3.0
|
NESCOS PROPOSAL
|
3.1
|
The North Eastern Supply Company of
Orissa Ltd. (NESCO) is carrying out the business of distribution and retail supply of
electricity in four Districts and a part of one district of State of Orissa namely
Mayurbhanj, Keonjhar, Bhadrak, Balasore and major part of Jajpur. The company receives
bulk supply from GRIDCO at several interconnected points at HT and EHT.
|
3.2
|
The profile of the company as on 31
March 2001 portrays a graphic account of current activities.
Total no. of consumers
|
-
|
3,11,804
|
Total input in MU
|
-
|
2443
|
Total billing in MU
|
-
|
1357
|
Total billing in lakhs of rupees
|
-
|
30778.97
|
33 KV lines (in Kms.)
|
-
|
1881.2
|
11KV lines (in Kms.)
|
-
|
11317.17
|
LT lines (in Kms.)
|
-
|
14125.15
|
33/11KV sub-stations
|
-
|
182 nos.
|
11/0.4 KV sub-stations
|
-
|
8380 nos.
|
|
3.3
|
The comparative figure of
consumption at different voltage levels as well as energy purchase in MU from the FY 98-99
onwards with a projection for the future periods is taken from various filings with the
Commission & tabulated to serve as an indicator about pattern of consumption in the
area of licence. Table-1
Energy Sale & Purchase
Segment
|
FY 99 Billing MU
|
FY 00 Billing MU
|
FY 01 Billing MU
|
FY 02 Billing MU
|
FY 03 Expected Billing
MU
|
LTcategory
|
482.498 |
506 |
515 |
611.34 |
667.55 |
HT category
|
204.774 |
312 |
355 |
306.26 |
313.69 |
EHT category
|
454.071 |
461 |
487 |
243.72 |
293.716 |
Total Sales
|
1141.343 |
1279 |
1357 |
1161.32 |
1274.95 |
Energy purchase
|
|
2258 |
2443 |
2208.4 |
2291.2 |
|
3.4
|
Sale Mix Analysis The
voltage wise sale mix of consumers is given in the table below to indicate that the
consumption is getting skewed in favour of LT which has been taken from technical format
T-1 and RST application for the FY 2000-01,para-3 of the RST application of 2001-02 for
the FYs 1999-00 and 2000-01 and the same data in respect of FY 2002 and 2003 has been
taken from technical format T-1 of RR application 2002-03.
Table-2
Sale mix variation
Segment
|
NESCO FY
99 |
NESCO FY 00
|
NESCO FY 01 |
NESCO FY 02 |
NESCO FY 03
|
|
% of Total |
% of Total |
% of Total |
% of Total |
% of Total |
LT category
|
42.27 |
39.56 |
37.95 |
52.64 |
52.36 |
HT category
|
17.94 |
24.39 |
26.16 |
26.37 |
24.60 |
EHT category
|
39.78 |
36.04 |
35.89 |
20.99 |
23.04 |
Total
|
100.0% |
100.0% |
100% |
100% |
100% |
FY 2001-02 |
3.5
|
NESCO in its RST application of FY
01-02 has stated that there exists a very high degree of non-technical loss in its LT
distribution system. It expects a growth rate of 24% in the domestic category for the year
2001-02 on the assumption that during the ensuing year a large number of consumers may be
inducted into the billing net in addition to regular checking of meters in order to
achieve the targeted growth rate.
|
3.6
|
NESCO estimates a growth of 23% in
respect of commercial consumption and 22% in respect of irrigation consumer due to
aggressive metering policy and regularization of hooking consumers and stoppage of
pilferage and unauthorised abstraction of energy.
|
3.7
|
In respect of HT consumers it
expects a negative growth due to closure of TISCO Unit at Joda for about 3 months and
switching over of industrial consumers to captive generation and reduction in demand.
|
3.8
|
Equal apprehension has been
expressed by NESCO in respect of EHT consumption due to recession in Ferro Chrome sector
resulting in either shut down or sub-optimal operation of the Ferro Chrome industries in
Orissa, FY 2002-03 |
3.9
|
NESCO estimates a growth rate of 10%
in domestic category, 12% for commercial category and 7% for irrigation category for FY
2002-03 based on the trend of the previous year.
|
3.10
|
It expects a growth rate of 2% in HT
category based on the pattern of consumption available upto 2001-02 and a meagre rise of
about only 1% in EHT category based on the consumption trend of the preceeding year and
expecting revival of one of the EOUs.
|
3.11
|
REVENUE REQUIREMENT
|
3.11.1
|
The licensee is required to meet
the cost of power purchase from GRIDCO, the cost of distribution which covers expenses on
account of employees, administration and general expenses, repair and maintenance
expenses, depreciation, interest on loan, appropriation to contingency reserve and
provision for bad and doubtful debts. In addition to this, the licensee is expected to
earn a reasonable return on its capital base based on the methodology prescribed in the
Sixth Schedule to the Electricity Supply Act, 1948. The cost of power purchase covers not
only the cost of power required to meet the need of the end users but also it covers the
cost of energy lost on account of technical and commercial losses of the distribution
system. The licensee is also required to meet the cost of capital of new investments
needed to improve system reliability and quality of power supply.
|
3.11.2
|
The licensee earns its only source
of revenue through retail supply tariff from the consumers of electricity within its area
of license. A summary of proposals of its revenue requirement and the expected revenue at
the present tariff for the year 2001-02 as proposed by the licensee is presented in the
table below. Table : 3 : 3
(Rs. in crore)
Power Purchase Cost |
310.84 |
Distribution cost |
204.86 |
Contribution to contingency reserve |
1.13 |
Total revenue requirement |
516.83 |
(-) Misc. Receipts |
2.60 |
Reasonable return |
1.55 |
Net revenue requirement |
515.55 |
Net revenue receipt from sale of power to
DISTCOs |
303.84 |
Deficit |
211.71 |
|
3.11.3
|
NESCO in its application of 2001-02
has stated that during its operation for the last two and half years the tariff awards of
OERC on 30 December 1999 and 19 January 2001 were found to be notional as certain
concessions allowed to industrial consumers by the Commission had completely nullified the
effect of RST revision. Similarly, the increase granted in the RST order of 19.01.2001 was
found to be inadequate to meet the actual and anticipated expenses of the licensee and the
Commission disallowed certain legitimate and reasonable expenses and under-estimated the
power purchase expenses. NESCO continued to incur losses from 1st April 1999 on
account of these factors. This trend continued for the years 2000-01 and 2001-02.
|
3.11.4
|
NESCO in its application has stated
that in the last two tariff orders, the Commission has adopted a method of rationalization
of tariff for creating a consumer friendly environment allowing concessions which had
serious financial implications coupled with heavy increase in BST which totally nullified
the effect of tariff revision.
|
3.11.5
|
NESCO has stated that in its last
tariff order of January 2001, a sale rate of 269.98 paise per KWH was determined by the
Commission which was lower than the average cost of supply of 281 paise per unit leading
to a revenue gap which is likely to further go up if the supplementary special agreement
with a reduced per unit rate is approved for the EOUs. Finally, NESCO states that even if
the company was able to achieve 100% collection efficiency, the increase in revenue
granted vide RST order dt.19.01.2001 currently in force for FY 2001-02 will be far less
than the increase in cost of power due to upward revision of BST. The last increase in BST
and the resultant increase in RST tariff led to closure of power intensive ferro-chrome
units thereby severely affecting the financial position of NESCO.
|
3.12
|
Distribution loss NESCO
in its application has stated that it has set a target to reduce losses in the LT sector
to achieve an overall estimated loss of 47% in the FY 2001-02 in spite of heavy reduction
in HT and EHT consumption. The pilot project for loss study as directed by the Commission
has been taken up and the report has also been submitted to the Commission. For the FY
2002-03, it propose to double its efforts and outlay on metering and monitoring of
consumers targeting a reduction of 3% loss to achieve a distribution system loss of 44%
during the year. Accordingly, it has requested OERC to accept the distribution loss of 44%
while computing its revenue requirement for the year 2002-03. |
3.13
|
Tariff Revision Proposal
|
3.13.1
|
NESCO has proposed an overall tariff
rise of 32% to compensate for the shortfall in revenue requirement for the year 2001-02.
It has also requested to carry forward a substantial portion of losses incurred by it for
recovery in future tariff and has requested OERC to give a relief in BST considering
NESCOs present financial condition.
|
3.13.2
|
NESCO proposes to move towards a
cost based tariff structure for which a minimum increase of 30 paise per unit has been
suggested in EHT/HT category and a rise of 60-130 paise per unit has been proposed for
different consumers in LT category. No change has been proposed in tariff for Kutir Jyoti
consumers. It also proposes modification to the monthly minimum fixed charges for various
categories of consumers.
|
3.14
|
Cross-subsidy
|
3.14.1
|
NESCO submits that if the
Commission deems it necessary for phasing out cross-subsidy at a faster pace, the
Commission can consider the proposal for State Government subsidy to compensate the
utility for the financial implications of the proposed measure. It has stated that on
account of limited capacity of EHT industry for cross-subsiding LT sector, the need for
state subsidy for LT sector is all the more necessary. Thus, the State Government has a
significant role to play in balancing the varying interest of different classes of
consumers. It has requested OERC to come out with appropriate direction in this regard.
|
3.14.2
|
It has proposed no change in the
special tariff for consumers with load of 100 MVA and above and a guaranteed monthly load
factor of 80%.
|
3.15
|
Special tariff for consumers with
load of 25 MVA and above and having high load factor
|
3.15.1
|
NESCO has proposed to offer a
special single part tariff for industrial consumers having contract demand of 25 MVA and
above subject to achieving load factor of at least 70% in the relevant month. For load factor of 70% or above but less than 80%: Rs.2.40 per KWh
For load factor of 80% or above but less than 90%: Rs.2.30 per KWh
For load factor of 90% or above : Rs.2.20 per KWh |
3.15.2
|
The above rate would be a
consolidated rate and no separate power factor incentive or rebate for payment would be
available to these consumers.
|
3.15.3
|
The above special rates are based on
the present BST and upon any revision of the same the above special rates would be
revised.
|
3.16
|
NESCOs prayer for
2001-02
-
Approval of the proposed retail tariff and charges
-
Confirmation of the revenue requirement
-
Confirmation of expected revenue from the proposed tariff
-
Permission to carry forward the gap between expected revenue and the revenue requirement
in 2001-02 and the unabsorbed past loss for adjustment in future years.
|
3.17
|
Financial year 2002-03 The
revenue requirement and the expected revenue for the year 2002-03 as projected by NESCO is
given in the table below :
Table : 4 : 4
(Rs. in Crore)
Power Purchase Cost |
321.52 |
Distribution cost |
194.96 |
Contribution to contingency reserve |
1.36 |
Total revenue requirement |
517.84 |
(-) Misc. Receipts |
2.60 |
Reasonable return |
1.72 |
Net revenue requirement |
516.96 |
Net revenue receipt from sale of power to
DISTCOs |
339.91 |
Deficit |
177.05 |
|
3.18
|
NESCOs prayer for
2002-03
Confirmation of revenue requirement for NESCO
Permission for submission of an amended revenue requirement statement (if required)
along with a tariff revision proposal after the tariff order for BST and RST order for
2001-02 is released by OERC.
|