6.5
|
Reasonable Return With
regard to reasonable return it is clarified that the same has to be calculated on the
basis of the capital base arrived at in accordance with the provision of Sixth Schedule to
the Supply Act, 1948. |
6.6
|
Treatment of Working Capital
|
6.6.1
|
The Commission believes that the
companies must commit themselves to a higher level of efficiency, bring loan to meet the
working capital needs so that the transmission utility and the generators are not starved
of funds. There is a gap between the revenue billed and the revenue realised due to
inefficiency on the part of the licensees for failing to take appropriate and expeditious
steps like disconnection in time or initiation of civil suits to realise the arrear dues.
Domestic, irrigation and agricultural consumers are not required to pay any DPS for delay
in payment, whereas small and medium industries and other categories only pay one time
DPS. This is a disincentive for revenue collection especially when the licensees are not
capable of realising the dues after the due date of payment is over. The Commission also
may at appropriate time consider for levy of DPS for those consumers who are at present
not covered under DPS for delay in payment.
|
6.6.2
|
The distribution companies have
failed to bring required working capital to ensure cash balance in the system to meet all
expenses. The licensee can get rebate on prompt payment from GRIDCO @2% per month, which
will reduce its power purchase liability. In a sense if the licensee arranges working
capital from the commercial and financial institutions they can save not only the DPS but
will earn a rebate from the GRIDCO that will compensate the interest on working capital
and may accrue some revenue in the form of rebate. The Commission also may at appropriate
time consider for levy of DPS for those consumers who fail to pay the bills during the
stipulated period.
|
6.7
|
T&D loss
|
6.7.1
|
The next issue is determination of
the total cost of distribution and retail supply. The supply business requires purchase of
power by the DISTCOs from the transmission company (GRIDCO) for supply to consumers. The
energy received at grid sub-stations at 33 kV by the DISTCOs and supplied to the end-use
consumers at different voltage levels entails both technical and commercial losses. The
Commission hitherto have been following the concept of determination of power procurement
after applying a normative loss level to the total power proposed to be sold by the
licensee, irrespective of the quantum of actual power purchase by DISTCOs from GRIDCO.
This quantum of power purchase is metered in each grid sub-station and is reflected in the
various data recorded in the energy billing centre (EBC) of GRIDCO and also in the BST
bill of GRIDCO raised on DISTCOs.
|
6.7.2
|
The World Bank Staff Appraisal
Report of April 1996 projected different levels of transmission and distribution loss for
the year 1996-97 to the FY 2002-03 based on the studies made by a group of reputed
consultants. The Commission while approving the tariff application in the year 1997-98
took cognizance of these projected loss figures. While adopting a loss level of 35% for
the year 1997-98, the Commission went by the estimate of 34.8% made in the SAR as against
the claim of 47% made by GRIDCO for that year. The projections made in the
SAR, the level
of T&D loss as established by the audit report of GRIDCO gives a wide disparity in the
projections and actual performance as can be revealed from the table below. Table : 6
As per SAR of 1996
|
FY 97 |
FY 98 |
FY 99 |
FY 00 |
FY 01 |
FY 02 |
FY 03 |
Energy available for sale (MU) |
9785 |
10902 |
12726 |
13902 |
14809 |
15560 |
16342 |
T&D losses (%) |
39.5 |
34.8 |
29.2 |
24.3 |
22.7 |
21.7 |
20.6 |
Electricity sale (MU) |
5924 |
7103 |
9004 |
10528 |
11442 |
12187 |
12976 |
Table : 7
Actual performance
|
FY 97 |
FY 98 |
FY 99 |
FY 00 |
Energy available (MU) |
9651
Audited |
10324
Audited |
10571
BST order 2000-01 |
10131
BST order 2000-01 |
T&D losses (%) |
49.47 |
49.24 |
48.60 |
45.36 |
Electricity sale (MU) |
4876 |
5240 |
5433
RST filing 00-01 |
5536
Tax audit RST filing of CESCO 00-01 |
|
6.7.3
|
The members the Commission Advisory
Committee specifically discussed the issues of high percentage of T&D loss,
Distribution loss, poor performance of Distcos, subsidy, cross-subsidy. Majority of the
members suggested that the recomendation of the Kanungo committee should be kept in view
while finalising the tariff and revenue requirement of DISTCOs as neither the Government
of Orissa filed any objection nor depute any representative to appear in the hearing.
Members also advocated in favour of uniform retail tariff for the whole State. Some of the
Members raised issues specific to the interest groups they represent. But there was near
unanimity with regard to the certain issues. It was felt that T&D loss was still high
and while fixing the target level of loss, the Commission should not go back to the level
already set. Rather the target level of loss be set at still lower. It was also felt that
installation of meters and consumer services were far from satisfactory. Most of the
members opined that there should be thorough scrutiny on the input cost of the licensees,
while Some suggested that depreciation should not be charged on the assets those have
already outlived. The Chief Electrical Engineer, S.E. Railways raised certain vital issues
to be tackled while passing this tariff order to give benefit to the Railways.
|
6.7.4
|
The objectors in general were of
the opinion that the adoption of a uniform loss figure for the four distribution companies
with a different load mix was hiding the inefficiency of the companies with higher
components of HT and EHT load. EHT component of load makes a big difference to the overall
loss figure for the company as loss in EHT category is practically negligible. The overage
loss as a percentage of the total power procurement from the GRIDCO by DISTCOs as well as
the direct sale figures at EHT as projected by the four DISTCOs are given in the table for
the FY 2001-02.(RR02-03 filing of DISTCOS). Table : 8
|
NESCO |
WESCO |
SOUTHCO |
CESCO |
TOTAL |
Input for the DISTCOs (MU) |
2208.4 |
2920.2 |
1541.3 |
4024.6 |
10694.45 |
Sale at EHT (MU) |
243.72 |
583.5 |
122.27 |
266.02 |
1215.51 |
Proposed Distribution Loss (%) |
47.4 |
45.1 |
41 |
45 |
45 |
|
6.7.5
|
Some of the objectors have pointed
out that the distribution loss is being computed after taking into account even the zero
loss EHT energy input into the system to show a reduced level of loss. The total power
sale to a DISTCO is arrived at the Energy Billing Centre of GRIDCO by integrating the EHT
drawal at 132/220 kV and bulk power drawal at 33 kV in any grid sub-station. Therefore,
sale at EHT can be taken out from the total power purchase figures to determine the energy
input to various DISTCOs for supply to HT and LT consumers. If the EHT sale projected by
the four DISTCOs are taken out from the total sale projected by these companies then the
distribution loss as the percentage loss of HT and LT input works out to 53.3% for NESCO,
56.3% for WESCO, 44.1% for SOUTHCO and 48.2% for CESCO with an overall loss figure of
50.6% for the State as a whole under HT & LT category.
|
6.7.6
|
As we will be determining the
energy input into the DISTCOs system based on the billing figures of GRIDCO for the FY
2001-02, it will be appropriate to determine the loss as a percentage of HT and LT input
after deducting the direct sale at EHT to show a comparative picture of performance of the
four DISTCOs and also plan for bringing down the distribution loss at the HT & LT
level, which will ultimately bring down the overall distribution loss in a DISTCO.
|
6.7.7
|
Identical comparison can be done for
the FY 2002-03 by determining distribution loss as a percentage of HT and LT input.
|
6.7.8
|
The Commission in the tariff order
dtd.19.01.2001 had observed that the task of fixing a level of loss in the absence of
verifiable and reliable data has led it to apply a value judgement that should be fair,
reasonable and financially sound. Any arbitrariness on the part of the Commission will
either affect the financial viability of the licensee or sustain undue burden on the
consumers.
|
6.7.9
|
The Commission had also observed in
the last tariff order that the high T&D loss is not an isolated phenomena in Orissa.
Higher level of loss figures are being gradually disclosed in all most all the reforming
states in the country. The Commission was also of the view that the benchmark of T&D
loss at 35% was as a measure of performance perceived to be unrealistic and unacceptable
by GRIDCO and the DISTCOs. The World Bank on whose SAR Commission relied in fixing an
overall loss level of 35% in FY 1997-98 subsequently came out in its midterm review report
dtd.31.10.1998 that it underestimated the actual loss level. The World Bank states
"Consultation with the Commission on the issue of recognizing the actual system loss
levels and pass through of prior years financial losses, given that we all so
severely underestimated GRIDCOs system losses in 1996 and set unachievable
performance targets".
|
6.7.10
|
Therefore DISTCOs all along
complained about to unrealistic loss level of 35% adopted by the Commission while adopting
a loss level of 34% for the FY 2000-01 including the losses at EHT transmission system of
3.7%, the Commission had directed the DISTCOs during the course of the hearing to carry
out pilot studies within a period of six months from April, 2001 to September, 2001 and
submit the same to the Commission for its appraisal while determining the target level of
loss reduction from year to year. The Commission is constrained to place on record the
utter failure of licensees to address this most important and crucial issue which was
being raked up by them time and again. DISTCOs have not initiated any concerned and
vigorous effort to fix meters in feeders, LV side of transformer and consumers served by
the feeder to ascertain the actual level of loss.
|
6.7.11
|
Due to insistence by Commission the
DISTCOs started determination of loss on a selected feeder. It was a much delayed exercise
by all the licensees. Also Commissions effort to engage outside consultants to
oversee the pilot loss study could not take off due to the financial problem of the
licensees. Only WESCO initiated a study by engaging an outside agency.
|
6.7.12
|
However, the Commission with the
assistance of the Department for International Development (DFID) has conducted pilot
study in one 11 kV feeder for WESCO, NESCO and SOUTHCO and two feeders of CESCO by
appointing its own consultants. The report of this pilot study demonstrates that there is
ample scope and opportunity for quick reduction of loss by the DISTCOs.
|
6.7.13
|
The distribution companies while
submitting the business plan for a period of 5 years to the Committee of independent
expert in the month of October, 2001 have supplied the following distribution loss figures
for the year 2001-02 to 2004-05:- Table-9
Figure of distribution loss projected by DISTCOs before
the Committee of Independent Experts
Name of the company |
FY 01-02 |
FY 02-03 |
FY 03-04 |
FY 04-05 |
CESCO |
40.94% |
39.35% |
37.57% |
36.08% |
NESCO |
46.98% |
40.77% |
36.85% |
34.12% |
WESCO |
41.08% |
39% |
36.93% |
34.89% |
SOUTHCO |
40.89% |
39.21% |
36.01% |
33.14% |
ALL ORISSA |
42.21% |
39.56% |
37.00% |
34.87% |
|
6.7.14
|
This, however, excludes the
transmission loss of 4.65%, projected by GRIDCO from 2001-02 to 2005-06.
|
6.7.15
|
The committee, however, accepted a
distribution level loss of 42.21% for the base year of FY 2001-02 after hearing the
DISTCOs and suggested reduction of distribution loss by 5% each year from FY 2002-03 to
reach a level of 22.21% in the year 2005-06. Similarly, the committee had also approved a
reduction of transmission loss at a rate 0.3% each year from FY 2002-03 till the losses
reach 3.7% by 2005-06. This is projected in the table below. Table
: 10
Loss figures approved by the Committee of Independent Experts
|
FY 01-02 |
FY 02-03 |
FY 03-04 |
FY 04-05 |
FY 05-06 |
Distribution loss |
42.21% |
37.21% |
32.21% |
27.21% |
22.21% |
Tranmission loss |
4.7% |
4.4% |
4.1% |
3.8% |
3.7% |
|
6.7.16
|
As explained in para 6.7.6,
computation of loss after deducting the zero loss EHT energy from year to year is given
below. Table : 11
Computation of loss as a percentage of HT & LT input based on the Business Plan
submitted by DISTCOs to the Committee of Independent Experts
|
FY 01-02 |
FY 02-03 |
FY 03-04 |
FY 04-05 |
FY 05-06 |
Loss as a %age HT & LT input |
49.67% |
45.01% |
39.9% |
34.25% |
28.39% |
|
6.7.17
|
The committee of independent
experts appointed by the Government of Orissa to review the power sector reform in their
report have suggested reduction of distribution loss at the rate of 5% per annum. The
pilot study conducted by the Commission brings out very clearly that the scope of
reduction of distribution loss is enormous provided the companies take effective steps
such as technical, financial and managerial decisions for reduction of distribution loss.
Any number of alibis expressing inability for not reducing the distribution loss are not
acceptable to the Commission. Besides higher level of loss found out on the basis of pilot
study is purely indicative as the number of feeders selected were very few compared to the
existing number of feeders. Pilot study results cannot be taken as basis of loss levels
existing in different DISTCOs, as study on one feeder out of hundreds of feeders in the
company with varied load mix, concentration of loads, length and size of feeders cannot be
a representative one. But this study brought to the fore very interesting facts like
direct tapping of 11 kV feeder by industrial consumers, by-passing of meter CTs. It so
happened in some areas where pilot study was being taken up, the consumers locked their
houses and went away forbidding the utility staff and Commission consultant to check the
status of the meter. Pole scheduling in the study area revealed unauthorized abstraction
of energy by the illegal consumers, consuming energy far more in excess of what was shown
in the consumer ledger of the DISTCOs.
|
6.7.18
|
In the 2001-02 tariff filing, WESCO
had reported a loss level of 38% for that year. But while submitting the revenue
requirement application FY 2002-03, WESCO have reported distribution loss for the year
2001-02 as 45%. This kind of irresponsible reporting for a particular year has been made
within an interval of 3 months. It implies that the DISTCOs have demonstrated a very
casual attitude in projecting the figure to the Commission for the purpose of
determination of tariff or revenue requirement. The case of other companies are also not
different.
|
6.7.19
|
The Commission accepts the
distribution loss figure as approved by the Kanungo Committee as 42.21% for the FY 2001-02
which is treated as the base year. This figure of 42.21% represents the overall average
distribution loss for the entire State but varies across the four distribution companies.
The variation in loss figures across the DISTCOs are exhibited in Table-12. The Commission
also adopts the recommendation of the committee for reduction of distribution loss at
least at the rate of 5% per annum from 2001-02 to 2002-03. The Commission therefore
directs that for the purpose of determination tariff and the revenue requirement the rate
of loss reduction will be calculated at the rate of 5% (overall average for the state)
starting from the FY 2001-02 and 2002-03. Accordingly, the following loss figures are
approved for the aforesaid purpose for the year 2001-02 and 2002-03. While formulating the
multi-year tariff proposed to be effective from 01.04.2003, this aspect of loss reduction
along with collection efficiency etc will be decided for subsequent years. Table : 12
PURCHASE & SALES BY
DISTCOs BASED ON 10 MONTHS ACTUAL |
|
FY 2001-02 |
Expected/Projected
for FY 2002-03 |
|
Purchase (MU) |
Loss(%) |
Sale(MU) |
Purchase (MU) |
Loss(%) |
Sale(MU) |
CESCO
|
4167.77 |
40.94% |
2461.485 |
4321.00 |
35.94 |
2768.03 |
NESCO
|
2253.62 |
46.98% |
1194.8693 |
2291.20 |
41.98 |
1329.36 |
WESCO
|
2980.64
|
41.08% |
1756.1931 |
3066.54 |
36.08 |
1960.13 |
SOUTHCO
|
1525.07 |
40.89% |
901.46888 |
1682.39 |
35.89 |
1078.58 |
TOTAL
|
10927.10 |
42.21% |
6314.02 |
11361.13 |
37.21 |
7136.10 |
|
6.7.20
|
Commission wants to make it
expressly clear that there is no shortcut way unless a systematic drive is made to reduce
the distribution loss. This should necessarily include metering of 11 kV feeders, metering
at LV side of transformers, pole scheduling, verification if deemed necessary of consumer
connected loads, rectification or replacement of consumer meters so that each feeder is
converted to a Profit Centre as has been very aptly stated by the Ministry of
Power, GoI, which is allotting large sum of funds to meet cost of metering etc. to achieve
the goal in a time bound manner, which will be available through State Govts. to utilities
and SEBs under APDRP programme.
|
6.7.21
|
There are 846 Nos. of 33/11 kV
feeders in the State under the four DISTCOs. There are about 900 field sections in the
DISTCOs. This means that there may be 1 to 2 Nos. of 11 kV feeders under each section and
1 No. of 33 kV feeder and 9 Nos. of 33/11 kV transformers and at least 30 Nos. of
distribution transformers in each feeder. Once members and other supporting staff
including MRT personnel are made available, it would be possible to complete within one
year for monitoring of all feeders along with complete pole scheduling leading to
identification and regularisation of unauthorised connection. Progressive achievements
will bring substantial in reduction of loss in feeders.
|
6.7.22
|
Commission, among other things shall
attach highest priority on these aspects and would expect the licensee to aggressively
start taking up related activities. Commission would, on its part approach DFID to provide
support to temporarily hire services of technical personnel by the Commission to oversee
the progress made in this regard by the licensee on a day to day basis.
|
6.7.23
|
Although the Commission in
deference to the spirit of OER Act, 1995 would have liked for a hands-off regulation while
dealing with DISTCOs. But it finds to its dismay that utilities have taken advantage of
this liberal gesture and have done precious little to address this single major factor of
loss reduction which constitutes a menace to the viability of the power sector. Therefore,
Commission would closely associate itself in monitoring the activities of DISTCOs in this
regard.
|
6.7.24
|
As indicated in para 6.7.16 the loss
as a percentage of HT & LT input for the year 2005-06 approved by the Kanungo
Committee should be targeted at 28.39% to be attained by all the DISTCOs.
|