets in its earlier orders. As this is in pursuance of Transfer Scheme
    Rules, 1996 neither OHPC nor GRIDCO has any control over the same. | 
  
    | 5.1.11 | Capital expenditure GRIDCO
    replied that no specific example of delay in execution of PMU projects has been cited.
    Accordingly, the contention of the objector not to allow interest on loan component is not
    acceptable. Investment made by GRIDCO mostly accounts for improvement in the system
    voltage reliability of power supply while simultaneously reducing the transmission loss to
    some extent.  | 
  
    | 5.1.12 | Calculation of capital
    base Objectors have argued that like previous years, zero coupon bonds
    should be excluded from the capital base calculation. | 
  
    | 5.1.13 | Reasonable return Some
    objectors have pleaded that the Commission should follow GOI notification in 1999 on
    reasonable return and calculate return based on vintage of the assets. | 
  
    | 5.1.14 | Miscellaneous receipts SOUTHCO
    and WESCO requested GRIDCO to furnish bills for power wheeled to other states and alleged
    that the entire power from OPGC was being injected to MP. Such miscellaneous income should
    be excluded from the revenue requirement. | 
  
    | 5.1.15 | Transmission tariffs GRIDCO
    maintained that the method of billing for power transmitted through displacement has been
    approved by OERC. The question of availability of cheaper power at Choudwar grid and
    billing at higher tariff to consumers of Choudwar has no relevance to the subject. | 
  
    | 5.1.15.1 | As ICCL is using the transmission
    system of GRIDCO, they are required to pay the necessary wheeling charges/transmission
    tariff as approved by the Commission. | 
  
    | 5.1.15.2 | GRIDCO also maintained that no
    agreement/contract excepting enforceable agreement/contract is valid under OER Act, 1995.
    Therefore, the contention that GRIDCO cannot levy transmission tariff because of the
    existing agreement is incorrect. The Policy Guidelines of development of micro/ mini/
    small hydro electric projects issued by Government of Orissa is not a policy directive and
    is not applicable to the present proceedings. | 
  
    | 5.1.15.3 | GRIDCO has objected to comparison of
    its transmission charges with that of PGCIL as the basis of calculation is different. It
    is also factually incorrect to state that PGCIL is charging 10 p/u, as the rate varies
    from month to month and does not include transmission loss. | 
  
    | 5.1.15.4 | GRIDCO has reiterated that the
    proposed wheeling charge is to encourage the CPPs to give additional power to GRIDCO, as
    the power from CPP is very cheap. Besides, CPPs have helped in stabilising the power
    supply for improvement of voltage at load centres where CPPs are located. It cannot be
    compared to the situation of power wheeling from Kaniha to Meramundali or from Farakka to
    State of Orissa. | 
  
    | 5.1.16 | Legal sanctity of
    transmission tariff GRIDCO replied that fixation of wheeling charge at 10
    paise/unit is conditional and is subject to transfer of power to western region. The
    matter is to be taken up by CEA/MoP with Government of Orissa and hence, CEA's
    recommendation is not in the final stage and not applicable. Moreover, CERC orders are
    applicable to inter-state wheeling of power from Orissa to MP and not for intra-state
    wheeling. CERC order on wheeling to MP has been contested in the Orissa High Court by
    GRIDCO and the case is pending final disposal. | 
  
    | 5.1.17 | Export of power GRIDCO
    has taken up the matter of sale of surplus power to AP, Karnataka, Delhi and other states.
    APTRANSCO is not willing to enter into long term PPA, as AP is going to be power surplus
    with commissioning of Simadri power and BSES thermal power station. AP may not purchase
    any power from GRIDCO on expiry of the present agreement on 31.3.2002. GRIDCO is in
    constant dialogue with EREB and CEA to sort out the technical constraints for evacuation
    of power from GRIDCO system. | 
  
    | 5.1.17.1 | GRIDCO refuted the allegation that
    it procured costly power and sold cheap power from Machkund. GRIDCO replied that it
    procured power from TSTPS and FSTPS at an average rate of 191.73 paise/unit, which is less
    than the rate at which power is sold to APTRANSCO. | 
  
    | 5.1.18 | Other issues It
    would not be proper to await the decision of the state government on the Kanungo Committee
    as appropriate tariff is required for improvement of financial health of GRIDCO. | 
  
    | 5.1.18.1 | The proposed increase in tariff is
    46% and not 60% claimed by the objectors. | 
  
    | 5.1.18.2 | GRIDCO has completed its audited
    accounts for 1998-99 and submitted the same before OERC. The audited accounts for 1999-00
    and 2000-01 are likely to be completed and filed with the Commission soon. The application
    for FY 2002 is based on the management account and there is no bar in accepting the
    management account for the purpose of revenue requirement. | 
  
    | 5.1.18.3 | GRIDCO is investing in new lines and
    substations to ensure improved reliability of power supply. In fact, the outage rate has
    been reduced considerably and reliable, uninterrupted power supply is generally available
    from GRIDCO's EHT substations. | 
  
    | 5.1.18.4 | The OER Act specifically provides
    that no rating committee shall be formed. Hence, the provision Section 57 A(2) of the
    Electricity (Supply) Act, 1948 is not applicable. | 
  
    | 5.1.18.5 | GRIDCO is agreeable to pay the
    escalation on landed cost of coal and fuel oil to NALCO. GRDICO has received the revised
    escalation claim by NALCO without any supporting details. GRIDCO will consider the request
    on receipt of the documents. | 
  
    | 5.1.18.6 | NALCO's establishments at
    Bhubaneswar fall under the command area of CESCO and GRIDCO cannot wheel power from
    NALCO's CPP to above places. | 
  
    | 5.1.18.7 | The Commission in every order in the
    past has considered various objections and recorded them either for rejection or
    acceptance as the case may be. Hence the question of throwing the objection to dustbin
    after receipt does not arise. | 
  
    | 5.1.18.8 | As the Commission is bound to decide
    the tariff within 90 days as per provision contained in the OER Act. Hence, time specified
    by the Commission in the process of tariff proceedings appears to be reasonable. | 
  
    | 5.1.18.9 | Function of the Commission has been
    clearly defined in the OER Act and the proposal of the objector that the Commission should
    directly procure power is totally untenable. | 
  
    | 5.1.18.10 | It is not clear how a single-part or
    two-part tariff does affect GRIDCO. | 
  
    | 5.1.18.11 | Electricity tariff is not the only
    consideration for an unit to remain economically viable. |