| 6.5 | Reasonable Return With regard to
    reasonable return it is clarified that the same has to be calculated on the basis of the
    capital base arrived at in accordance with the provision of Sixth Schedule to the Supply
    Act, 1948. | 
  
    | 6.6 | Treatment of Working Capital | 
  
    | 6.6.1 | The Commission believes that the companies must commit
    themselves to a higher level of efficiency, bring loan to meet the working capital needs
    so that the transmission utility and the generators are not starved of funds. There is a
    gap between the revenue billed and the revenue realised due to inefficiency on the part of
    the licensees for failing to take appropriate and expeditious steps like disconnection in
    time or initiation of civil suits to realise the arrear dues. Domestic, irrigation and
    agricultural consumers are not required to pay any DPS for delay in payment, whereas small
    and medium industries and other categories only pay one time DPS. This is a disincentive
    for revenue collection especially when the licensees are not capable of realising the dues
    after the due date of payment is over. The Commission also may at appropriate time
    consider for levy of DPS for those consumers who are at present not covered under DPS for
    delay in payment. | 
  
    | 6.6.2 | The distribution companies have failed to bring required
    working capital to ensure cash balance in the system to meet all expenses. The licensee
    can get rebate on prompt payment from GRIDCO @2% per month, which will reduce its power
    purchase liability. In a sense if the licensee arranges working capital from the
    commercial and financial institutions they can save not only the DPS but will earn a
    rebate from the GRIDCO that will compensate the interest on working capital and may accrue
    some revenue in the form of rebate. | 
  
    | 6.7 | T&D loss | 
  
    | 6.7.1 | The next issue is determination of the total cost of
    distribution and retail supply. The supply business requires purchase of power by the
    DISTCOs from the transmission company (GRIDCO) for supply to consumers. The energy
    received at grid sub-stations at 33 kV by the DISTCOs and supplied to the end-use
    consumers at different voltage levels entails both technical and commercial losses. The
    Commission hitherto have been following the concept of determination of power procurement
    after applying a normative loss level to the total power proposed to be sold by the
    licensee, irrespective of the quantum of actual power purchase by DISTCOs from GRIDCO.
    This quantum of power purchase is metered in each grid sub-station and is reflected in the
    various data recorded in the energy billing centre (EBC) of GRIDCO and also in the BST
    bill of GRIDCO raised on DISTCOs. | 
  
    | 6.7.2 | The World Bank Staff Appraisal Report of April 1996 projected
    different levels of transmission and distribution loss for the year 1996-97 to the FY
    2002-03 based on the studies made by a group of reputed consultants. The Commission while
    approving the tariff application in the year 1997-98 took cognizance of these projected
    loss figures. While adopting a loss level of 35% for the year 1997-98, the Commission went
    by the estimate of 34.8% made in the SAR as against the claim of 47% made by GRIDCO for
    that year. The projections made in the SAR, the level of T&D loss as established by
    the audit report of GRIDCO gives a wide disparity in the projections and actual
    performance as can be revealed from the table below. Table : 6As per SAR of 1996
 
      
        |   | FY 97 | FY 98 | FY 99 | FY 00 | FY 01 | FY 02 | FY 03 |  
        | Energy available for sale (MU) | 9785 | 10902 | 12726 | 13902 | 14809 | 15560 | 16342 |  
        | T&D losses (%) | 39.5 | 34.8 | 29.2 | 24.3 | 22.7 | 21.7 | 20.6 |  
        | Electricity sale (MU) | 5924 | 7103 | 9004 | 10528 | 11442 | 12187 | 12976 |  Table : 7Actual performance
 
      
        |    | FY 97 | FY 98 | FY 99 | FY 00 |  
        | Energy available (MU) | 9651Audited
 | 10324Audited
 | 10571BST order 2000-01
 | 10131BST order 2000-01
 |  
        | T&D losses (%) | 49.47 | 49.24 | 48.60 | 45.36 |  
        | Electricity sale (MU) | 4876 | 5240 | 5433RST filing 00-01
 | 5536Tax audit RST filing of CESCO 00-01
 |  | 
  
    | 6.7.3 | The members the Commission Advisory Committee specifically
    discussed the issues of high percentage of T&D loss, Distribution loss, poor
    performance of Distcos, subsidy, cross-subsidy. Majority of the members suggested that the
    recommendation of the Kanungo committee should be kept in view while finalising the tariff
    and revenue requirement of DISTCOs as neither the Government of Orissa filed any objection
    nor depute any representative to appear in the hearing. Members also advocated in favour
    of uniform retail tariff for the whole State. Some of the Members raised issues specific
    to the interest groups they represent. But there was near unanimity with regard to the
    certain issues. It was felt that T&D loss was still high and while fixing the target
    level of loss, the Commission should not go back to the level already set. Rather the
    target level of loss be set at still lower. It was also felt that installation of meters
    and consumer services were far from satisfactory. Most of the members opined that there
    should be thorough scrutiny on the input cost of the licensees, while Some suggested that
    depreciation should not be charged on the assets those have already outlived. The Chief
    Electrical Engineer, S.E. Railways raised certain vital issues to be tackled while passing
    this tariff order to give benefit to the Railways. | 
  
    | 6.7.4 | The objectors in general were of the opinion that the
    adoption of a uniform loss figure for the four distribution companies with a different
    load mix was hiding the inefficiency of the companies with higher components of HT and EHT
    load. EHT component of load makes a big difference to the overall loss figure for the
    company as loss in EHT category is practically negligible. The overage loss as a
    percentage of the total power procurement from the GRIDCO by DISTCOs as well as the direct
    sale figures at EHT as projected by the four DISTCOs are given in the table for the FY
    2001-02.(RR02-03 filing of DISTCOS). Table : 8 
      
        |    | NESCO | WESCO | SOUTHCO | CESCO | TOTAL |  
        | Input for the DISTCOs (MU) | 2208.4 | 2920.2 | 1541.3 | 4024.6 | 10694.45 |  
        | Sale at EHT (MU) | 243.72 | 583.5 | 122.27 | 266.02 | 1215.51 |  
        | Proposed Distribution Loss (%) | 47.4 | 45.1 | 41 | 45 | 45 |  | 
  
    | 6.7.5 | Some of the objectors have pointed out that the distribution
    loss is being computed after taking into account even the zero loss EHT energy input into
    the system to show a reduced level of loss. The total power sale to a DISTCO is arrived at
    the Energy Billing Centre of GRIDCO by integrating the EHT drawal at 132/220 kV and bulk
    power drawal at 33 kV in any grid sub-station. Therefore, sale at EHT can be taken out
    from the total power purchase figures to determine the energy input to various DISTCOs for
    supply to HT and LT consumers. If the EHT sale projected by the four DISTCOs are taken out
    from the total sale projected by these companies then the distribution loss as the
    percentage loss of HT and LT input works out to 53.3% for NESCO, 56.3% for WESCO, 44.1%
    for SOUTHCO and 48.2% for CESCO with an overall loss figure of 50.6% for the State as a
    whole under HT & LT category. | 
  
    | 6.7.6  | As we will be determining the energy input into the DISTCOs
    system based on the billing figures of GRIDCO for the FY 2001-02, it will be appropriate
    to determine the loss as a percentage of HT and LT input after deducting the direct sale
    at EHT to show a comparative picture of performance of the four DISTCOs and also plan for
    bringing down the distribution loss at the HT & LT level, which will ultimately bring
    down the overall distribution loss in a DISTCO. | 
  
    | 6.7.7 | Identical comparison can be done for the FY 2002-03 by
    determining distribution loss as a percentage of HT and LT input. | 
  
    | 6.7.8 | The Commission in the tariff order dtd.19.01.2001 had observed
    that the task of fixing a level of loss in the absence of verifiable and reliable data has
    led it to apply a value judgement that should be fair, reasonable and financially sound.
    Any arbitrariness on the part of the Commission will either affect the financial viability
    of the licensee or sustain undue burden on the consumers. | 
  
    | 6.7.9 | The Commission had also observed in the last tariff order
    that the high T&D loss is not an isolated phenomena in Orissa. Higher level of loss
    figures are being gradually disclosed in all most all the reforming states in the country.
    The Commission was also of the view that the benchmark of T&D loss at 35% was as a
    measure of performance perceived to be unrealistic and unacceptable by GRIDCO and the
    DISTCOs. The World Bank on whose SAR Commission relied in fixing an overall loss level of
    35% in FY 1997-98 subsequently came out in its midterm review report dtd.31.10.1998 that
    it underestimated the actual loss level. The World Bank states "Consultation with the
    Commission on the issue of recognizing the actual system loss levels and pass through of
    prior years' financial losses, given that we all so severely underestimated GRIDCO's
    system losses in 1996 and set unachievable performance targets". | 
  
    | 6.7.10 | Therefore DISTCOs all along complained about to unrealistic
    loss level of 35% adopted by the Commission while adopting a loss level of 34% for the FY
    2000-01 including the losses at EHT transmission system of 3.7%, the Commission had
    directed the DISTCOs during the course of the hearing to carry out pilot studies within a
    period of six months from April, 2001 to September, 2001 and submit the same to the
    Commission for its appraisal while determining the target level of loss reduction from
    year to year. The Commission is constrained to place on record the utter failure of
    licensees to address this most important and crucial issue which was being raked up by
    them time and again. DISTCOs have not initiated any concerned and vigorous effort to fix
    meters in feeders, LV side of transformer and consumers served by the feeder to ascertain
    the actual level of loss. | 
  
    | 6.7.11 | Due to insistence by Commission the DISTCOs started
    determination of loss on a selected feeder. It was a much delayed exercise by all the
    licensees. Also Commission's effort to engage outside consultants to oversee the pilot
    loss study could not take off due to the financial problem of the licensees. Only WESCO
    initiated a study by engaging an outside agency. | 
  
    | 6.7.12 | However, the Commission with the assistance of the Department
    for International Development (DFID) has conducted pilot study in one 11 kV feeder for
    WESCO, NESCO and SOUTHCO and two feeders of CESCO by appointing its own consultants. The
    report of this pilot study demonstrates that there is ample scope and opportunity for
    quick reduction of loss by the DISTCOs. | 
  
    | 6.7.13 | The distribution companies while submitting the business plan
    for a period of 5 years to the Committee of independent expert in the month of October,
    2001 have supplied the following distribution loss figures for the year 2001-02 to
    2004-05:- Table-9Figure of distribution loss projected by DISTCOs before
 the Committee of Independent Expert
 
      
        | Name of the company | FY 01-02 | FY 02-03 | FY 03-04 | FY 04-05 |  
        | CESCO | 40.94% | 39.35% | 37.57% | 36.08% |  
        | NESCO | 46.98% | 40.77% | 36.85% | 34.12% |  
        | WESCO | 41.08% | 39% | 36.93% | 34.89% |  
        | SOUTHCO | 40.89% | 39.21% | 36.01% | 33.14% |  
        | ALL ORISSA | 42.21% | 39.56% | 37.00% | 34.87% |  | 
  
    | 6.7.14 | This, however, excludes the transmission loss of 4.65%,
    projected by GRIDCO from 2001-02 to 2005-06. | 
  
    | 6.7.15 | The committee, however, accepted a distribution level loss of
    42.21% for the base year of FY 2001-02 after hearing the DISTCOs and suggested reduction
    of distribution loss by 5% each year from FY 2002-03 to reach a level of 22.21% in the
    year 2005-06. Similarly, the committee had also approved a reduction of transmission loss
    at a rate 0.3% each year from FY 2002-03 till the losses reach 3.7% by 2005-06. This is
    projected in the table below. Table : 10Loss figures approved by the Committee of Independent Experts
 
      
        |    | FY 01-02 | FY 02-03 | FY 03-04 | FY 04-05 | FY 05-06 |  
        | Distribution loss | 42.21% | 37.21% | 32.21% | 27.21% | 22.21% |  
        | Transmission loss | 4.7% | 4.4% | 4.1% | 3.8% | 3.7% |  | 
  
    | 6.7.16 | As explained in para 6.7.6, computation of loss after
    deducting the zero loss EHT energy from year to year is given below. Table
    : 11Computation of loss as a percentage of HT & LT input based on the Business Plan
    submitted by DISTCOs to the Committee of Independent Experts
 
      
        |   | FY 01-02 | FY 02-03 | FY 03-04 | FY 04-05 | FY 05-06 |  
        | Loss as a %age HT & LT input | 49.67% | 45.01% | 39.9% | 34.25% | 28.39% |  | 
  
    | 6.7.17 | The committee of independent experts appointed by the
    Government of Orissa to review the power sector reform in their report have suggested
    reduction of distribution loss at the rate of 5% per annum. The pilot study conducted by
    the Commission brings out very clearly that the scope of reduction of distribution loss is
    enormous provided the companies take effective steps such as technical, financial and
    managerial decisions for reduction of distribution loss. Any number of alibis expressing
    inability for not reducing the distribution loss are not acceptable to the Commission.
    Besides higher level of loss found out on the basis of pilot study is purely indicative as
    the number of feeders selected were very few compared to the existing number of feeders.
    Pilot study results cannot be taken as basis of loss levels existing in different DISTCOs,
    as study on one feeder out of hundreds of feeders in the company with varied load mix,
    concentration of loads, length and size of feeders cannot be a representative one. But
    this study brought to the fore very interesting facts like direct tapping of 11 kV feeder
    by industrial consumers, by-passing of meter CTs. It so happened in some areas where pilot
    study was being taken up, the consumers locked their houses and went away forbidding the
    utility staff and Commission consultant to check the status of the meter. Pole scheduling
    in the study area revealed unauthorized abstraction of energy by the illegal consumers,
    consuming energy far more in excess of what was shown in the consumer ledger of the
    DISTCOs. | 
  
    | 6.7.18 | In the 2001-02 tariff filing, WESCO had reported a loss level
    of 38% for that year. But while submitting the revenue requirement application FY 2002-03,
    WESCO have reported distribution loss for the year 2001-02 as 45%. This kind of
    irresponsible reporting for a particular year has been made within an interval of 3
    months. It implies that the DISTCOs have demonstrated a very casual attitude in projecting
    the figure to the Commission for the purpose of determination of tariff or revenue
    requirement. The case of other companies are also not different. | 
  
    | 6.7.19 | The Commission accepts the distribution loss figure as
    approved by the Kanungo Committee as 42.21% for the FY 2001-02 which is treated as the
    base year. This figure of 42.21% represents the overall average distribution loss for the
    entire State but varies across the four distribution companies. The variation in loss
    figures across the DISTCOs are exhibited in Table-12. The Commission also adopts the
    recommendation of the committee for reduction of distribution loss at least at the rate of
    5% per annum from 2001-02 to 2002-03. The Commission therefore directs that for the
    purpose of determination tariff and the revenue requirement the rate of loss reduction
    will be calculated at the rate of 5% (overall average for the state) starting from the FY
    2001-02 and 2002-03. Accordingly, the following loss figures are approved for the
    aforesaid purpose for the year 2001-02 and 2002-03. While formulating the multi-year
    tariff proposed to be effective from 01.04.2003, this aspect of loss reduction along with
    collection efficiency etc will be decided for subsequent years. Table
    : 12 
      
        | PURCHASE & SALES BY
        DISTCOs BASED ON 10 MONTHS ACTUAL |  
        |    | FY 2001-02 | Expected/Projected
        for FY 2002-03 |  
        |     | Purchase(MU) | Loss(%) | Sale(MU) | Purchase(MU) | Loss(%) | Sale(MU) |  
        | CESCO | 4167.77 | 40.94% | 2461.485 | 4321.00 | 35.94 | 2768.03 |  
        | NESCO | 2253.62 | 46.98% | 1194.8693 | 2291.20 | 41.98 | 1329.36 |  
        | WESCO | 2980.64 | 41.08% | 1756.1931 | 3066.54 | 36.08 | 1960.13 |  
        | SOUTHCO | 1525.07 | 40.89% | 901.46888 | 1682.39 | 35.89 | 1078.58 |  
        | TOTAL | 10927.10 | 42.21% | 6314.02 | 11361.13 | 37.21 | 7136.10 |  | 
  
    | 6.7.20 | Commission wants to make it expressly clear that there is no
    shortcut way unless a systematic drive is made to reduce the distribution loss. This
    should necessarily include metering of 11 kV feeders, metering at LV side of transformers,
    pole scheduling, verification if deemed necessary of consumer connected loads,
    rectification or replacement of consumer meters so that each feeder is converted to a
    Profit Centre as has been very aptly stated by the Ministry of Power, GoI, which is
    allotting large sum of funds to meet cost of metering etc. to achieve the goal in a time
    bound manner, which will be available through State Govts. to utilities and SEBs under
    APDRP programme. | 
  
    | 6.7.21 | There are 846 Nos. of 33/11 kV feeders in the State under the
    four DISTCOs. There are about 900 field sections in the DISTCOs. This means that there may
    be 1 to 2 Nos. of 11 kV feeders under each section and 1 No. of 33 kV feeder and 9 Nos. of
    33/11 kV transformers and at least 30 Nos. of distribution transformers in each feeder.
    Once members and other supporting staff including MRT personnel are made available, it
    would be possible to complete within one year for monitoring of all feeders along with
    complete pole scheduling leading to identification and regularisation of unauthorised
    connection. Progressive achievements will bring substantial in reduction of loss in
    feeders.   | 
  
    | 6.7.22 | Commission, among other things shall attach highest priority
    on these aspects and would expect the licensee to aggressively start taking up related
    activities. Commission would, on its part approach DFID to provide support to temporarily
    hire services of technical personnel by the Commission to oversee the progress made in
    this regard by the licensee on a day to day basis. | 
  
    | 6.7.23 | Although the Commission in deference to the spirit of OER
    Act, 1995 would have liked for a hands-off regulation while dealing with DISTCOs. But it
    finds to its dismay that utilities have taken advantage of this liberal gesture and have
    done precious little to address this single major factor of loss reduction which
    constitutes a menace to the viability of the power sector. Therefore, Commission would
    closely associate itself in monitoring the activities of DISTCOs in this regard. | 
  
    | 6.7.24 | As indicated in para 6.7.16 the loss as a percentage of HT
    & LT input for the year 2005-06 approved by the Kanungo Committee should be targeted
    at 28.39% to be attained by all the DISTCOs. |