6.21
|
Talcher Thermal Power
Station (TTPS)
|
6.21.1
|
Fixed cost
|
6.21.1.1
|
GRIDCO has submitted that NTPC has
filed a petition before the CERC to approve TTPS tariff for FY 2001 to 2005 where the
fixed cost for FY 02 is calculated at Rs.189.28 Crore which has been calculated for a
capital cost of Rs.431.83 Crore based on the audited figure of 1999-00. In the application
NTPC has also sought approval for increase in the fixed cost at the rate of Rs.1.88 lakhs
per month for additional capitalisation of Rs.1.00 Crore. The application is pending
before the CERC.
|
6.21.1.2
|
GRIDCO has submitted that as per
existing PPA and the MOU the tariff has to undergo a revision on year to year basis,
taking into account the capitalisation on account of R&M or otherwise. As per this
provision NTPC has claimed fixed charges of Rs.13.62 Crore per month from April 2000 due
to additional capitalisation of Rs.92.08 Crore during FY 2001. The expenditure on R&M
during FY 2002 is likely to be Rs.34.27 Crore.
|
6.21.1.3
|
GRIDCO has calculated the fixed cost
@ Rs.13.62 Crore per month for the full year based on bills presented by TTPS and
additional fixed cost due to R&M of Rs.34.27 Crore @ Rs.1.7 lakhs per month per Crore
of investment which aggregates to Rs.170.45 Crore per annum. As the proposal of GRIDCO is
in conformity with the terms of PPA and the Minutes of Meeting dt.23/24.09.1996 we accept
the fixed cost as proposed by GRIDCO. Therefore, for calculating the cost of power, the
Commission approves the fixed cost at Rs.170.45 Crore for the year 2001-02.
|
6.21.1.4
|
In its ARR application for
2002-03,GRIDCO has considered the same Rs.170.45 Crore as fixed cost and has requested to
allow recovery of additional cost as surcharge if the cost allowed by CERC is higher than
the cost considered for ARR application from the date the CERC order is made effective.
Pending finalisation of PPA the Commission approves the fixed cost as Rs.170.45 Crore for
FY 2002-03 in line with the observation made in the preceding paragraph.
|
6.21.2
|
Variable Charges
|
6.21.2.1
|
GRIDCO has stated that in its tariff
computation, NTPC indicated the variable cost as 55.66 paise/unit, based on revised
station parameters. The significant change is the increase of Station Heat Rate from 3200
kCal/kWh to 3300 kCal/kWh and of Auxiliary Consumption from 11.75% to 12%.
|
6.21.2.2
|
GRIDCO has disputed the change in
station parameters applied for in NTPCs petition to CERC. NTPC, however, has
insisted that the station parameters signed in its earlier PPA could not be achieved, and
now proposes a realistic target.
|
6.21.2.3
|
GRIDCO has proposed variable charges
which includes FPA for TTPS at 65.97 paise/unit for FY 02 based on average of costs of
coal and oil for FY 01 and its calorific value with an escalation of 10%.
|
6.21.2.4
|
Commission has based its calculation
of variable cost taking into consideration the cost of fuel and the calorific value which
has been averaged for a period of eleven months taken out from the bills served by TTPS
for the FY 2001-02 upto February, 2002. Accordingly, the Commission approves a variable
charge of 66.30 paise/unit as against 65.97 paise/unit proposed by GRIDCO.
|
6.21.2.5
|
For 2002-03, GRIDCO has proposed the
same 65.97 paise/unit as variable charge. The Commission considers it reasonable to give
an escalation of 4% towards change in price of oil and coal for the FY 2002-03 over the
variable charges of 2001-02 and accordingly, approves variable charges of 67.43 paise/unit
for FY 2002-03.
|
6.21.3
|
Year End Charges
|
6.21.3.1
|
GRIDCO in its application for FY
2001-02 has submitted that the year end charges of TTPS include cess on water, water
charges, electricity duty and income tax. Considering the claim of 2000-01 as the base
year GRIDCO in its BST application estimates a total requirement of Rs.29.81 Crore for the
FY 2001-02. On 30.3.2002, GRIDCO has in its calculation said that year end charges would
be 26.24 paise/unit. The Commission examined the claims and has approved the following
projections as year end adjustment for the FY 2001-02. Water cess and water charges of
Rs.0.39 Crore, Electricity duty calculated @ 12 paise/unit on an auxiliary consumption on
normative level of generation is estimated at Rs.3.57 Crore, Income tax of Rs.38.55 crore
based on advance income tax bill raised by NTPC for April, 2001 to December, 2001 and
prorated to 12 months. GRIDCO has also claimed Rs.1.93 Crore towards income tax paid of
the year 1997-98. However, it is felt that the arrear income tax paid for 1997-98 is not
justifiable as a pass through in 2001-02 in the absence of audited accounts and,
therefore, is not allowed. The total year end charges approved for the year 2001-02 is
thus Rs.42.50 Crore as against Rs.57.99 Crore proposed by GRIDCO on 30.3.2002.
|
6.21.3.2
|
For the year 2002-03, GRIDCO has
proposed year end charges of Rs.28.11 Crore towards income tax, electricity duty, water
charges and FPA adjustment. Commission approves a figure of Rs.42.50 Crore towards year
end charges i.e. at the same level as that the year 2001-02.
|
6.21.4
|
Orissa Power Generation
Corporation (OPGC)
|
6.21.4.1
|
Fixed cost: OPGC as reported by
GRIDCO has submitted its tariff calculation for FY 02 claiming a fixed cost of Rs.248.777
Crore. The tariff calculation as agreed to between OPGC and GRIDCO has been submitted in
(ED-4 of volume 3) where the fixed cost is accepted as Rs.247.928 Crore.
|
6.21.4.2
|
After checking calculations, the
Commission approves the fixed cost as Rs.247.93 Crore. The same figure has been proposed
by GRIDCO in its ARR application for 2002-03, which is provisionally accepted.
|
6.21.4.3
|
Variable charges :
The variable charges as proposed by OPGC is 51.93 paise/unit both for 2001-02 and 2002-03.
This figure has been checked at the Commissions end and the Commission accepts the
figure of 51.93 paise/unit.
|
6.21.4.4
|
FPA : In FY 2002
& FY 2003 application the FPA has been claimed @4.39 paise/unit assuming an escalation
of 10% on the average cost of fuel and its calorific value for the year 2000-01.
|
6.21.4.5
|
The Commission does not consider the
rate of escalation proposed at 10% to be appropriate and reasonable as the rate of
inflation is hovering around 4%. Therefore after considering an escalation of 4% on the
FPA of 2000-01 calculation the Commission arrives at a figure of 4.15 paise/unit for
2001-02. For 2002-03 the Commission considers it appropriate to give an escalation of 4%
on the estimated FPA of 2001-02 and accordingly, approves 4.32 paise/unit for the year
2002-03.
|
6.21.4.6
|
Year end charges: GRIDCO
has proposed year end charges of Rs.30.05 Crore on account of charges for land tax, water
cess, electricity duty and incentive based on actual bills of OPGC for FY 2001. On
30.3.2002, GRIDCO has submitted that total year end charges would be Rs.27.98
Crore. This
has been examined at the Commissions end and income tax is approved at Rs.11.75
Crore and water cess and land tax & rate at Rs.0.14 Crore based on the bills given by
OPGC and electricity duty at Rs.2.87 Crore calculated @12 paise/unit on the auxiliary
consumption for the year 2001-02. The total year end charges approved for 2001-02 is
Rs.14.77 Crore. No incentive has been given as the generation is kept at normative level.
For the year 2002-03, income tax and water cess, rent, land tax, electricity duty have
been kept at the same level. Accordingly, Commission approves Rs.14.77 Crore for FY
2002-03.
|
6.21.4.7
|
Captive Power Plants (CPP) :
GRIDCO in its application for FY 2001-02 and 2002-03 has stated that the procurement cost
for energy receipt from CPP is Rs.93.76 paise/unit comprising of 77 paise/unit as the base
rate and 16.76 paise/unit towards escalation on account of increasing of fuel cost. The
Commission has taken this rate into consideration for determining the cost of power
purchase from the CPP.
|
6.21.5
|
Central Power Stations
|
6.21.5.1
|
Transmission Loss :
The constituents of the eastern region share the losses occurring in the central
transmission system. For the year 2001-02 based on the figure of the global account for
the last 11 months the loss works out to 3.84%. The charges payable to the central
generation and transmission system are adjusted to account for the losses in the central
transmission system. This rate percentage has also been considered for determination of
loss for the FY 2002-03 as this is based on the data on the past 11 months as stated
earlier.
|
6.21.5.2
|
Transmission Charge for
PGCIL Lines : GRIDCO has stated that Government of India Notification dtd. 04
December, 1998, 11 May, 1999, 14 May, 1999 together notified tariffs of Farakka,
Kahalgaon, Talcher and Chukha transmission system as well as Rangit/Melli and Rangit/Raman
lines. The CERC has passed interim orders for payment of 80%, 88% and 80% of the fixed
cost indicated by PGCIL in their application for Dehri-Karmanasha, Jeypore-Gazuwaka and
Budhipadar-Korba transmission lines. PGCIL has submitted application to CERC for tariff
fixation for Rangit-Siliguri and Malda-Bongaigaon transmission system. As per CERC order
dated 22.6.99, tariff for Rs.5.0917 Crore is paid for FY 2002 towards Rangit-Siliguri
transmission system and order dated 17.11.2000 tariff of Rs.22.843 Crore is paid for FY
2002 towards Malda-Bongaigaon transmission system.
|
6.21.5.2.1
|
In this BST application, GRIDCO has
considered the annual fixed charges of Rs.262.366 Crore for all the above, based on the
application.
|
6.21.5.2.2
|
PGCIL is eligible for incentive for
availability above 95%. In this application, an availability level of 99% is assumed for
computation of incentive and the amount of Rs.4.48 Crore is considered which is based on
the actual for FY 2001.
|
6.21.5.2.3
|
The amount of income tax for the
ensuing year is based on the actual advance income tax paid by PGCIL in FY 01 i.e. Rs.8.14
Crore.
|
6.21.5.2.4
|
PGCIL has raised an additional
charge to recover annual maintenance cost (AMC) of the special type energy meters
installed at interface points. For the ensuing year, Rs.5.00 lakh is taken, which is as
per actual bills of FY 2001.
|
6.21.5.2.5
|
PGCIL has billed separately towards
Foreign Exchange Rate Variation (FERV) of Rs.4.8 Crore, backed by a Government of India
notification, in FY 2001. The same amount is considered for FY 02.
|
6.21.5.2.6
|
The calculation furnished by GRIDCO
in form DF18 has been checked up at the Commissions end wherein GRIDCO has shown the
figure as Rs.237.43 Crore and year end charges of Rs.15.22 Crore, total being Rs.252.65
Crore. However, in the application as stated above GRIDCO has considered the annual tariff
as claimed by PGCIL of Rs.279.83 Crore. Taking the CERC order into consideration we feel
that it is reasonable to take the estimate of Rs.252.65 Crore as fixed cost of PGCIL
transmission system charges for the FY 2001-02 and as well as FY 2002-03. The energy
billed in the EREB system has been taken as 19469.93 MU based on global accounts for the
months April, 2001 to February,2002 and prorated for the month of March 2002. As such it
is estimated that the transmission charge including central transmission loss to be 13.50
paise/unit for the year 2001-02. This rate is also considered for the year 2002-03.
|
6.21.5.3
|
Chukka : GRIDCO in
its application of FY 02 has stated that the procurement cost from Chukka is taken as per
the Government of India notification dated 26.08.99 as per the details below.
-
100 paise/unit for the period June to September
-
150 paise/unit for balance period (April to May and October to March)
-
A further five paise/unit is added to the above rates based on PGCIL letter dated 19
November 1999 to the Eastern Region beneficiaries, levied for the Power Trading
Corporation (PTC). In addition to this, GRIDCO has to bear the Central Transmission losses
on the PGCIL net work and also has to pay for the transmission charges. GRIDCO has
proposed a rate of 163.06 paise/unit for 2001-02 and 151.40 paise/unit for 2002-03.
|
6.21.5.3.1
|
Based on the actual drawl from this
power station taken from the global account of EREB upto February, 2002 and projection for
March, 2002 it is observed that the average rate per unit of this power station works out
to Rs.150.66 paise/unit inclusive of central transmission loss and transmission charges.
|
6.21.5.3.2
|
For the year 2002-03, it is expected
that GRIDCO would have full drawl of our share from the Chukha power station. It is
estimated that the rate per unit from this power station inclusive of central transmission
loss and PGCIl transmission charges will be 143.59 paise/unit. The estimated higher rate
for the year 2001-02 is on account of non-drawal of Orissa share particularly during the
monsoon period.
|
6.21.5.4
|
Central Thermal Power
Station : Under ERC Act, the tariff in respect of the Central Power Stations will
be determined by the Central Electricity Regulatory Commission from 15.5.99 onwards.
|
6.21.5.4.1
|
The Ministry of
Power, Government of India have notified the tariff in respect of the Talcher Super
Thermal Power Station Kaniha (Orissa), Farakka Super Thermal Power Station (West Bengal),
Kahalgaon Super Thermal Power Station (Bihar) under Section 43(A) of The Act, 1948 prior
to 15.5.99. This tariff is, therefore, current and has not been replaced as yet. |
6.21.5.4.2
|
The Commission has analysed the
various parameters for calculation of tariff payable by GRIDCO for drawal of power from
Central Thermal Stations. Table : 20
Energy sent out ESO
(Figures In MU)
|
2001-02 |
2002-03 |
Central Thermal Stations |
Proposed by GRIDCO |
Estimated by Commission |
Proposed by GRIDCO |
Estimated by Commission |
Talcher STPS |
5501.53 |
5964.73 |
5168.13 |
5964.73 |
Farakka STPS |
7898.71 |
7797.94 |
8006.261 |
7797.94 |
Kahalgaon STPS |
4215.02* |
4022.47 |
4369.66 |
4022.47 |
Total |
17615.26 |
17785.14 |
17544.051 |
17785.14 |
* DF-12, 13 & 14 |
6.21.5.4.3
|
The forecast of energy sent out from
the various Central Thermal Stations are provided by GRIDCO in form DF12, 13 & 14 of
BST 2002 filing. The Commission examined the generation figures of these stations from the
global account of energy prepared by the EREB for the period of April 2001 to February,
2002 and thereafter took into consideration the generation projection by EREB for the
months of March, 2002 and arrived at the estimated energy sent out for the FY 2001-02.
|
6.21.5.4.4
|
For the FY 2002-03 the figures of
ESO proposed by GRIDCO has not been substantiated by any evidential document to justify
the departure and as such the Commission estimates that the same level of generation as
approved by Commission for 2001-02 will be same for the FY 2002-03.
|
6.21.5.5
|
Fixed Cost: The
fixed cost of various central thermal stations based on Government of India notification
is given in Table : 21. Table : 21
Fixed Cost
Central Thermal
Stations |
Fixed cost for FY
00-01 (Rs. InCrore) |
Date of Notification |
Effective till |
Talcher STPS |
644.99 |
May 7, 99 |
March 31, 2000 |
Farakka STPS |
668.33 |
May 5, 99 |
March 31, 2002 |
Kahalgaon STPS |
477.88 |
December 9, 98 |
March 31, 2000 |
|
6.21.5.5.1
|
GRIDCO in its BST filing of 2001-02
in para 2.5.8.1 has stated that GRIDCO has made fixed cost calculation based on the recent
petition filed by NTPC to CERC for approval of revised fixed charge due to additional
capitalisation and foreign exchange rate variation for the years 1997-98 to 2000-01 in
respect of the generating station.
|
6.21.5.5.2
|
GRIDCO has stated that the fixed
cost calculated as per the aforesaid NTPC filing comes to Rs.713.458 Crore for FSTPS,
Rs.660.636 Crore for TSTPS and Rs.504.215 Crore for Kahalgaon. The revised schedule of
charges is yet to be finalised by CERC. For the projected generation, the effective per
unit cost for year 2001-0-2 including adjustment for Central Sector line loss is 129.24
paise/unit for Talcher STPS, 80.80 paise/unit for Farakka STPS and 97.87 paise/unit for
Kahalgaon TPS. If the projected generation is not achieved the fixed cost per unit as
proposed will go up proportionately.
|
6.21.5.5.3
|
The proposal of GRIDCO was examined
at Commissions end. In the absence of order by CERC the Commission has calculated
the fixed cost as per the existing GOI notification subject to final order by
CERC.
Incidentally it may be mentioned that GRIDCO is being billed on the basis of the
Government of India notification as indicated in para 6.21.5.5. Accordingly, the fixed
cost as proposed by GRIDCO and estimated by Commission for the purpose of calculation for
the year 2001-02 is given in Table : 22. Table : 22
Fixed Cost
(Rs. in Crore)
Central Thermal Stations |
GRIDCOs
Proposal |
Commissions
Estimate |
Talcher STPS |
660.636 |
644.99 |
Farakka STPS |
713.458 |
668.33 |
Kahalgaon STPS |
504.215 |
477.88 |
|
6.21.5.5.4
|
GRIDCO has proposed the same fixed
cost for 2002-03 as proposed in 2001-02. The fixed cost estimated by the Commission for
the FY 2001-02 will also apply in respect of the FY 2002-03 pending finalisation of order
by CERC.
|
6.21.5.6
|
Variable charges: GRIDCO
in para 2.5.8.2 of the BST application FY 2001-02 and ARR application FY 2002-03 have
furnished the calculation of variable charges prepared in accordance with the GoI
notification. Table : 23
Central Thermal
Stations |
Variable charge for
FY 2001-02 (Paise/unit) |
Date of Notification |
Effective till |
Talcher STPS |
32.72 |
May 5, 1999 |
March 31, 2000 |
Farakka STPS |
46.16 |
May 7, 1999 |
March 31, 2002 |
Kahalgaon STPS |
50.86 |
December 9, 1998 |
March 31, 2000 |
|
6.21.5.6.1
|
The Commission has accepted the
rates as provided in Government of India notification as outlined above. The rates stated
above been applied for the FY 2002-03.
|
6.21.5.6.2
|
The rate of variable charge
inclusive of adjustment of central line loss proposed by GRIDCO (Central line loss of 4%)
and estimated by Commission (Central line loss of 3.55%) is given in Table : 24. This rate
has also been accepted for the purpose of calculation of variable charges for the FY
2002-03. Table : 24
(Paise/unit)
Central Thermal Stations |
GRIDCOs
Proposal |
Commissions
Estimate |
Talcher STPS |
34.13 |
34.03 |
Farakka STPS |
48.07 |
48.01 |
Kahalgaon STPS |
52.98 |
52.89 |
|
6.21.5.7
|
Fuel Price Adjustment :
FPA has been calculated by GRIDCO on the basis of actual bills for the period April to
August, 2001 with an escalation of 10%. GRIDCO estimates the FPA for FY 2002 including
Central line losses at 7.40 paise/unit for TSTPS, 55.24 paise/unit for FSTPS and 49.83
paise for KhSTPS in para 2.5.8.3 of the BST application for the FY 2001-02. GRIDCO in its
ARR application of 2002-03 has considered the same base i.e. the average of cost of fuel
and calorific value for the months of April to August, 2001 with an escalation to 10%.
They have calculated the FPA as 7.39 paise/unit, for TSTPS 55.13 paise/unit for FSTPS,
49.85 paise/unit for KhSTPS inclusive of Central line losses. The Commission took into
consideration the cost of fuel and calorific value on the basis of the data available for
the period of April 2001 to February 2002. Since the calculation is being done on the
billing figures for past eleven months for the year 2002, no escalation on these figures
is considered for 2001-02. While calculating for 2002-03, an escalation of 10% as has been
proposed by GRIDCO has been taken into consideration over the base figure of 2001-02.
|
6.21.5.7.1
|
The rates of FPA as proposed by
GRIDCO and as estimated by the Commission inclusive of central transmission loss for the
year 2001-02 is given in Table: 25. Table : 25
(Paise/unit)
|
2001-02 |
2002-03 |
Central Thermal Stations |
GRIDCOs
Proposal |
Commissions
Estimate |
GRIDCOs
Proposal |
Commissions
Estimate |
Talcher STPS |
7.40 |
7.01 |
7.39 |
7.71 |
Farakka STPS |
55.24 |
49.08 |
55.13 |
53.99 |
Kahalgaon STPS |
49.83 |
51.07 |
49.85 |
56.18 |
|
6.21.5.8
|
Miscellaneous Charges
(Income Tax, Incentive, Water Cess and Water Charges): GRIDCO has projected the
year-end charges for FY 2002 at par with the actual bills claimed by NTPC for FY 1999-00
upto February 2000 and annualize the figures. It has said that all charges except
incentive are based on actual dues of NTPC. It has proposed year-end charges adjusting for
central line losses is 31.94 paise/unit for TSTPS, 22.82 paise/unit for FSTPS and 27.20
paise/unit for KhSTPS. On 30.03.2002 GRIDCO has submitted the year-end charges for various
Central Thermal Stations based on the following parameters.
-
Income tax has been calculated on the basis of claim from 4/2001 to 12/2001 and has been
projected for the months of January to March 2002.
-
Water cess claimed on basis of amount paid from 4/2001 to 6/2001 has been projected for
the months of July 2001 to March 2002.
-
Electricity duty has been assessed only in respect of TSTPS based on the assessment of
FY 2000-01.
-
Incentive in respect of all the three stations has been assessed on the basis of
estimates of the FY 2000-01.
|
6.21.5.8.1
|
The Commission has checked the
proposal and based on following parameters has calculated the year-end charges.
-
Income Tax has been calculated on the basis of advance income tax bill claimed by NTPC
for the months of April, 2001 to December, 2001 and prorated for 12 months.
-
Water cess based on bills raised on GRIDCO for 1999-00.
-
Electricity duty for TSTPS based on the auxiliary consumption for 2001-02 has been
calculated @ 12 paise/unit.
-
Incentive has been given as per actual E.S.O. achieved for year 2001-02.
|
6.21.5.8.2
|
Accordingly, the year end adjustment
approved by the Commission inclusive of central transmission loss is given in Table : 26. Table : 26
Year End Charges (FY 2001-02)
(Paise/unit)
Central Thermal Stations |
GRIDCOs
Proposal December, 2001 |
GRIDCOs projection
dt.30.03.2002 |
Commissions
Estimate |
Talcher STPS |
31.94 |
21.96 |
16.24 |
Farakka STPS |
22.82 |
25.70 |
18.09 |
Kahalgaon STPS |
27.20 |
30.08 |
18.20 |
|
6.21.5.8.3
|
For the year 2002-03, GRIDCO has
proposed year-end charges at par with the actual bills claimed by NTPC for 1999-00 and
annualized. Accordingly, the year end charges adjusted for the Central line losses is
given in Table : 26. The Commission feels it reasonable to adopt the year end charges
similar to that of FY 2001-02. Accordingly, the Commissions estimate is also given
in Table : 27. Table : 27
Year End Charges (FY 2002-03)
(Paise/unit)
Central Thermal Stations |
GRIDCOs Proposal |
GRIDCOs projection
dt.30.03.2002 |
Commissions Estimate |
Talcher STPS |
33.96 |
21.96 |
16.24 |
Farakka STPS |
22.50 |
25.70 |
18.09 |
Kahalgaon STPS |
25.17 |
30.08 |
18.20 |
|
6.21.5.8.4
|
GRIDCOs proposed cost of power
from various generating stations and Commissions
approval of such cost have been given in Table : 28 for 2001-02 and in Table 29 for
2002-03. Table : 28
Comparison of Power Purchase Costs for 2001-02
GRIDCOs Proposal
Source
|
Requirement
MU |
Fixed
Cost P/U |
Variable
Cost P/U |
FPA
P/U |
Misc
(Yr.end) P/U |
PGCIL
Tr. Charge P/U |
Total
Cost P/U |
Total
Cost (Rs.in Cr.) |
OHPC
|
3676.86 |
- |
72.11 |
- |
- |
- |
72.11 |
265.13 |
Machhkund
|
301.49 |
- |
11.00 |
- |
- |
- |
11.00 |
3.32 |
Indravati*
|
1942.38 |
- |
117.30 |
- |
- |
- |
117.30 |
227.84 |
TTPS
|
2203.92 |
77.34 |
65.97 |
- |
13.52 |
- |
156.83 |
345.65 |
Ib TPS
|
2280.30 |
108.73 |
51.93 |
4.39 |
13.18 |
- |
178.22 |
406.40 |
CPPs
|
59.44 |
- |
77.00 |
16.76 |
- |
- |
93.76 |
5.57 |
Total State
|
10464.38 |
39.98 |
73.07 |
1.05 |
5.72 |
- |
119.83 |
1253.92 |
FSTPS
|
501.10 |
80.80 |
48.07 |
55.24 |
22.82 |
14.99 |
221.92 |
111.20 |
KhSTPS
|
170.43 |
97.87 |
52.98 |
49.83 |
27.20 |
15.73 |
243.61 |
41.52 |
TSTPS
|
728.93 |
129.24 |
34.13 |
7.40 |
31.94 |
14.61 |
217.32 |
158.41 |
Chukha
|
126.33 |
- |
147.61 |
- |
- |
15.44 |
163.06 |
20.60 |
Total C.S.
|
1526.79 |
|
|
|
|
|
217.27 |
331.73 |
Total
|
11991.17 |
47.51 |
70.16 |
4.39 |
8.27 |
1.90 |
132.23 |
1585.65 |
Billed Amount
(Rs..in Cr.)
|
569.75 |
841.32 |
52.58 |
99.20 |
22.79 |
1585.65 |
|
Note : (Central transmission loss of 4% for central
stations included)
Commissions Approval
Source
|
Requirement
MU |
Fixed
Cost P/U |
Variable
Cost P/U |
FPA P/U |
Misc
(Yr.end) P/U |
PGCIL
Tr. Charge P/U |
Total
Cost P/U |
Total
Cost (Rs.in Cr.) |
OHPC
|
3311.78 |
|
24.99 |
|
|
|
24.99 |
82.75 |
Machhkund
|
319.48 |
|
11.00 |
|
|
|
11.00 |
3.51 |
Indravati*
|
2909.01 |
|
44.90 |
|
|
|
44.90 |
130.62 |
TTPS
|
2232.53 |
76.35 |
38.19 |
28.11 |
19.04 |
|
161.69 |
360.98 |
Ib TPS
|
2280.50 |
108.72 |
51.93 |
4.15 |
6.47 |
|
171.27 |
390.59 |
CPPs
|
476.22 |
|
93.76 |
|
|
|
93.76 |
44.65 |
Total State
|
11529.52 |
36.29 |
40.35 |
6.27 |
4.97 |
- |
87.87 |
1013.10 |
FSTPS
|
198.50 |
89.13 |
48.01 |
49.08 |
18.09 |
13.50 |
217.81 |
43.24 |
KhSTPS
|
40.54 |
123.55 |
52.89 |
51.07 |
18.20 |
13.50 |
259.22 |
10.51 |
TSTPS
|
433.41 |
112.46 |
34.03 |
7.01 |
16.24 |
13.50 |
183.23 |
79.41 |
Chukha
|
143.10 |
|
137.16 |
|
|
13.50 |
150.66 |
21.56 |
Total C.S.
|
815.55 |
|
|
|
|
|
189.71 |
154.72 |
Total
|
12345.07 |
39.68 |
41.42 |
7.05 |
5.56 |
0.89 |
94.60 |
1167.82 |
Billed Amount
(Rs..in Cr.)
|
489.82 |
511.27 |
87.08 |
68.64 |
11.01 |
1167.82 |
|
Note : Central Transmission Loss of 3.84% for central sector stations
included.
Table : 29
Comparison of Power Purchase Costs for 2002-03
GRIDCOs Proposal
Source
|
Requirem-ent
MU |
Fixed
Cost P/U |
Variable
Cost P/U |
FPA
P/U |
Misc (Yr.end) P/U |
PGCIL
Tr. Charge P/U |
Total
Cost P/U |
Total
Cost (Rs.in Crs.) |
OHPC
|
3,415.50 |
|
72.11 |
|
|
|
72.11 |
246.29 |
MACHAKUND
|
315.29 |
|
11.00 |
|
|
|
11.00 |
3.47 |
INDRAVATI *
|
1,942.38 |
|
117.30 |
|
|
|
117.30 |
227.84 |
TTPS
|
2,203.92 |
77.34 |
65.97 |
- |
12.75 |
|
156.06 |
343.95 |
IB TPS
|
2,726.62 |
90.93 |
51.93 |
4.39 |
12.21 |
|
159.46 |
434.79 |
CPPs
|
635.00 |
|
93.76 |
|
|
|
93.76 |
59.54 |
TOTAL STATE
|
11,238.70
|
37.23
|
73.33
|
1.07
|
5.46
|
-
|
117.08
|
1,315.88
|
FSTPS
|
596.38 |
89.13 |
48.08 |
55.13 |
22.50 |
15.18 |
230.02 |
137.18 |
KHSTPS
|
- |
|
|
|
|
|
- |
- |
TSTPS
|
696.96 |
139.41 |
34.08 |
7.39 |
33.96 |
15.14 |
229.98 |
160.29 |
CHUKKA
|
150.23 |
|
136.24 |
|
|
15.25 |
151.49 |
22.76 |
TOTAL C.S.
|
1,443.57
|
|
|
|
|
|
221.83
|
320.23
|
TOTAL
|
12,682.27
|
44.84
|
70.73
|
3.94
|
7.77
|
1.73
|
129.01
|
1,636.11
|
Billed Amount (Rs.in Crs.)
|
568.69 |
897.02 |
50.01 |
98.49 |
21.89 |
1,636.11 |
|
Note : (Central transmission loss of 4.00% for central stations
included)
Commissions Approval
Source
|
Requirement
MU |
Fixed
Cost P/U |
Variable
Cost P/U |
FPA P/U |
Misc
(Yr.end) P/U |
PGCIL
Tr. Charge P/U |
Total
Cost P/U |
Total
Cost (Rs.in Cr.) |
OHPC
|
3676.86 |
|
24.73 |
|
|
|
24.73 |
90.93 |
Machhkund
|
315.29 |
|
11.00 |
|
|
|
11.00 |
3.47 |
Indravati*
|
1942.38 |
|
63.82 |
|
|
|
63.82 |
123.96 |
TTPS
|
2232.53 |
76.35 |
38.19 |
29.24 |
19.04 |
|
162.82 |
363.49 |
Ib TPS
|
2280.50 |
108.72 |
51.93 |
4.32 |
6.47 |
|
171.44 |
390.97 |
CPPs
|
900.00 |
|
93.76 |
|
|
|
93.76 |
84.38 |
Total State
|
11347.56 |
36.87 |
44.63 |
6.62 |
5.05 |
- |
93.17 |
1057.21 |
FSTPS
|
291.60 |
89.13 |
48.01 |
53.99 |
18.09 |
13.50 |
222.71 |
64.94 |
KhSTPS
|
- |
123.55 |
52.89 |
56.18 |
18.20 |
13.50 |
264.33 |
- |
TSTPS
|
1443.06 |
112.46 |
34.03 |
7.71 |
16.24 |
13.50 |
183.93 |
265.42 |
Chukha
|
230.00 |
|
130.09 |
|
|
13.50 |
143.59 |
33.03 |
Total C.S.
|
1964.66 |
|
|
|
|
|
184.96 |
363.39 |
Total
|
13312.22 |
45.57 |
45.03 |
7.66 |
6.46 |
1.99 |
106.71 |
1420.60 |
Billed Amount
(Rs..in Cr.)
|
606.65 |
599.46 |
101.99 |
85.98 |
26.51 |
1420.60 |
|
Note : Central Transmission Loss of 3.84% for central
sector stations included. |