6.33
|
Load factor billing
As opined by some of the objectors, it is true that it is the statutory
obligation on the part of the licensee to replace meters. Load factor billing has been
prescribed for a limited period the meter remains defective/or the consumer goes without
meter to serve as a disincentive for the consumer and help adoption of metering by
consumers. Hence, the Commission directs that the load factor billing should continue as
per the existing tariff.
|
6.34
|
Incentive for maintaining high power factor
|
6.34.1
|
For the first time, the Commission in its tariff order dt.30.12.99
introduced an incentive to encourage improvement in power factor above 90%. Subsequently,
the limit was raised to 97% in the RST order dt.19.01.2001. WESCO estimates that the
rebate alone on this account to HT/EHT consumers will be of the order of Rs.1.31 crore
during the FY 2001-02.
|
6.34.2
|
Some objector opined that for the health of electrical machinery it is
risky to maintain power factor between 97% and unity power factor lagging because there is
every chance of high voltage when suddenly some load gets off from the circuit.
|
6.34.3
|
It should be kept in view that the industries for better protection of
their installation should follow prudent operational practice installing protective
devices, so as to isolate the equipment during abnormal transient condition arising out of
sudden load throw off or tripping of meter or feeders.
|
6.34.4
|
Further, as indicated below the KVA demand of the industry decreases as
the PF improves, there by benefiting the consumer on account of higher demand charge.
PF KVA
Excess KVA
201 1
0
0.99 1.01
0.01
0.98 1.02
0.02
0.97 1.031
0.031
0.96 1.042
0.042
|
6.34.5
|
Similar provision of power factor incentive/rebate have been recommended
by other State Regulatory Commissions such as Gujurat Electricity Regulatory Commission,
U.P. Electricity Regulatory Commission, Maharashtra Electricity Regulatory Commission
where incentive is allowed for maintaining PF above 95%. Hence, the Commission does not
consider it necessary to make change in the existing provision with regard to power factor
incentive.
|
6.35
|
Incentive for prompt payment
|
6.35.1
|
Some objectors suggested for relaxation of the rebate period of 48 hours.
WESCO in its RST application for the year 2001-02 has estimated that the rebate on account
of prompt payment within 48 hours of presentation of bill during the FY 2001-02 will be
order of Rs.2.1crore in addition to an amount of Rs.0.5 crore on account of rebate of 10
paise/unit. Hence, it is expected that to avail such heavy amount of rebate, consumers
should put extra efforts and make payment of bills in time.
|
6.35.2
|
As per Commissions order, certain categories of consumers are
entitled to a rebate of 1% of the amount of the monthly bill (excluding arrears and
electricity duty) if payment is made within 48 hours of the presentation of the bill. When
a cash discount is allowed for payment within a specified period, the cost of credit can
be computed. For instance, if 15 days credit is offered with a stipulation of 1% cash
discount for payment within 48 hours (two days), excluding the day for service of the
bills, it means that the cost of deferment of payment by 12 days is 1%. If payment is made
12 days earlier than the due date, 1% of the amount can be saved, which amounts to an
annual attractive saving rate of 30%.
|
6.35.3
|
If cash discount is not availed, the effective rate of interest will work
out to 30.3%. The rational for availing trade credit should be its saving in cost
over the form of short term financing, its flexibility and convenience. Stretching trade
credits or accounts payable results in cash discount foregone.
|
6.35.4
|
As an example, Mahanadi Coal Field with a monthly bill of Rs.8 crore gets
a rebate of Rs.8 lakh per month or nearly a crore of rupees over a period of one year. It
is in the interest of the consumer to avail the cash benefit or pay the normal charges
i.e. within 15 days from the date of bill..
|
6.35.5
|
This practice of prompt payment is followed by the generators for raising
bills against GRIDCO and by GRIDCO to DISTCOs also. In this age of SATCOM, FAX, Internet
and STD commercial benefits must dictate and guide not only the functioning of the
licensee but those of the consumers also.
|
6.35.6
|
It has been reported by the licensees that a number of consumers are
availing this prompt payment rebate. The objections have come mostly from the various
Departments of the Government for fear of audit objections for not availing the rebate due
to their cumbersome official procedure within their organization before releasing payment
for consumption of electricity. For them 48 hours may not be adequate and they may not be
able to avail the prompt payment rebate. In that case, they can pay the normal charges
within the due date of 15 days and convince the audit about their difficulty of not
availing the rebate or alternatively streamline the procedure to avail the rebate as a
commercial incentive for the Government
|
6.35.7
|
In view of this, the Commission does not consider it necessary to depart
from its past order regarding incentive on prompt payment.
|
6.36
|
Metering of street lights
|
6.36.1
|
Issues that street light metering has not been done and billing is done on
load factor basis was raised during the course of the hearing. In this regard, Commission
would like to convey that meetings were taken by this Commission with Director, Municipal
Administration, Government of Orissa, Chief Executives of Municipalities and Managing
Directors of DISTCOs on 11.04.2001 and 19.04.2001 to resolve the issues on metering of
street lights.
-
It was agreed in the meeting that inspection to assess the connected load would be taken
up by Municipality and DISTCOs.
-
A single agreement for street lighting will be executed for a municipal area.
-
Wherever metering is in place, the rates applicable for street lighting category should
be implemented.
-
Until metering is in place, calculation of consumption for the purpose of billing will
have to be mutually worked out by the municipalities and DISTCOs considering the connected
load and the number of burning hours for street lighting. Preferably average 11 hours
burning of the lamps may be adopted due to seasonal variation. No maintenance should be
carried out during day time which requires avoidable consumption of electricity.
-
The switching ON and OFF of street lights will be done by the staff of the licensee.
Replacement of bulbs, fittings and maintenance thereof shall be carried out by the
municipal staff.
|
6.36.2
|
The licensees should take adequate steps to comply with the decisions
taken in the joint meeting with the Director, Municipal Administration, Government of
Orissa and Chief Executives of Municipalities, as stated above.
|
6.37
|
Industrial policy framed by Government of Orissa
An issue was raised by the Orissa Small Scale Industries Association that the
proposed amendment in tariff by the licensee is directly against the Industrial Policy
Resolution (IPR) of Government of Orissa. This is clarified that Industrial policy
differentiating categories and conferring benefits change from time to time on various
considerations. Electricity charges are to be non-discriminatory from economic point of
view and it is neither desirable nor possible to synchronize the pricing in keeping with
changes from industrial and financial angle. However, if the State Government desires to
extent any benefit to a class or group of consumers, they can do so under Section 12(3) of
OER Act, 1995 by providing subsidy.
|
6.38
|
Retaining of Security Deposit by licensee
|
6.38.1
|
The objection raised by some objectors (OCA) that bi-monthly domestic
bills are increasing loss to the licensee is not correct as the licensee is already
retaining charges of supply of two months against security deposit which can be utilized
as working capital.
|
6.39
|
Multi-year Tariff
|
6.39.1
|
In course of the hearings, the utilities as well as some of the
respondents spoke about the element of uncertainty and risk inherent in an annual tariff
setting exercise and they pleaded for introduction of a multi-year tariff regime which
would reduce such uncertainty and bring in predictability. We, too are conscious of the
need for greater certainty in the regulatory treatment of a host of issues having direct
impact on tariff setting. It shall be our endeavor to set in motion a multi-year tariff
regime effective from April, 2003 for FY 2003-04 after wide publicity and valued
consultation with all the stakeholders. We have, in fact, initiated preparation of a
five-year sectoral plan covering generation, transmission and distribution which will
provide key inputs to this exercise. The draft consultation document which is currently
under finalisation will also be brought out to facilitate the process of such consultation
and obtain comments from the various stakeholders.
|
6.39.2
|
The utilities have to improve upon their own performance within a
stipulated time frame by upgrading their managerial skills and efficiency by scrupulously
adhering to certain operational norms like reduction in the level of loss, attaining
certain level of billing and collection efficiency, setting a target for investment and
avoiding time and cost overruns in execution of projects, etc. This calls for fixing a
target to be achieved over a Control period than a target confining to a
single year to provide a kind of predictability to the consumers, their own shareholders
and to the Regulatory Commission. The Commission considers it prudent and desirable to go
for a multi-year tariff regime for which the utilities should conform themselves to a
multi-year target setting in the areas stated above. We also feel that the FY 2001-02
should be considered as the base year for all calculations as suggested by the Kanungo
Committee.
|
6.39.3
|
Some objectors raised the issue that the licensee should accept the
payment by account payee cheque instead of demand draft.
|
6.39.4
|
As per the existing provision in OERC Distribution Code, 1998 (Regulation
1993), the bill amount shall be paid by the consumer either in cash or by bank draft or by
bankers cheque or where specifically allowed by the licensee by account payee cheque
or credit cards. Hence, the facilities are already available in the OERC Regulation.
|
6.39.5
|
Some of the objectors advocated in favour of uniform retail tariff
throughout the state . Historically, uniform tariffs have been used in Orissa, and indeed
in all states of India, in spite of significant cost differences to serve different
geographic areas. Prices that differ in relation to differences in cost generally make
better use of societys resources than uniform tariffs.
|
6.39.6
|
Some objectors suggested for reduction of cross subsidies. As has already
been dealt in the Retail Supply Tariff order of the Commission dated 19.01.2001, the
tariff structure that this Commission inherited was a highly distorted one. In the past
years by rationalising the tariff structure it has been ensured that there is a
progressive increase in the rate of tariff for those who are paying less than the average
cost of supply. The Commission in future tariff revisions will take steps for
rationalization of tariff i.e. gradually adopting a uniform rate for all consumer
categories using electricity on the same voltage of supply which is a good measure of the
cost of supply or thereby reduce the cross subsidy between groups of consumers.
|
6.39.7
|
The question of a reasonable railway traction tariff raised by the S.E.
Railway so as to maintain a railway traction tariff, not exceeding that of HT industrial
consumer was also highlighted for consideration by OERC. The Commission would like to
clarify that the railway traction tariff in Orissa is at par with that of HT or EHT
consumers depending upon the voltage of supply as the tariff structure has been totally
linked to the voltage of supply. Railway traction tariff is lower in Orissa. Therefore
railways should have no grouse on this account.
|
6.39.8
|
The railways had also raised the issue of a single part tariff which is
today applicable only to very large industries with a guaranteed off-take to which
category the railways does not belong.
|
6.39.9
|
The second issue relates to the prevalent maximum demand charge in Orissa.
It needs to be clarified that the Commission does not propose to make any change to the
current maximum demand charge in force. Railway further concern about recording and
charging of maximum demand for individual supply points as per the existing system turned
out to be totally unrealistic as the railways were moving loads for all substations along
this track. In this connection, the Railways quoted the letter of Ministry of Energy CEA,
New Delhi dated 21.10.1988 proposing billing on the basis of simultaneous maximum demand
recorded in contiguous substation of the SEBs. It may be mentioned here that the railway
traction supply is from the EHT network of the GRIDCO and the billing is done by the
various supply companies to the railways in their area of license. Therefore, the
Commission is of opinion that the issue should be mutually discussed by the railways with
the four distribution companies and their views on the matter may be placed before the
Commission for taking a holistic view.
|
6.39.10
|
The railways also proposed that the integration period of 30 minutes for
measurement of maximum demand in respect of railway traction has been changed to 15
minutes. The railways requested that the OERC may consider restoration of integration
period 30 minutes as per the earlier method which is also in confirmity with the clause
No.2(8) of Electricity Supply Act, 1948.
|
6.39.11
|
The Commission deliberated on this issue and observed that 30 minute
integration period for all categories has been provided in the Regulation of ASEB,
Ahmedabad Electricity Company, MPSEB, HSEB, DVP, Gujurat, Maharashtra, Tamil Nadu. Fifteen
minute integration period has been provided by UPERC, APERC for loads more than 4000 KVA,
and for railway traction by WBSEB. There are SEBs with one hour integration period also.
|
6.39.12
|
The railways earlier have made a case that there can be growth of traction
only if the cost of tariff matches the cost of diesel locomotion. Keeping this fact in
view, the Commission will consider favourably the adoption of 30 minute integration period
which can reduce the overall tariff for railways. It will be, therefore, desirable to
discuss the issue along with the issue of simultaneous maximum demand due to feed
extension for meeting the demand of the rolling stocks after discussion with the various
supply companies of the state. The railways and DISTCOs may mutually discuss and come up
with a proposal for consideration of the Commission. This will require amendment of the
supply regulation OERC Distribution (Condition of Supply) Code, 1998. Till such time the
present arrangement shall continue.
|
6.40
|
Consumer Service
|
6.40.1
|
Construction Power
Objection was raised by M/s. Aditya Aluminium that the industries under
construction may be classified separately and no demand charge should be levied on
construction power. There seems to have no logic behind the objection as the licensee is
to arrange/book, the quantum of power as per the contract demand and pay fixed charge
against the said quantum of power which he has to recover from the consumer.
|
6.40.2
|
Observations for over drawal penalty clause
For the purpose of calculation of minimum demand there should not be any
differentiation between peak or off peak hours. As such we do not accept the proposal of
the objector for any change in existing tariff order.
|
6.40.3
|
Observation for incentive higher consumption
|
6.40.3.1
|
Some objectors such as M/s. Mahanadi Coal fields Ltd. pleaded that load
factor as per standard nomenclature should be based on Maximum Demand and should have no
relation with Contract Demand.
|
6.40.3.2
|
It is clarified that, for the purpose of calculation of incentive energy,
the standard terminology of Load Factor has not been used, rather it is only the ratio of
the total number of units consumed during a given period to the total number of units that
would have been consumed had the contract demand or the maximum demand whichever is higher
was maintained through out the same period.
|
6.40.3.3
|
It may be noted that the incentive tariff for HT/EHT category of consumers
was introduced in the OERC RST order dt. 30.12.99 where incentive energy was considered
above the load factor of 50% of contract demand. Further as mentioned in the OERC RST
order dt. 19.01.2001 Some objectors objected to recording of load factor during the
FY 1999-00 in excess of 100% in the filing made by the licensee on the ground that it had
an element of absurdity. As prescribed in OERC Condition of Supply Regulation, 1998 load
factor of a consumer under no circumstances can exceed 100% Therefore consumption
ratio was adopted in place of load factor for determination of incentive energy. It is
further clarified that for the purpose of calculation of incentive energy, power factor
should be taken as 0.9 for conversion from KVA to KW or MVA to MW.
|
6.40.4
|
Treatment of Past Losses
|
6.40.4.1
|
With regard to the treatment of past losses, the Commission would like to
clarify that in the absence of audited accounts of the licensees, it is difficult to
determine the extent of loss that could have been admissible within the provisions of the
Sixth Schedule to the Supply Act, 1948. A decision on this issue can be taken only when
the accounts are compiled and audited in accordance with the relevant regulations of OERC.
|
6.40.4.2
|
The Commission observes with displeasure about non-maintenance of the
asset register by licensees inspite of its earlier direction. The Commission directs that
maintenance of asset register must be completed latest by 31 August and compliance
reported
|
6.40.5
|
Demand charges during statutory power cut
The levy of demand charge during the period of statutory power cut has to be
dealt in accordance with he relevant conditions of OERC (condition of supply) Code,1998.
|
6.40.6
|
Meter Rent
The Commission examined the issue of rents chargeable for the meters supplied by
the licensee and does not consider it necessary to make any change the rate already fixed
by the Commission in its order dtd.19.01.2001.
|
6.40.7
|
Quality of Supply & Service
Interruption, low voltage and unreliable supply is a matter of serious concern to
the Commission which is taking appropriate steps to verify the data furnished by the
licensee in this regard through an affidavit to the Commission. The Commission also is
taking effective steps for monitoring of these parameters for meeting the supply standards
as prescribed by it.
|
6.40.8
|
Unauthorised and Illegal abstraction of electricity
The issue of unauthorised abstraction of electricity is one of the principal causes of
high commercial losses in the licensees system which is being monitored every month
at the Directors Level Meeting. The licensees must take the help of law and order
authorities and the Commission is committed to allow any additional expenditure on account
of curbing the theft and unauthorised abstraction of electricity which must be taken up
vigorously and it shall continue to be monitored at the Commissions level.
|
6.40.9
|
Rural Electrification
The rural electrification work to be taken up by the licensee as a capital grant.
In this connection, the Kanungo Committee have suggested for setting up of Rural
Engineering, Planning Organisation (REPO) and Rural Electrification Planning Units (REPU)
under Government of Orissa to monitor R.E. and L.I. works. As and when REPO AND REPU start
functioning it is believed R.E. & L.I. works will be expedited.
|
6.40.10
|
Special Tariff for Power Intensive Industries
|
6.40.10.1
|
The Commission has taken a decision to continue with the tariff structure
approved vide its tariff order dtd.19.01.2001 in respect of all categories of consumers
supplied by the distribution and retail supply licensee. In this connection, the
Commission also examined the issues regarding a special tariff of the power intensive
categories of industries. Some of the objectors also submitted that a preferential
treatment to the EOUs was a burden to a licensee and the general consumer, as costly power
has to be procured to meet such demand. The Commission reiterate its commitment for
rationalisation of the tariff structure linked to the voltage of supply. Keeping the above
objective in view, incentive tariff has already been introduced for consumers of contract
demand of 110 KVA and above available power supply at HT or EHT in the previous tariff
orders. That automatically reduces the per unit cost of electricity with a higher level of
consumption as the fixed cost in the form of maximum charge gets distributed over a larger
number of units.
|
6.40.10.2
|
The Commission however, has taken note of very special nature of some of
the industries who provide continuous high load factor to the system and in the process
provides a support during the off-peak hours as base loads besides dissuading such units
from setting up CPPs. On the other hand this helps in getting cross subsidy from such
classes of consumers to other classes of consumers who are charged below the level of cost
of supply. This has also to be weighed against the option of having an industry within its
fold of supply of a licensee with a lower profit margin and the option of not having the
industry at all. The Commission has favourably considered in the past the above option and
have allowed signing of special agreement with a proposal of guaranteed off-take at a rate
lower than the normal rate applicable to similar class of industries.
|
6.40.10.3
|
The Commission in its past orders had approved tariff for consumers with a
contract demand with 100 MVA and above with a guaranteed load factor of 80% @ 200
paise/unit without levy of any demand charge. The Commission has approved a rate of 182
paise/unit with a guaranteed load factor of 90% and a contract demand of 50 MW in respect
of INDAL by approving for entry into special agreement between INDAL and WESCO. This rate
is linked to the Bulk supply Tariff approved in the Commissions order
dtd.19.01.2001. This rate will undergo a change on account of revision in Bulk Supply
Tariff.
|
6.40.10.4
|
The Commission will examine such special agreements for approval as and
when it is placed before the Commission provided the rates are within the parameters
indicated above.
|
6.40.10.5
|
Any licensee willing to enter into special agreement with a rate other
than that for a particular category can do so provided the licensee undertakes to absorb
the difference between the revenue at the approved rate and the rate at which it proposes
to enter into a special agreement with any industry. However, entry into special agreement
should be non-discriminatory in nature i.e. consumers falling into same category should be
offered similar rates.
|
6.41
|
Emergency power supply to CPPs
The Commission examined the request for raising the level of emergency power
availability to 75% of the capacity/co-generation plants to reduce the burden on the
smaller industries. The Commission would like to clarify that in the tariff order
dtd.19.01.2001, a rate of 380 paise/unit has been fixed for emergency power supply to CPP.
The order does not stipulate levy of any demand charge for emergency power supply to CPPs.
|
6.42
|
The revenue requirement estimated by WESCO has been duly examined at the
Commissions end.
|
6.43
|
Corrective measures and alternative calculation of revenue
requirement
|
6.43.1
|
During the tariff hearing the State Government did not appear and
participate despite due services of notice. It even failed to attend the Commission
Advisory Committee Meeting in this connection. The Commission has received no assistance
or commitment from the State Government and has had to proceed in the absence of
Governments participation. It may be mentioned that during the Workshop on
09.01.2000, organized by the Department of Energy, Government of Orissa, the Commission
made a presentation elaborating the various corrections as outlined in para 6.43.6 (A)
below. In the circumstances, the Commission has been constrained to recommend several
measures as listed below for approval by the Government of Orissa w.e.f. 01.04.2001 to
bring down the cost of power, cost of transmission of GRIDCO and cost of distribution. In
view of the urgency and importance of the measures for consumers of the State and for the
electricity industry and success of the State policy of reforms, it is absolutely
essential that the State Government should communicate their decision on the
recommendations without delay, in order that the Commission may give effect to the
alternative calculation of revenue requirement. Everyday of delay causes huge avoidable
cost to the consumers and the revenue gap of the licensees will go on snowballing beyond
control.
|
6.43.2
|
The terms and conditions for purchase of power from OHPC by GRIDCO is
governed by the power purchase agreement between OHPC and GRIDCO. The interim PPA between
OHPC and GRIDCO for purchase of power from OHPC old stations upto 31 March 2001 has been
approved by OERC with certain observations. Both OHPC and GRIDCO have been directed to
submit the PPA to OERC for approval. The new PPA in respect of these stations effective
from 01.04.2001 has not yet been received till date. Based on the latest commercial
practice OERC directs that parameters like O&M escalation, return on equity and
depreciation in respect of these stations will be calculated in accordance with the norms
given in this order. The Commission also decides to apply lower rate of depreciation
(pre-92 rates) for transmission and distribution assets to bring down the cost of supply
to the consumer.
|
6.43.3
|
Similarly the Commission would like to depart with respect to the O&M
escalation, ROE and depreciation norms in respect of UIHEP to bring down the input cost of
power.
|
6.43.4
|
(a) OHPC old stations
-
O&M escalation taken as per the weighted average of growth of Wholesale Price Index
and Consumer Price Index for FY 2001-02 which works out to 2.5%. The same rate has been
adopted for FY 2002-03.
-
Return on Equity is calculated @ 12% on OHPCs own investment of Rs 22.56 crore.
-
Depreciation has been allowed to the extent of loan repayment during the year.
(b) UIHEP
-
O&M escalation taken as per the weighted average of growth of WPI and CPI for FY
2001-02 which works out to 2.5%. The same rate has been assumed for FY 2002-03.
-
ROE has been calculated @12% on equity of Rs.298.70 crore.
-
Depreciation has been allowed to the extent of loan repayment during the year.
(c) GRIDCO & DISTCOs
Depreciation has been calculated at pre-92 rate for years 2001-02 and 2002-03 both in
respect of transmission and distribution business. |
6.43.5
|
The Commission is entrusted with heavy responsibility as per Section 11 of
the OER Act, 1995 under the head "Functions of the Commission". It would be
appropriate to quote the relevant portion of the above section. "11(1) Subject to
the provisions of this Act, the Commission shall be responsible to discharge, amongst
others, the following functions, namely-
-
to aid and advise, in matters concerning generation, transmission, distribution and
supply of electricity in the State ;
-
to regulate the working of licensees and to promote their working in an efficient,
economical and equitable manner;
.
|
6.43.6
|
(A) In view of the above provisions, the Commission would be
failing in discharging its responsibilities without giving proper advice to the State
Govt. for adopting the corrective steps to bring the reforms back to rails. Commission has
applied the following correctives in determining the revenue requirement for FY 2001-02
and 2002-03:-
-
Interest on GRIDCO bond issued by DISTCOs for the power purchase loan liabilities has
been calculated @8.5% for FY 2001-02 and FY 2002-03
-
Interest on World Bank loan has been calculated in terms of its original sanction
treating 70% as loan and 30% as grant for FY 2002-03
-
Interest on all existing bonds issued by GRIDCO have been calculated @8.5% for FY
2001-02 and FY 2002-03 assuming resecuritisation of the same.
-
New bonds of Rs.638 crore to be issued against power purchase liabilities of CPSUs
as on 28.02.2001 have been calculated @8.5% for FY 2002-03.
-
Impact of zero coupon bonds of Rs.400 crore issued by GRIDCO to Government of Orissa
against upvaluation of assets has not been considered for FY 2001-02 and FY 2002-03.
-
Outstanding loans from REC and PFC have been assumed for resecuritisation with a tax
free rate of 8.5%.
-
In view of swapping of Government and GRIDCO dues, interest on Government loan of
Rs.168.71 crore has not been allowed as a pass through for FY 2002-03.
-
Interest on GOO loans has not been allowed arising out of upvaluation of OHPC assets.
-
GOO loan of Rs.576.57 crore has been treated as loan on perpetuity.
(B) The Commission therefore advises Government of Orissa under section 11(1)(a) of
the OER Act, 1995 to approve the correctives w.e.f. 01.04.2001 as outlined in this para
from (i) to (ix) above to bring down the cost of power for the year 2001-02 and 2002-03. |
6.43.7
|
In this context the Commission deems it fit and proper to review the whole
question of revaluation of the assets of the erstwhile OSEB and Government of Orissa, at
the time of revesting of the same with GRIDCO and OHPC and the impact of the revaluation
on the tariff to be fixed now and in future. At the time of revesting GRIDCO and OHPC were
wholly owned Government companies. Section 23(4) of the OER Act, 1995 did not require any
such revaluation. When the assets of the OSEB vested in the State Government, the State
Government paid nothing for it and did not incur any expenses. The revaluation seems to
have been purely notional, agreed to between State Government on the one hand and GRIDCO
and OHPC on the other hand, the latter being Government companies at that time. Clause 2
of the statutory orders dated 01.04.1996 vesting assets with GRIDCO and OHPC runs as
follows.
In accordance with section 24 of the Act, the fair value shall be duly determined
of the property or rights in the undertaking involved at the time of transfer to or
involvement of any person or body other than the wholy owned Government company or
companies.
No such fresh and due determination of fair value appears ever to have been done
not even at the time of involvement of DISTCOs operating under the aegis of private
investor. There may have been some reason (like credit worthiness of GRIDCO and OHPC), at
the material time, for state and GRIDCO/OHPC agreeing to some notional revaluation, but
the Commission does not think any such reason to be relevant for the purpose of tariff
setting, involving rights of consumers and third parties or useful in the context of
present realities in the industry. The Commission therefore in the public interest has
attempted to nullify the effects of revaluation in the present tariff setting. |
6.43.8
|
Based on the observations of the preceding paragraphs of this order and
prudent commercial consideration relying on the existing purchase power agreements,
relevant rules, orders and evidential documents placed before the Commission. The
Commission determine the revenue requirement for the FY 2001-02 as well as for the year
2002-03. Accordingly the revenue requirement as estimated in two scenarios (i) with
correctives (ii) without correctives for 2001-02 is given in Table : 23. Details of
calculation of revenue requirement is given in Annex-A1. Table : 23
(Rs. in Crore)
Name of the licensee |
2001-02 (With correctives) |
2001-02 (Without correctives) |
Proposed sale in MU |
CESCO |
775.00 |
777.83 |
2461.48 |
NESCO |
435.44 |
444.00 |
1194.87 |
WESCO |
556.08 |
562.09 |
1756.19 |
SOUTHCO |
316.60 |
323.52 |
901.47 |
Additional RR on account of change in
cost of power and transmission by GRIDCO |
|
301.28 |
|
Total for DISTCOs |
2083.12 |
2394.34 |
6314.02 |
|
6.43.9
|
The revenue requirement for FY 2002-03 in both the scenarios (i) with
correctives and (ii) without correctives as per our recommendation regarding cost of power
and cost of transmission based on the principles enunciated in the earlier paragraphs of
this order is given in Table : 24. Details of calculation of revenue requirement is given
in Annex-A2. Table
: 24
(Rs. in Crore)
Name of the licensee |
2002-03 (With correctives) |
2002-03 (Without correctives) |
Difference |
Proposed sale in MU |
CESCO |
767.34 |
918.85 |
151.51 |
2768.03 |
NESCO |
421.62 |
509.25 |
87.63 |
1329.36 |
WESCO |
559.43 |
670.63 |
111.02 |
1980.13 |
SOUTHCO |
327.51 |
393.81 |
66.30 |
1078.58 |
Total for DISTCOs |
2075.90 |
2492.54 |
416.64 |
7136.10 |
|
6.43.10
|
It is evident from the calculations given in Table above that it will
require a very stiff upward revision in Retail Supply Tariff in respect of all consumers
of the State if the correctives proposed by the Commission is not accepted by the
government for immediate implementation. Incidentally, the correctives applied by the
Commission are, by and large, in line with those of Kanungo Committee recommendation with
minor modifications and few additional measures.
|
6.43.11
|
In this connection, the recommendation of the Kanungo Committee is very
pertinent wherein they had advised an external financial support other than debts to the
tune of Rs.3240 crore during a transition period of 4 years from 2001-02 to 2004-05 to
keep the tariff structure static at the current level and proposing to raise it by about
18% in the year 2005-06. It is expected that the Government will consider the advice of
the Commission in this regard and take immediate steps so as to avoid a stiff rise of
tariff to all classes of consumers particularly when State Government may not be in a
position to provide financial support as contemplated in the Kanungo Committee report.
|
6.43.12
|
However, if the decision of the Govt. of Orissa goes contrary to the
advice tendered by the Commission, the revenue requirement for the FY 2001-02 and 2002-03
as determined without applying the correctives shall be due for recovery from the
consumers.
|
6.44
|
Expected revenue from charges
The expected revenue from charges in respect of all the DISTCOs have been
determined by the Commission as explained in para 6.9.5.2 of this order in Table 15 &
16.
|
6.45
|
For the purpose of RST 2001-02, the licensee has given a proposal which is
given in annex to this order.
|
6.45.1
|
In para 6.43.8 the revenue requirement has been calculated by applying
necessary correctives to power and transmission cost payable to GRIDCO and distribution
cost.
|
6.45.2
|
Any revision of tariff in accordance with the OER Act, 1995 can be applied
prospectively. The reason is that a clear seven days notice before its
implementation is necessary under Sec. 26(5) of the OER Act, 1995. Revision of tariff
cannot be done in case of the FY 2001-02, which is already over. This situation arose
because of deficiencies on the part of the licensees to submit the revenue requirement and
tariff application in complete shape in time. As such, the tariff revision proposal for
the year 2001-02 submitted by the licensee is rejected.
|
6.45.3
|
As observed in para 6.43.12 if the decision of the Govt. of Orissa goes
contrary to the recommendations made by Commission the revenue requirement for the year
2001-02 as determined in this order without applying the correctives shall be due for
recovery. Since the FY 2002 is already over and no fixation of tariff is possible with
retrospective effect, the Commission will treat the gap between the revenue requirement
and expected revenue for the FY 2001-02 as a regulatory gap for recovery at a future date.
|
6.45.4
|
In as much as tariff proposals for FY 2001-02 have been rendered
infructuous, GRIDCO and DISTCOs propose that the Commission proceed under Section 26 (6)
of the OER Act, 1995 to determine tariff for FY 2002-03 on the basis of revenue
requirement for that year as approved by the Commission. Hence the Commission has
proceeded under section 26(6) to determine tariff under section 26(6) of the OER Act, 1995
for the FY 2002-03.
|
6.45.4.1
|
The Commission have made several recommendations to the Government of
Orissa for their implementation w.e.f. 01.04.2001. Accordingly the Commission have
determined the Retail Supply Tariff applying all correctives based on its recommendations
to the Government. If a decision to the contrary is taken by the Government the revenue
requirement for the FY 2002-03 as determined without applying the correctives shall be due
for recovery from the consumers. It will raise the revenue requirement by Rs.416.64 crore
on the basis of our present estimate. A tariff schedule is given in the Annex-D3.
|
6.45.5
|
This is based on the assumption that the existing retail supply
tariff as approved by OERC in order dated 19.01.2001 shall continue upto 31.07.2002 and
the rates indicated in Annex-D3 shall be
valid from 01.08.2002 to 31.03.2003 provided the recommendation as indicated earlier are
not accepted by the Government latest by 15 July 2002.
|
6.45.6
|
This tariff effective from 01.08.2002 shall be subject to such
proportionate reduction as may be necessary to the extent the Government accepts the
recommendation made by the Commission. The reductions being purely arithmatical in nature
shall take effect without any further proceeding for amendment under section 26(6) of the
OER Act 1995. However it is made clear that in case of such reduction a fresh notification
under section 26(5) of the OER Act will be made by the licensees with the approval of
OERC.
|
6.45.7
|
Finally, the Commission orders as follows with reference to the prayers of
the applicant. The Commission does not approve the retail supply tariff as proposed by
WESCO for 2001-02 and rejects the tariff revision proposal.
|
6.45.8
|
The Commission also does not approve the revenue requirement for the FY
2002-03 as proposed by WESCO and directs for implementation of Retail Supply Tariff as
determined by the Commission in this order to be effective after expiry of seven days of
the publication by the licensee under section 26(5) of the OER Act 1995.
|
6.45.9
|
In case the recommendations made by the Commission for necessary
correctives for determination of revenue requirement are accepted in toto by the
Government, the retail supply tariff as approved by OERC in order dated.19.01.2001 shall
continue unchanged after 31.07.2002.
|
6.45.10
|
Pursuant to order dated 19.04.2002 of the Honble High Court of
Orissa the order is not being notified to WESCO in terms of section 26(6) but is filed in
sealed cover in the Honble High Court of Orissa.
The application of M/s WESCO is disposed off accordingly.
Sd/-
(B.C. JENA)
M E M B E R
|
Sd/-
(H. SAHU)
M E M B E R
|
Sd/-
(D. C. SAHOO)
CHAIRMAN
|
|