6.5
|
Reasonable Return With regard to
reasonable return it is clarified that the same has to be calculated on the basis of the
capital base arrived at in accordance with the provision of Sixth Schedule to the Supply
Act, 1948. |
6.6
|
Treatment of Working Capital
|
6.6.1
|
The Commission believes that the companies must commit
themselves to a higher level of efficiency, bring loan to meet the working capital needs
so that the transmission utility and the generators are not starved of funds. There is a
gap between the revenue billed and the revenue realised due to inefficiency on the part of
the licensees for failing to take appropriate and expeditious steps like disconnection in
time or initiation of civil suits to realise the arrear dues. Domestic, irrigation and
agricultural consumers are not required to pay any DPS for delay in payment, whereas small
and medium industries and other categories only pay one time DPS. This is a disincentive
for revenue collection especially when the licensees are not capable of realising the dues
after the due date of payment is over. The Commission also may at appropriate time
consider for levy of DPS for those consumers who are at present not covered under DPS for
delay in payment.
|
6.6.2
|
The distribution companies have failed to bring required
working capital to ensure cash balance in the system to meet all expenses. The licensee
can get rebate on prompt payment from GRIDCO @2% per month, which will reduce its power
purchase liability. In a sense if the licensee arranges working capital from the
commercial and financial institutions they can save not only the DPS but will earn a
rebate from the GRIDCO that will compensate the interest on working capital and may accrue
some revenue in the form of rebate.
|
6.7
|
T&D loss
|
6.7.1
|
The next issue is determination of the total cost of
distribution and retail supply. The supply business requires purchase of power by the
DISTCOs from the transmission company (GRIDCO) for supply to consumers. The energy
received at grid sub-stations at 33 kV by the DISTCOs and supplied to the end-use
consumers at different voltage levels entails both technical and commercial losses. The
Commission hitherto have been following the concept of determination of power procurement
after applying a normative loss level to the total power proposed to be sold by the
licensee, irrespective of the quantum of actual power purchase by DISTCOs from GRIDCO.
This quantum of power purchase is metered in each grid sub-station and is reflected in the
various data recorded in the energy billing centre (EBC) of GRIDCO and also in the BST
bill of GRIDCO raised on DISTCOs.
|
6.7.2
|
The World Bank Staff Appraisal Report of April 1996 projected
different levels of transmission and distribution loss for the year 1996-97 to the FY
2002-03 based on the studies made by a group of reputed consultants. The Commission while
approving the tariff application in the year 1997-98 took cognizance of these projected
loss figures. While adopting a loss level of 35% for the year 1997-98, the Commission went
by the estimate of 34.8% made in the SAR as against the claim of 47% made by GRIDCO for
that year. The projections made in the SAR, the level of T&D loss as established by
the audit report of GRIDCO gives a wide disparity in the projections and actual
performance as can be revealed from the table below. Table : 6
As per SAR of 1996
|
FY 97 |
FY 98 |
FY 99 |
FY 00 |
FY 01 |
FY 02 |
FY 03 |
Energy available for sale (MU) |
9785 |
10902 |
12726 |
13902 |
14809 |
15560 |
16342 |
T&D losses (%) |
39.5 |
34.8 |
29.2 |
24.3 |
22.7 |
21.7 |
20.6 |
Electricity sale (MU) |
5924 |
7103 |
9004 |
10528 |
11442 |
12187 |
12976 |
Table : 7
Actual performance
|
FY 97 |
FY 98 |
FY 99 |
FY 00 |
Energy available (MU) |
9651
Audited |
10324
Audited |
10571
BST order 2000-01 |
10131
BST order 2000-01 |
T&D losses (%) |
49.47 |
49.24 |
48.60 |
45.36 |
Electricity sale (MU) |
4876 |
5240 |
5433
RST filing 00-01 |
5536
Tax audit RST filing of CESCO 00-01 |
|
6.7.3
|
The members the Commission Advisory Committee specifically
discussed the issues of high percentage of T&D loss, Distribution loss, poor
performance of Distcos, subsidy, cross-subsidy. Majority of the members suggested that the
recommendation of the Kanungo committee should be kept in view while finalising the tariff
and revenue requirement of DISTCOs as neither the Government of Orissa filed any objection
nor depute any representative to appear in the hearing. Members also advocated in favour
of uniform retail tariff for the whole State. Some of the Members raised issues specific
to the interest groups they represent. But there was near unanimity with regard to the
certain issues. It was felt that T&D loss was still high and while fixing the target
level of loss, the Commission should not go back to the level already set. Rather the
target level of loss be set at still lower. It was also felt that installation of meters
and consumer services were far from satisfactory. Most of the members opined that there
should be thorough scrutiny on the input cost of the licensees, while Some suggested that
depreciation should not be charged on the assets those have already outlived. The Chief
Electrical Engineer, S.E. Railways raised certain vital issues to be tackled while passing
this tariff order to give benefit to the Railways.
|
6.7.4
|
The objectors in general were of the opinion that the
adoption of a uniform loss figure for the four distribution companies with a different
load mix was hiding the inefficiency of the companies with higher components of HT and EHT
load. EHT component of load makes a big difference to the overall loss figure for the
company as loss in EHT category is practically negligible. The overage loss as a
percentage of the total power procurement from the GRIDCO by DISTCOs as well as the direct
sale figures at EHT as projected by the four DISTCOs are given in the table for the FY
2001-02.(RR02-03 filing of DISTCOS). Table : 8
|
NESCO |
WESCO |
SOUTHCO |
CESCO |
TOTAL |
Input for the DISTCOs (MU) |
2208.4 |
2920.2 |
1541.3 |
4024.6 |
10694.45 |
Sale at EHT (MU) |
243.72 |
583.5 |
122.27 |
266.02 |
1215.51 |
Proposed Distribution Loss (%) |
47.4 |
45.1 |
41 |
45 |
45 |
|
6.7.5
|
Some of the objectors have pointed out that the distribution
loss is being computed after taking into account even the zero loss EHT energy input into
the system to show a reduced level of loss. The total power sale to a DISTCO is arrived at
the Energy Billing Centre of GRIDCO by integrating the EHT drawal at 132/220 kV and bulk
power drawal at 33 kV in any grid sub-station. Therefore, sale at EHT can be taken out
from the total power purchase figures to determine the energy input to various DISTCOs for
supply to HT and LT consumers. If the EHT sale projected by the four DISTCOs are taken out
from the total sale projected by these companies then the distribution loss as the
percentage loss of HT and LT input works out to 53.3% for NESCO, 56.3% for WESCO, 44.1%
for SOUTHCO and 48.2% for CESCO with an overall loss figure of 50.6% for the State as a
whole under HT & LT category.
|
6.7.6
|
As we will be determining the energy input into the DISTCOs
system based on the billing figures of GRIDCO for the FY 2001-02, it will be appropriate
to determine the loss as a percentage of HT and LT input after deducting the direct sale
at EHT to show a comparative picture of performance of the four DISTCOs and also plan for
bringing down the distribution loss at the HT & LT level, which will ultimately bring
down the overall distribution loss in a DISTCO.
|
6.7.7
|
Identical comparison can be done for the FY 2002-03 by
determining distribution loss as a percentage of HT and LT input.
|
6.7.8
|
The Commission in the tariff order dtd.19.01.2001 had observed
that the task of fixing a level of loss in the absence of verifiable and reliable data has
led it to apply a value judgement that should be fair, reasonable and financially sound.
Any arbitrariness on the part of the Commission will either affect the financial viability
of the licensee or sustain undue burden on the consumers.
|
6.7.9
|
The Commission had also observed in the last tariff order
that the high T&D loss is not an isolated phenomena in Orissa. Higher level of loss
figures are being gradually disclosed in all most all the reforming states in the country.
The Commission was also of the view that the benchmark of T&D loss at 35% was as a
measure of performance perceived to be unrealistic and unacceptable by GRIDCO and the
DISTCOs. The World Bank on whose SAR Commission relied in fixing an overall loss level of
35% in FY 1997-98 subsequently came out in its midterm review report dtd.31.10.1998 that
it underestimated the actual loss level. The World Bank states "Consultation with the
Commission on the issue of recognizing the actual system loss levels and pass through of
prior years' financial losses, given that we all so severely underestimated GRIDCO's
system losses in 1996 and set unachievable performance targets".
|
6.7.10
|
Therefore DISTCOs all along complained about to unrealistic
loss level of 35% adopted by the Commission while adopting a loss level of 34% for the FY
2000-01 including the losses at EHT transmission system of 3.7%, the Commission had
directed the DISTCOs during the course of the hearing to carry out pilot studies within a
period of six months from April, 2001 to September, 2001 and submit the same to the
Commission for its appraisal while determining the target level of loss reduction from
year to year. The Commission is constrained to place on record the utter failure of
licensees to address this most important and crucial issue which was being raked up by
them time and again. DISTCOs have not initiated any concerned and vigorous effort to fix
meters in feeders, LV side of transformer and consumers served by the feeder to ascertain
the actual level of loss.
|
6.7.11
|
Due to insistence by Commission the DISTCOs started
determination of loss on a selected feeder. It was a much delayed exercise by all the
licensees. Also Commission's effort to engage outside consultants to oversee the pilot
loss study could not take off due to the financial problem of the licensees. Only WESCO
initiated a study by engaging an outside agency.
|
6.7.12
|
However, the Commission with the assistance of the Department
for International Development (DFID) has conducted pilot study in one 11 kV feeder for
WESCO, NESCO and SOUTHCO and two feeders of CESCO by appointing its own consultants. The
report of this pilot study demonstrates that there is ample scope and opportunity for
quick reduction of loss by the DISTCOs.
|
6.7.13
|
The distribution companies while submitting the business plan
for a period of 5 years to the Committee of independent expert in the month of October,
2001 have supplied the following distribution loss figures for the year 2001-02 to
2004-05:- Table-9
Figure of distribution loss projected by DISTCOs before
the Committee of Independent Expert
Name of the company |
FY 01-02 |
FY 02-03 |
FY 03-04 |
FY 04-05 |
CESCO |
40.94% |
39.35% |
37.57% |
36.08% |
NESCO |
46.98% |
40.77% |
36.85% |
34.12% |
WESCO |
41.08% |
39% |
36.93% |
34.89% |
SOUTHCO |
40.89% |
39.21% |
36.01% |
33.14% |
ALL ORISSA |
42.21% |
39.56% |
37.00% |
34.87% |
|
6.7.14
|
This, however, excludes the transmission loss of 4.65%,
projected by GRIDCO from 2001-02 to 2005-06.
|
6.7.15
|
The committee, however, accepted a distribution level loss of
42.21% for the base year of FY 2001-02 after hearing the DISTCOs and suggested reduction
of distribution loss by 5% each year from FY 2002-03 to reach a level of 22.21% in the
year 2005-06. Similarly, the committee had also approved a reduction of transmission loss
at a rate 0.3% each year from FY 2002-03 till the losses reach 3.7% by 2005-06. This is
projected in the table below. Table : 10
Loss figures approved by the Committee of Independent Experts
|
FY 01-02 |
FY 02-03 |
FY 03-04 |
FY 04-05 |
FY 05-06 |
Distribution loss |
42.21% |
37.21% |
32.21% |
27.21% |
22.21% |
Transmission loss |
4.7% |
4.4% |
4.1% |
3.8% |
3.7% |
|
6.7.16
|
As explained in para 6.7.6, computation of loss after
deducting the zero loss EHT energy from year to year is given below. Table
: 11
Computation of loss as a percentage of HT & LT input based on the Business Plan
submitted by DISTCOs to the Committee of Independent Experts
|
FY 01-02 |
FY 02-03 |
FY 03-04 |
FY 04-05 |
FY 05-06 |
Loss as a %age HT & LT input |
49.67% |
45.01% |
39.9% |
34.25% |
28.39% |
|
6.7.17
|
The committee of independent experts appointed by the
Government of Orissa to review the power sector reform in their report have suggested
reduction of distribution loss at the rate of 5% per annum. The pilot study conducted by
the Commission brings out very clearly that the scope of reduction of distribution loss is
enormous provided the companies take effective steps such as technical, financial and
managerial decisions for reduction of distribution loss. Any number of alibis expressing
inability for not reducing the distribution loss are not acceptable to the Commission.
Besides higher level of loss found out on the basis of pilot study is purely indicative as
the number of feeders selected were very few compared to the existing number of feeders.
Pilot study results cannot be taken as basis of loss levels existing in different DISTCOs,
as study on one feeder out of hundreds of feeders in the company with varied load mix,
concentration of loads, length and size of feeders cannot be a representative one. But
this study brought to the fore very interesting facts like direct tapping of 11 kV feeder
by industrial consumers, by-passing of meter CTs. It so happened in some areas where pilot
study was being taken up, the consumers locked their houses and went away forbidding the
utility staff and Commission consultant to check the status of the meter. Pole scheduling
in the study area revealed unauthorized abstraction of energy by the illegal consumers,
consuming energy far more in excess of what was shown in the consumer ledger of the
DISTCOs.
|
6.7.18
|
In the 2001-02 tariff filing, WESCO had reported a loss level
of 38% for that year. But while submitting the revenue requirement application FY 2002-03,
WESCO have reported distribution loss for the year 2001-02 as 45%. This kind of
irresponsible reporting for a particular year has been made within an interval of 3
months. It implies that the DISTCOs have demonstrated a very casual attitude in projecting
the figure to the Commission for the purpose of determination of tariff or revenue
requirement. The case of other companies are also not different.
|
6.7.19
|
The Commission accepts the distribution loss figure as
approved by the Kanungo Committee as 42.21% for the FY 2001-02 which is treated as the
base year. This figure of 42.21% represents the overall average distribution loss for the
entire State but varies across the four distribution companies. The variation in loss
figures across the DISTCOs are exhibited in Table-12. The Commission also adopts the
recommendation of the committee for reduction of distribution loss at least at the rate of
5% per annum from 2001-02 to 2002-03. The Commission therefore directs that for the
purpose of determination tariff and the revenue requirement the rate of loss reduction
will be calculated at the rate of 5% (overall average for the state) starting from the FY
2001-02 and 2002-03. Accordingly, the following loss figures are approved for the
aforesaid purpose for the year 2001-02 and 2002-03. While formulating the multi-year
tariff proposed to be effective from 01.04.2003, this aspect of loss reduction along with
collection efficiency etc will be decided for subsequent years. Table
: 12
PURCHASE & SALES BY
DISTCOs BASED ON 10 MONTHS ACTUAL |
|
FY 2001-02 |
Expected/Projected
for FY 2002-03 |
|
Purchase(MU) |
Loss(%) |
Sale(MU) |
Purchase(MU) |
Loss(%) |
Sale(MU) |
CESCO
|
4167.77 |
40.94% |
2461.485 |
4321.00 |
35.94 |
2768.03 |
NESCO
|
2253.62 |
46.98% |
1194.8693 |
2291.20 |
41.98 |
1329.36 |
WESCO
|
2980.64 |
41.08% |
1756.1931 |
3066.54 |
36.08 |
1960.13 |
SOUTHCO
|
1525.07 |
40.89% |
901.46888 |
1682.39 |
35.89 |
1078.58 |
TOTAL
|
10927.10 |
42.21% |
6314.02 |
11361.13 |
37.21 |
7136.10 |
|
6.7.20
|
Commission wants to make it expressly clear that there is no
shortcut way unless a systematic drive is made to reduce the distribution loss. This
should necessarily include metering of 11 kV feeders, metering at LV side of transformers,
pole scheduling, verification if deemed necessary of consumer connected loads,
rectification or replacement of consumer meters so that each feeder is converted to a
Profit Centre as has been very aptly stated by the Ministry of Power, GoI, which is
allotting large sum of funds to meet cost of metering etc. to achieve the goal in a time
bound manner, which will be available through State Govts. to utilities and SEBs under
APDRP programme.
|
6.7.21
|
There are 846 Nos. of 33/11 kV feeders in the State under the
four DISTCOs. There are about 900 field sections in the DISTCOs. This means that there may
be 1 to 2 Nos. of 11 kV feeders under each section and 1 No. of 33 kV feeder and 9 Nos. of
33/11 kV transformers and at least 30 Nos. of distribution transformers in each feeder.
Once members and other supporting staff including MRT personnel are made available, it
would be possible to complete within one year for monitoring of all feeders along with
complete pole scheduling leading to identification and regularisation of unauthorised
connection. Progressive achievements will bring substantial in reduction of loss in
feeders.
|
6.7.22
|
Commission, among other things shall attach highest priority
on these aspects and would expect the licensee to aggressively start taking up related
activities. Commission would, on its part approach DFID to provide support to temporarily
hire services of technical personnel by the Commission to oversee the progress made in
this regard by the licensee on a day to day basis.
|
6.7.23
|
Although the Commission in deference to the spirit of OER
Act, 1995 would have liked for a hands-off regulation while dealing with DISTCOs. But it
finds to its dismay that utilities have taken advantage of this liberal gesture and have
done precious little to address this single major factor of loss reduction which
constitutes a menace to the viability of the power sector. Therefore, Commission would
closely associate itself in monitoring the activities of DISTCOs in this regard.
|
6.7.24
|
As indicated in para 6.7.16 the loss as a percentage of HT
& LT input for the year 2005-06 approved by the Kanungo Committee should be targeted
at 28.39% to be attained by all the DISTCOs.
|