7.0
|
REVENUE REQUIREMENT
|
7.1
|
CESCO submitted its revenue requirement for the year
2000-01 in September, 2000. The Commission has relied on the data &
information presented by CESCO as well as the facts and arguments put
forth by the objectors before it for analyzing the revenue requirement.
|
7.2
|
Quantum of Power Purchase
|
7.2.1
|
CESCO purchases power at different supply points from
GRIDCO for supply to consumers in its area of operation. The requirement
of power purchase is directly related to the quantum of energy sold to
the consumers and the transmission & distribution loss occurring in
the licensee’s system. While estimating energy sale for 2000-01, CESCO
has analysed the pattern of consumption of various groups of consumers
for the year 1998-99, 1999-00 and projected these figures for the
financial year 2000-01 in the format prescribed by OERC. According to
the analysis of energy sale mix between LT, HT & EHT consumers for
the FY 2000, LT consumption accounted for 66.92% while HT & EHT
accounted for 16.98% and 16.10% respectively.
The Commission in its query to the licensee pointed out that there
appeared to be no correlation between the growth projected for the year
2000-01 and that achieved during the year 1999-00. This point was also
raised by some of the objectors who stated that by projecting a higher
than expected growth rate in LT, the licensee was trying to project a
higher revenue requirement in the form of higher power purchase and show
a lower estimate of expected revenue due to low tariff rate of this
segment.
In case of LT category CESCO projected consumption basing on the actual
consumption from April 00-July 00 and prorating the same for eight
months. Further additional billings on account of the cyclone affected
consumers after restoration of power, the addition of new consumers and
the loss reduction activities were incorporated in the estimation.
In case of domestic consumers, growth of 18.53% in consumption was
recorded in the year 1999-00 over the previous year. CESCO
in OERC form No. T-1 has furnished information relating to the number of
consumers and their connected load and subsequently estimated the
consumption for the year 2000-01 which worked out to a rise of 13.27%
for the year 2000-01 compared to the year 1999-00.
It estimated a growth of 11.20% for commercial consumers.
In case of irrigation consumers CESCO estimated a rise of 17.32% taking
the growth in number of consumers and contract demand as submitted to
OERC in Form No. T-1.
In case of HT category of consumers the growth rate of 7.0% was
estimated for the year 2000-01 based on the trend of consumption from
April 00-July 00 and prorating the same for eight months. Besides
additional billed units gained due to commercial loss reduction
activities were also incorporated.
In respect of EHT category of consumers, CESCO presumed a growth rate of
15.33% for the FY 2000-01 based on the actual consumption from April to
August 2000 and considering intimation for change in contract demand or
energy off-take by the consumers.
|
7.2.2
|
The Commission analysed the consumption of various groups
of consumers and studied the consumption pattern of all HT & EHT
consumers. A detailed analysis of the billed units of the LT consumers
particularly of the domestic and commercial consumers without meters or
with defective meters was also carried out. Consumers with correct
meters are billed on the basis of actual meter reading whereas others
with defective meters or no meters at all are billed on the basis of
load factor. In he light of persistent public compliant regarding wrong
billing, non-installation of meters and poor commercial practices the
Commission doubts the accuracy of consumption figures projected by CESCO.
However these figures are accepted for the purpose of revenue
requirement for the year 2000-01 as furnished in OERC Form No.T-1.
|
7.2.3
|
Estimated level of consumption at various voltage level
are given in Table-3 for 2000-01.
Table - 3
Category
|
Consumption
|
LT
|
1528.22
|
HT
|
361.57
|
EHT
|
369.53
|
Total
|
2259.32
|
|
7.2.4
|
This shows an increase of about 13.52 % over the sale in
FY 1999-00 and the same was examined at the Commission’s end. A
comparative picture of the consumption of the previous two years along
with projection for 2000-01 as presented by the licensee in its filing
in September, 2000 is given in Table-4.
Table - 4
Consumption in MU
|
1198-99
|
1999-00
|
2000-01
|
LT
|
1160.96
|
1331.87
|
1528.22
|
HT
|
366.94
|
337.95
|
361.57
|
EHT
|
434.92
|
320.41
|
369.53
|
Total
|
1962.82
|
1990.24
|
2259.32
|
% Rise
|
-
|
1.42
|
13.52
|
CESCO has provided an analysis of the pattern of
consumption of the consumers covered under LT, HT & EHT categories
in para 2.3 of its RST application and details in OERC Form No. T-1.
The actual growth in consumption during 1999-00 is obviously stunted
due to ravages caused by super-cyclone.
|
7.3
|
Transmission & Distribution Loss
|
7.3.1
|
CESCO has estimated T&D loss at 42.66% for 2000-01. It
has stated that for the year 1999-00 the estimated loss figure was
45.68%.
|
7.3.2
|
CESCO’s estimation of the overall loss percentage at
42.66% does not include the loss at EHT which is being recovered by the
Transmission and Bulk Supply Licensee i.e. GRIDCO, through the Bulk
Supply Tariff. In effect, therefore, the end-use consumers as per CESCO’s
proposal would have to bear the EHT loss passed through in the BST in
addition to 42.66% loss proposed by CESCO.
Majority of the objectors were concerned about the reporting of very
high level of loss in the transmission and distribution system of the
licensee particularly after the privatisation which under SEB management
used to be recorded at lower level.
The authenticity of loss level projected by the licensee has not been
supported with verifiable data to ascertain the correctness of the
projection in the absence of metering in large number of consumer
premises. The pilot study to establish the loss level conducted in 1998
can not be treated as authentic today. The Commission’s suggestion to
conduct a fresh pilot study in order to establish commercial and
technical loss levels should have been completed. Such a study requires
100% metering for consumers connected to a selected number of
distribution transformers in selected feeders with mixed load.
If EHT sale is taken out from the total sale, then the distribution loss
as a percentage of HT and LT input works out to 47.07% for CESCO.
The objectors also pointed out that the loss was being computed taking
into account the zero loss EHT energy input into the system to arrive at
a smaller figure. Secondly, this figure was arbitrarily fixed and the
system data were manipulated to justify the same. Therefore, the loss
projection was entirely arbitrary and without any basis and hence should
not be accepted.
There were variations in the loss projections made by the objectors
though there was general suggestion to adopt overall loss level at 32%
including 3.5% towards transmission loss. The objectors were of
unanimous view that this high level of T&D loss had remained
uncontrolled during the past three years and should have been brought
down.
|
7.3.3
|
The Commission is very much concerned about the reported
high loss level in the system and the fact that there is no appreciable
decline in the level of loss. This has a serious bearing on the revenue
and finance of the licensee and hence the tariff.
The Commission, therefore, has the unenviable task of fixing a level of
loss in the absence of verifiable and reliable data and apply value
judgement that should be fair, reasonable, acceptable, achievable and
financially sound. Any arbitrariness on the part of the Commission will
either affect the financial viability of the licensee or unduly burden
the consumers.
It may be relevant to note that Orissa is not the only state having high
T&D loss. The T&D loss figures unveiled in some states like
Andhra Pradesh, Delhi, Haryana, Maharashtra and Uttar Pradesh were at
the levels of 52%, 55%, 36.6%, 32% and 36.5% respectively in the
immediate post-reform regime.
In fact it is this Commission which for the first time in India
identified and quantified the crucial importance of T&D loss level
and linked it to tariff fixation. T&D losses of more than 35% have
never been allowed by this Commission to be passed on in tariff in spite
of the reported losses at level as high as 47.31% (1997-98 audited
account). On the contrary, the level of benchmark adopted by OERC has
been perceived to be unrealistic and unacceptable by the World Bank
team, GRIDCO and the Distribution Companies. Even with the above
benchmark there will be substantial gap between revenue requirements of
licensees and anticipated revenue at the existing tariff rate.
The loss levels reported by the various distribution companies are given
in Table-5. This does not include losses in EHT transmission.
Table : 5
Distribution Loss (%)
Year
|
NESCO
|
WESCO
|
SOUTHCO
|
CESCO
|
1998-99 (as per filling)
|
45
|
44.8
|
43.2
|
48.64
|
1999-00 (as per filling)
|
43
|
44.1
|
41.8
|
45.68
|
2000-01 (target)
|
38
|
38
|
38
|
42.66
|
2001-02 (target)
|
35
|
35
|
35
|
NA
|
2002-03 (target)
|
32
|
32
|
32
|
NA
|
2003-04 (target)
|
30
|
30
|
30
|
NA
|
2004-05 (target)
|
28
|
28
|
28
|
NA
|
The Commission directed during the course of hearing
that the distribution licensees must now carry out pilot studies for
determination of technical and non-technical loss in their system for a
period of six months from April, 2001 to September, 2001 and submit the
same to the Commission after which the Commission will take a view on
loss reduction programme. The Commission intends to obtain a commitment
for an accelerated T&D loss reduction programme giving year-wise
targets for loss reduction till the year 2010. But this has to wait
until the pilot studies are made and reasonably reliable data base is
built. For the purpose of calculation of revenue requirement the
Commission has decided to adopt an overall loss level of 34% including
the losses in EHT transmission system which is around 3.7% for the year
2000-01. On this basis the distribution loss works out to 31.46%.
|
7.3.4
|
CESCO proposes to sale 2259.32 MU during 2000-01. GRIDCO’s
power purchase on account of supply to CESCO would be 3423.21 MU based
on the prescribed 34% of T&D loss. CESCO’s purchase from GRIDCO
would be limited to 3.7% (being the approved transmission loss in EHT)
less than what is purchased by GRIDCO for supply to CESCO. For the
purpose of revenue requirement and sale to its consumers, CESCO has to
purchase only 3296.55 MU during 2000-01. The system loss in CESCO works
out to 3296.55-2259.32 = 1037.23 MU. This loss expressed as a percentage
of input to the CESCO system is 31.46% and the same is allowed for the
purpose of revenue requirement of CESCO. The end use consumer has to pay
for 34% of T&D loss as approved by the Commission. The above
calculation is presented in Table-6.
Table: 6
|
2259.32 MU
|
Power to be purchased by GRIDCO for CESCO applying
a loss level of 34%
|
2259.32/0.66 = 3423.21 MU
|
Power to be purchased by CESCO from GRIDCO less
loss of 3.7% at EHT
|
3423.21X0.963= 3296.55MU
|
Energy loss in CESCO’s system
|
3296.55–2259.32 = 1037.23MU
|
Distribution loss of CESCO’s system
|
1037.23/3296.55 = 31.46%
|
|
7.4
|
Cost of Power
|
7.4.1
|
CESCO has to purchase 3296.55 MU from GRIDCO at the rate
of Rs.200/KVA/month + 99 paise/unit approved separately by the
Commission in BST Order dated 19.01.2001(Case No.27/2000). The
Commission has examined the power purchase bills of CESCO for April,
1999 to March, 2000. The bill details have been supplied by CESCO in
Evidential Document Vol-III of Retail Supply Tariff of 2000-01. The
average cost per unit of power purchased from GRIDCO for the months of
April, 1999 to March, 2000 is 126.37 paise/unit. The rate/unit payable
by CESCO under revised Bulk Supply tariff would be 138.24 paise/unit.
The cost of power @ 138.24 paise/unit for purchase of 3296.55 MU would,
therefore, be Rs.455.73 crores instead of Rs.527.98 crores asked by
CESCO at an average rate of 134 paise/unit.
|
7.4.2
|
Institution of Purchase Power Price Adjustment Clause (PPPAC).
Since the revised bulk supply tariff rate to be effective from
01.02.2001 has been considered for determination of cost of power for
CESCO the Commission does not consider it necessary to institute
Purchase Power Price Adjustment Clause (PPPAC) as requested by the
licensee.
|
7.5
|
Operating Expenses
|
7.5.1
|
The operating expenses for distribution and retail supply
may be considered under the following heads :-
Employees Cost
Administration & General Expenses
Repair and Maintenance Expenses
Less expenses capitalized
|
7.6
|
Employees Cost
|
7.6.1
|
Employees cost involves cost of manpower in service as
well terminal benefits to be payable to retiring persons including
pension.
|
7.6.2
|
CESCO has proposed Rs.99.98 crores for the FY 2000-01
towards Employees. This is far in excess of Rs.82.75 crores claimed and
allowed for 99-00. This cost includes a sum of Rs.0.35 crores towards
contribution to PF and Pension. CESCO has stated that increase in
employees cost projected for the FY 2000-01 is 5.95% (Para 4.2 of RTA)
above the provisional expenses for the FY 1999-00 (OERC Form No. F-21).
CESCO projects an estimated increase of 3% towards annual increment.
CESCO has also stated that the %age growth used for projecting the
Employee Costs is based on the growth arising purely because of the
inflation rate and also because of the rise in salary as a result of
annual increments. We find that for 99-00, the licensee has ignored the
limit of Rs.82.75 crores put by Commission which it itself had
projected. Based on excess expenditure of 99-00 the licensee has
projected Rs.99.98 crores for 2000-01 which obviously is excessive and
unjustified.
|
7.6.3
|
Since the audited actuals for the year 1999-00 are not
available the Commission considers it appropriate to take the approved
figures of the Commission for the year 1999-00 as base and allow 8%
increase to factor in increment and inflation. Accordingly, Rs.89.37
crores is considered appropriate for the purpose of employees expenses
instead of 99.98 crores as proposed by the licensee.
Expenses
|
Commission’s approval for 99-00
|
CESCO’s projection
00-01 |
Commission’s approval for 00-01
|
Employees Expenses
|
82.75
|
99.98
|
89.37
|
|
7.7
|
Administration & General Expenses
|
7.7.1
|
CESCO has proposed A&G expenses for the FY 2000-01 as
Rs.19.17 crores (Form F-23) in their original application and changed it
to 18.75 crores in subsequent submission (sequel to clarification to
queries). These expenses include expenses on communication, professional
charges, property related expenses, conveyance and travelling, training,
other expenses and material related expenses. The A&G expenses are
said to be based on actual expenses incurred during 1999-00 and budget
estimate for the year 2000-01.
|
7.7.2
|
The Commission has examined the Licensee’s proposal on
A&G Expenses. A&G expenses as per the information supplied by
CESCO in OERC Form No.F-23 for 1999-00 was Rs.9.44 crores. The
Commission in its last tariff order of 1999-00 approved Rs.6.28 crores
towards A&G expenses, considering the disaggregated audited figures
of 1997-98 as base and allowing 6% over it to factor in for inflation.
|
7.7.3
|
Objectors in general questioned the prudence of A&G
expenses being incurred by CESCO and wanted it to be cut down severely
and expressed concern about rising trend in A&G expenses. They
requested that this expenditure should be kept under control preferably
limiting to the percentage hike of about 6%.
|
7.7.4
|
While examining the details of A&G expenses it is
revealed that CESCO has proposed a sum of Rs.7 crores towards consulting
charges. Similarly, substantial provisions have been made towards
printing and stationary, bill generation and hiring of vehicles. In the
clarification to consumers queries, CESCO submitted that the use of
consultants have been made very judiciously by CESCO. Even in case of
preparation of asset register the licensee has decided to undertake the
activity on its own, thereby saving on the consultant’s fees. CESCO is
planning to spend Rs.2.5 crores towards outside management technical
support. Similarly, they also require Tariff Filing support from outside
agencies for which the outlay of Rs.50 lakhs has been earmarked. They
have reported to have spent Rs.30 lakhs for tariff filing of FY 2000,
the amount they intend to pass on in tariff in the year 2000-01. It is
strange that CESCO spent Rs.50.00 lakhs towards tariff filing when the
entire guideline for tariff filing was circulated by OERC. In spite of
that the filing of CESCO had to change number of times to meet the
Commission’s filing requirement. Thus expenditure on this account is
excessive and unjustified.
|
7.7.5
|
So far hiring charges of vehicle is concerned, CESCO
explained that they have deployed vehicles for collection activities
which improves their revenue position. It is stated that CESCO had been
saddled with massive corruption from earlier period. It has taken a
drive to weed out corruption and streamline the same for which they have
made a provision of Rs.75 lakhs under consultant’s charges.
|
7.7.6
|
During course of the hearing many objectors were of the
opinion that the justifications given by the licensee towards increase
in A&G expenses are not reasonable and cannot be considered prudent
enough to be passed on to consumers. Harsh observations were given on
huge expenses on consultants and outside management support. The
licensee should have taken note of the Commission’s observations in
the last tariff order that the licensee should enhance the expertise of
the employees and upgrade their level of skill instead of engaging
consultants with excessive fees to burden the consumers.
|
7.7.7
|
The Commission observes that the licensee should observe
due diligence in spending money towards A&G expenses. The Commission
considers it reasonable to allow an annual increase of 8% over the
approved figure of 1999-00 to factor in inflation excluding licence
fees. Over and above the figure, an amount of Rs.0.50 crores is allowed
for licence fees and Rs.0.50 crores is allowed towards expenses to be
incurred for billing and collection improvement. Thus total A&G
expenses are approved at Rs.7.78 crores as against amount of Rs.18.75
crores proposed by licensee.
Sl. No.
|
Particulars |
Rs. in Crores
|
1
|
A&G expenses approved in 1999-00 order
|
6.28
|
2
|
Add 8% increase over Sl.1
|
0.50
|
3
|
Add license fee
|
0.50
|
4
|
Add billing and collection improvement expenses
|
0.50
|
|
Total
|
7.78
|
|
7.8
|
Repair and Maintenance Expenses
|
7.8.1
|
The R&M expenses proposed by CESCO is Rs.19.88 crores
for the FY 2000-01. This estimate is stated to be based on 5.4% of Gross
Fixed Asset at the beginning of the year. The licensee had been allowed
an amount of Rs.19.05 crores in tariff order 1999-00 towards Repair and
Maintenance Expenses.
|
7.8.2
|
While answering the query raised by the Commission
regarding application of lower provision for repair and maintenance for
new assets replaced due to super cyclone, CESCO clarified that they have
inherited ageing and aged assets from GRIDCO which would require
substantial R&M. The cyclone too has caused the R&M expenses to
go up considerably. The expenses shown under R&M by the licensee are
purely for the purpose of repair carried on the licensees fixed asset in
order to add revenue earning live to the asset. In fact the actual
R&M expenditure is much more than what has been claimed.
|
7.8.3
|
The Commission examined the licensee’s proposal on
R&M expenses and considers it reasonable to allow 5.4% of gross
fixed asset as at the beginning of the year 2000-01. Fixed asset
position as at the beginning of the year has undergone a change due to
replacement of asset on account of super cyclone and hence the
Commission recalculates the same and arrives a figure of Rs.362.49
crores (Table-13) as on 31st March, 2000. Accordingly, taking 5.4% of
the gross fixed asset as at the beginning of the year, the R&M
expenses for the FY 2000-01 is approved at Rs.19.57 crores.
|
7.9
|
Interest on Loan
|
7.9.1
|
CESCO proposed an interest amount of Rs.20.95 crores to be
charged to revenue. CESCO stated in their application that the interest
burden charged to revenue has decreased in view of the repayments
proposed to be made on the Gridco Loan in the ensuing Year FY-01 (Para
4.7.1 of the RST). Interest on various loans availed from various
lending agencies as reported by CESCO is given in Table-9. The table
also include Commission’s approved figure for the year FY-00 taken
from the tariff order for CESCO dt.30.12.99.
Table : 9
( Rs in Crores)
Lender/Source
|
FY 2000
|
Commission’s Approval FY 2000
|
FY 2001
|
Loan Agreement with GRIDCO
|
21.93
|
25.70
|
19.15
|
Working Capital Loan from Banks
|
0.00
|
0.00
|
1.80
|
Total
|
21.93
|
25.70
|
20.95
|
The interest to be paid for the VRS loan has not been
considered for the purpose of the calculation of the Revenue Requirement
of the licensee for the FY 01. The benefits accruing to the licensee
from the exercise of the VRS should be sufficient to service the debt
being proposed to be availed for the VRS. |
7.9.3
|
Out of Rs.20.95 crores to be passed on to Revenue,
Rs.19.15 crores is payable to GRIDCO covered under subsidiary loans
agreement and Rs.1.80 crores towards working capital loans. Interest on
other loans like IBRD (PMU), IBRD (Metering). IBRD (Cyclone) etc. have
been capitalised as shown in Table-10. No penal interest has been
included in the revenue requirement.
|
7.9.4
|
The Commission accepts Rs.20.95 crores to be included in
the Revenue Requirement for the year 2000-01 towards interest expenses.
|
7.9.5
|
INTEREST TO BE CAPITALISED
CESCO proposed an amount of Rs.15.01 crores as interest during
construction to be capitalised for the year 2000-01 as in Table : 27 of
their application of Sept., 2000. The correct total is Rs.14.95 crores.
The loans from various sources as approved by the Commission for FY
99-00, actual expenditure in 99-00 and proposal for the 2000-01 are
given in Table-10.
Table : 10
(Rs. in Crores)
Sources/purpose Of Loan |
Approved by The Commission for 99-00 |
Actuals (as per CESCO’s filing) for 99-00 |
Proposal for the year 2000-01
|
IBRD(PMU)
|
28.89
|
11.13
|
40.12
|
Cyclone damage
|
0
|
35.28
|
35.50
|
RE Works
|
14.92
|
7.27
|
0
|
Metering
|
0
|
0
|
3.78
|
Others
|
0
|
2.06
|
0.75
|
Total
|
43.81
|
55.74
|
80.15
|
|
7.9.6
|
For the year 2000-01 as indicated in table above there is
an estimated receipt of Rs.40.12 crores against PMU works. The
Commission does not find much justification in the licensee’s
projection of Rs.40.12 crores when its actual performance of pervious
year is at the level of Rs.11.13 crores only. The Commission limits the
expenditure to the extent of Rs.11.13 crores against PMU and accordingly
loan and the interest liabilities are adjusted. Similarly, loan for
restoration of cyclone damage has been restricted to Commission’s
approval of Rs.51.35 crores due to which the interest during
construction gets reduced from Rs.14.95 crores to Rs.12.43 crores as
given in the Table-11.
Table : 11
|
LOAN |
INTEREST |
Lender/Source
|
CESCO’s Projection
|
OERC approval
|
CESCO’s Projection
|
OERC approval
|
IBRD Loan for System Improvement
|
106.47
|
77.38
|
11.23
|
9.34
|
PFC Cyclone Rehabilitation
|
30.00
|
13.35
|
1.13
|
0.50
|
IBRD Cyclone Rehabilitation
|
38.00
|
38.00
|
2.47
|
2.47
|
IBRD Metering
|
3.78
|
3.78 |
0.12
|
0.12
|
Total
|
|
|
14.95
|
12.43
|
|
7.9.7
|
Hence Commission approves Rs.12.43 crores to be
capitalised for the year 2000-01.
|
7.10
|
Depreciation
|
7.10.1
|
CESCO has proposed depreciation of Rs.26.87 crores on an
asset base of Rs.368.23 crores as on 31.3.2000 in their submission
dtd.02.11.2000. This figure has undergone change during the filing and
clarifications. CESCO has adopted for calculating depreciation the
straight-line method as per the rates notified by Ministry of Power,
Govt. of India from time to time.
|
7.10.2
|
The provision of depreciation was raised by many of the
objectors during the course of the hearing as already reported elsewhere
in this order. Shri R.P. Mohapatra, Retd. Member, OSEB had stated that
depreciation should be calculated on the basis of notification Ministry
of Power, Govt. of India dtd. March, 1994. He also stated that asset
being second hand the rate of depreciation has to be determined by the
competent Govt. in each case “having regard to the nature, age and
condition of the assets at the time acquisition”. He had also made a
point that in case of 30-40% of the total assets procured by OSEB
depreciation upto 90% of asset value must have been recovered on which
no depreciation should be charged. He also raised the issue of
maintenance of fixed asset register and submitted that depreciation on
any asset should not exceed 90% of the original cost of asset.
Shri B.N. Das had given some general and strategic suggestion on behalf
of UCCI for tariff fixation. His suggestion is that correct calculation
of depreciation as per Govt. of India’s circular should be made after
dividing the assets into blocks at the time of revision of percentage of
depreciation, if it is not possible for OERC to deviate from Govt. of
India norms. Depreciation already collected and balance to be collected
for each block of assets should be exhibited in registers by GRIDCO and
DISTCOs within a time frame to be fixed by OERC.
|
7.10.3
|
The Commission has asked for Fixed Assets Registers and
has called for reports on physical verification of Fixed Assets. Without
Fixed Assets Registers and physical verification report, depreciation
cannot be calculated correctly. Beside statutory accounting
requirements, it is to be seen that the consumers are charged for the
assets which are used and useful to them.
|
7.10.4
|
In reply CESCO mentioned that building up an Asset
Register in a massive exercise as no records were maintained by its
predecessor (GRIDCO). However, the licensee has decided to deploy a
dedicated team of experienced professionals from among its own resources
for building Asset Register.
|
7.10.5
|
While calculating depreciation, CESCO has withdrawn assets
value of Rs.29 crores damaged due to super cyclone. The Commission in
its Order dtd.19.04.2000 estimated the value of the damaged assets as
Rs.34.74 crores which has been withdrawn from the gross fixed assets to
find out the balance as on 31.03.2000 for the purpose of depreciation
calculation. The balance of gross fixed assets is recalculated to
Rs.362.49 crores as on 31.03.2000 the details of which has been
indicated in Table-13.
The detail calculation of depreciation is given in Table-12
Table : 12
Calculation of Depreciation
Category of Assets
|
Asset position as on 31.3.2000
|
Rate of Depreciation
|
Amount of Depreciation
|
Land
|
6.70
|
0
|
0
|
Building
|
8.56
|
3.02%
|
0.26
|
Network Asset
|
302.73
|
7.84%
|
23.74
|
Over head lines
|
43.47
|
5.27%
|
2.29
|
Furniture & fixtures
|
0.27
|
12.77%
|
0.03
|
Vehicles
|
0.01
|
33.40%
|
0
|
Others
|
0.75
|
12.77%
|
0.10
|
Total
|
362.49
|
|
26.42
|
The Commission accordingly, approves an amount of Rs.26.42 crores for
depreciation for the FY 2000-01. |
7.11
|
Bad and Doubtful Debt
|
7.11.1
|
CESCO in OERC Form No. F-17 has stated that the provision
for Bad & Doubtful Debt for the year 1999-00 and 2000-01 would be
Rs.23.63 crores and Rs.22.98 crores, respectively.
|
7.11.2
|
Clarifying to the consumers queries raised against the
tariff filing, CESCO stated that the provision for bad and doubtful debt
has been calculated as per the norms fixed by the Commission i.e.15% on
a receivable base of two months of revenue. CESCO also stated that it
would improve its collection efficiency over earlier years. CESCO
mentioned in their clarification that the bad debt of the licensee would
be much more than the amount claimed.
|
7.11.3
|
Many of the objectors have questioned the provision of
Rs.22.98 crores as bad debt which is prima facie excessive.
|
7.11.4
|
The Commission examined the proposal submitted by the
licensee and analysed the suggestions and objections raised by the
objectors during the hearing. It is constrained to note the inefficiency
of the licensee in sending correct and adequate bills and in realisation
of its dues. But the Commission is looking at the reality of the
situation and as approved in the last tariff order considers 2.5% of the
gross sales to be assumed as bad debt for being charged to revenue. On
this basis, the Commission approves Rs.15.59 crores as Bad &
Doubtful Debt allowed for recovery through tariff.
|
7.12
|
Loss due to damaged assets
CESCO proposes Rs.21.66 crores to be recovered from the consumers
through tariff towards cost of assets damaged due to super cyclone.
CESCO has written off Rs.29 crores for loss due to cyclone out of which
it intends to pass on Rs.21.66 crores to consumer this year and balance
of Rs.7.34 crores in the next year.
|
7.12.1
|
The Commission has carefully examined the facts. It is
viewed that the earlier order of the Commission vide No.OERC/Engg/76/99/649
dt.19.04.2000 in regards to “restoration of damage due to super
cyclone, should be strictly adhered to. The Commission had also approved
that the total expenditure required for restoration of system damaged by
super-cyclone be divided into two parts - Capital and Revenue
Expenditure. The licensee shall spend Rs.51.35 crores towards
replacement of old damaged assets and shall be capitalised to form a
part of the asset base. At the same time cost of the damaged assets
worth Rs.34.74 crores shall be taken out from the asset base to ensure
that consumers are not charged for the assets which are “not in use
or useful”. In other words, consumers have to pay for the
additional burden of assets for Rs.16.61 crores (i.e. Rs.51.35 -
Rs.34.74 crores) due to super-cyclone.
|
7.12.2
|
Cost of damaged asset is not an item of expenditure as
prescribed in the Sixth Schedule to the Electricity Supply Act, 1948.
Abnormal financial loss occurred other than the provisions of the
Electricity Supply Act cannot be passed on to tariff, but can be
adjusted against annual profit and loss accounts of the company. Annual
financial loss, if any, after adjustment is carried forward and
appropriated against the profit in the year when clear profit is excess
of Reasonable Return. Hence the Commission disapproves the claim and
does not allow to pass on Rs.21.66 crores to consumers.
|
7.13
|
Contribution to Contingency Reserve
|
7.13.1
|
CESCO has not proposed anything on special appropriation
towards contribution to contingency reserve as required under Para-IV of
Sixth Schedule to the Act, 1948.
|
7.14
|
Carry Forward of Past Losses
Under Special Appropriation, CESCO proposes Rs.13.77 crores towards
previous losses to be passed on to tariff. CESCO in their clarification
dated 12.12.2000 stated that it has not claimed any amount on account of
previous losses in its tariff application. The figure of Rs.13.77 crores
shown against previous losses shown in forms F-12 and F-13 of the main
application, volume II, is in fact the amount of Rs.1.48 crores
disallowed by the Commission in the last tariff order and the
differential bulk supply tariff which has not been effective and is sub-judice.
|
7.14.1
|
The Commission has gone through the details and is of the
opinion that the licensee has not adhered to the norms and performance
benchmark fixed by the Commission in the last tariff orders. Further,
audited accounts of the licensee for the year 1998-99 and 1999-00 have
not been submitted for assessment of actual loss. Hence loss incurred by
the licensee cannot be allowed to be passed on to consumers in this
tariff.
|
7.14.2
|
However, the Commission recognises that any loss incurred
by the licensee within the performance benchmark and expenditure limit
fixed by the Commission, after verification of prudence and
reasonableness, can be considered as carry forward for adjustment in
future tariff.
|
7.15
|
Other Special Appropriation as approved by the State
Govt.
|
7.15.1
|
CESCO proposes Rs.1.41 crores as other special
appropriation to be passed on to tariff in the FY 2000-01. On
examination it is revealed that the licensee has claimed 0.5% of the
loan balance as on 31st March, 2001 complying to the provisions of the
Sixth Schedule to the Act, 1948. As per the provisions of the Sixth
Schedule, 0.5% is of the loan is taken as part of the reasonable return
and being considered separately while calculating reasonable return.
|
7.16
|
Capital Base
|
7.16.1
|
Original Cost of Fixed Assets
CESCO had projected its original cost of fixed assets at Rs.475.71
crores in their Tariff Application of 04.10.2000 which has been
subsequently changed to Rs.446.71 crores (sequel to the clarification to
queries to RTA). CESCO, in their clarification, stated that they have
computed the amount of assets as per the Commission’s guidelines and
reduce the gross block of asset by Rs.29 crores in the current year (FY
99-00) based on the depreciated value of assets as that is to be written
off from the assets and charged to the profit and loss accounts (OERC
Form F-35).
|
7.16.2
|
This has been examined with reference to information
submitted by CESCO and Commission’s Order served vide letter No.
OERC-Engg-76/99/649 dtd.19.4.2000. The Commission in its aforesaid
letter has decided that Rs.34.74 crores worth of asset value have to be
written off as “assets damaged in the super-cyclone”. The Commission
after due examination had permitted a capital expenditure of Rs.51.35
crores as capital expenditure for works damaged due to cyclone. CESCO
has projected in their filing a sum of Rs.70.78 crores against
investment in cyclone damaged works.
|
7.16.3
|
While clarifying the Commission’s queries raised during
the public hearing CESCO clarified that the licensee was under
considerable pressure to immediately restore power supply to all areas
that were left in the dark in the wake of the cyclone. The initial
reports on the damages caused by the cyclone put the losses at Rs.129
crores. The Commission went on to approve a figure which is around 50%
of the actual costs. Most of the materials were ordered before the Hon’ble
Commission had passed its directive on the limit of these expenses.
Hence, the actual expenditure incurred in this process was far more than
the limit sanctioned by the Commission. Also, the licensee had already
incurred these expenses by the time the Commission gave its directive.
Hence, the licensee humbly requests the Commission to allow these
expenses based on the actual figures and kindly re-consider the limit of
Rs.51.35 crores allowed by the Commission. The licensee humbly prays
that the Commission allow the licensee the actual costs incurred.
|
7.16.4
|
The Commission during the hearing rejected the application
of the licensee towards excess investment in respect of cyclone damage
over and above the limit fixed by the Commission in its order
dtd.19.4.2000. Moreover the licensee has not informed/filed any
application for approval of excess investment as referred above with the
Commission. Thus the Commission is of the opinion that the gross fixed
assets and capital work in progress are to be calculated as per the
Commission’s order dtd.19.4.2000. Accordingly Rs.34.74 crores of asset
value has been withdrawn from the asset base of 31.3.2000 and capital
investment towards restoration of cyclone damage has been limited to
Rs.51.35 crores instead of Rs.70.78 crores.
|
7.16.5
|
As stated in para 7.22.2 capital investment and under PMU
has been limited to Rs.11.13 crores funded by World Bank. This will
limit gross value of network asset at Rs.318.88 crores as against
Rs.365.24 crores claimed by the licensee. The detail calculation of
gross fixed asset as proposed by licensee and approved by the Commission
is given in Table-13.
Table : 13
CESCO’s proposal on gross fixed asset
Particulars
|
Asset as on 31.3.99
|
Addition during 99-00 |
Deletion during 99-00 |
Closing balance as on
31.3.00
|
Addition during 00-01
|
Closing balance as on
31.3.01
|
Land
|
6.70
|
0.00
|
0.00
|
6.70
|
0.00
|
6.70
|
Buildings
|
8.56
|
0.00
|
0.00
|
8.56
|
0.00
|
8.56
|
Network Assets
|
315.22
|
22.25
|
29.00
|
308.47
|
56.78
|
365.24
|
Overhead lines
|
21.36
|
22.11
|
0.00
|
43.47
|
21.35
|
64.82
|
Furniture & fixtures
|
0.21
|
0.06
|
0.00
|
0.27
|
0.18
|
0.45
|
Vehicle
|
0.01
|
0.00
|
0.00
|
0.01
|
0.00
|
0.01
|
Other equip.
|
0.69
|
0.06
|
0.00
|
0.75
|
0.17
|
0.93
|
Total
|
352.75
|
44.48
|
29.00
|
368.23
|
78.48
|
446.71
|
Commission’s approval on gross fixed asset
Particulars
|
Asset as on 31.3.99
|
Addition during 99-00 |
Deletion during 99-00 |
Closing balance as on
31.3.00
|
Addition during 00-01
|
Closing balance as on
31.3.01
|
Land
|
6.70
|
0.00
|
0.00
|
6.70
|
0.00
|
6.70
|
Buildings
|
8.56
|
0.00
|
0.00
|
8.56
|
0.00
|
8.56
|
Network Assets
|
315.22
|
22.25
|
34.74
|
302.73
|
16.15
|
318.88
|
Overhead lines
|
21.36
|
22.11
|
0.00
|
43.47
|
11.96
|
55.43
|
Furniture & fixtures
|
0.21
|
0.06
|
0.00
|
0.27
|
0.18
|
0.45
|
Vehicle
|
0.01
|
0.00
|
0.00
|
0.01
|
0.00
|
0.01
|
Other equip.
|
0.69
|
0.06
|
0.00
|
0.75
|
0.17
|
0.92
|
Total
|
352.75
|
44.48
|
34.74
|
362.49
|
28.46
|
390.95
|
Accordingly, original cost of fixed assets on
31.3.2000 and 31.3.2001 as Rs.362.49 crores and Rs.390.95 crores
respectively are considered reasonable by the Commission.
|
7.17
|
Receipts against Consumers Contribution
|
7.17.1
|
Capital contribution from consumers of Rs.74.81
crores as on 31.3.2001 has been deducted by the licensee from fixed
asset for calculation of capital base. This is accepted by the
Commission for calculation of capital base for the year 2000-01.
|
7.18
|
Original cost of Work In Progress
|
7.18.1
|
For the purpose of Capital Base calculation, CESCO
has projected Rs.99.57 crores towards original cost of work in progress
as on 31.3.2001. The comparative position of capital expenditure during
the year 1999-00 and proposed during 2000-01 is given in the Table-14.
Table : 14
(Rs. in crores)
Particulars |
Closing balance of WIP as on 31.3.00 |
Closing balance of WIP as on 31.3.01 |
System Improvement (IBRD) |
37.06 |
95.36 |
Other T&D |
2.92 |
1.59 |
Sub-Total |
39.98 |
96.95 |
Special T&D of REC |
0.16 |
0.08 |
R.E.C. (S.I. Scheme) |
0.15 |
0.02 |
R.E./L.I. Scheme |
0.99 |
0.49 |
R.E.C. (Normal) |
3.94 |
1.97 |
Harijan Bastee in R.E.C. |
0.15 |
0.07 |
R.E.C. (M.N.P.) |
0.20 |
0.10 |
R.E.C. (S.P.A.) |
0.55 |
0.28 |
Restoration of super cyclone damage |
0.27 |
0.00 |
Sub-Total |
6.41 |
3.01 |
Total |
46.39 |
99.96 |
|
7.18.2
|
The expenditure of Rs.9.42 (6.41 + 3.01) crores shown
against R.E. works in the above table should not be taken into
consideration in CWIP as the Commission has recommended the Govt. to
provide grant in aid/capital subsidy to the licensee the entire capital
expenditure incurred during 1999-00. The Commission has also recommended
that the licensee shall not claim any subsidy from State Govt. for
future years. This will obviate the necessity from the annual revenue
subsidy payment by govt. from year to year. It was also stated that the
assets created out of the grant-in-aid will not be considered for the
purpose of capital base and hence not earned any return. Any revenue
loss for undertaking such un-remunerative R.E. work shall be subsidised
by general pool of consumers. Same approach will also be applied for R.E.
works for the year 2000-01. Accordingly, for the purpose of calculation
of capital base Rs.6.41 crores and Rs.3.01 crores totaling to Rs.9.42
crores will be taken out from CWIP. CWIP as on 31.3.99 was Rs.20.75
crores. The total CWIP as on 31.3.2001 will be Rs.52.72 crores excluding
Rs.9.42 crores for R.E. works. The calculation is in Table-15.
Table : 15
CWIP as on 31.3.99 |
Rs.20.75 crores |
Expenditure for 1999-00 |
Rs.55.75 crores |
IDC for 1999-00 |
Rs.14.26 crores |
Sub-total |
Rs.90.76 crores |
Less transferred to fixed asset |
Rs.44.47 crores |
Balance as on 31.3.2000 |
Rs.46.29 crores |
Capital expenditure 2000-01 |
Rs.31.88 crores |
IDC for 2000-01 |
Rs.12.43 crores |
Sub-total |
Rs.90.60 crores |
Less transferred to fixed asset |
Rs.28.46 crores |
Balance as 31.3.2001 |
Rs.62.14 crores |
Less R.E. works |
Rs.9.42 crores |
Total |
Rs.52.72 crores |
|
7.18.3
|
This figure of Rs.52.72 crores will be considered for
calculation of capital base. The licensee proposes huge expenditure
without corresponding load growth which will bring a burden to the
consumers of the State unless there is reduction in transmission and
distribution loss. The licensee is also showing an expenditure of
Rs.19.96 crores on metering alone during 1999-00 and 2000-01. This
itself should bring about perceptible improvement in reduction in
commercial losses, improved billing and revenue to the licensee. It is,
therefore, necessary that a higher targeted level of loss reduction
should be aimed by the licensee.
|
7.19
|
Compulsory Investment under Para IV
|
7.19.1
|
In OERC Form No. F-33 CESCO has shown balance of
contingency reserve as on 01.4.01 as Rs.1.32 crores whereas in the
revised capital base (Form F-14) filed with the Commission CESCO has
proposed Rs.1.18 crores towards investment compulsory made under para IV
of Sixth Schedule to the Act, 1948. But no documentary evidence has been
produced to the Commission towards compulsory investment. As such the
Commission does not consider it necessary to take this Rs.1.18 crores
for the purpose of capital base for FY 2000-01.
|
7.20
|
Working Capital
|
7.20.1
|
Average cost of stores
|
7.20.1.1
|
According to para XVII(e)(i) of the Sixth Schedule of the
Act, 1948, a sum equal to of one-twelfth of the sum of book cost of
stores, materials and supplies including fuel on hand at the end of each
month of the year of account should be taken into account as working
capital for calculating the capital base. CESCO has proposed Rs.29.95
crores on this head.
|
7.20.1.2
|
The Commission examined the proposal of CESCO. A stock of
three months’ consumption of materials at any particular point of time
can be considered reasonable. Accordingly the Commission approves
one-forth of the total annual consumption of materials i.e. Rs.4.89
crores as reasonable for the purpose of working capital for stores to be
included in the capital base.
|
7.20.2
|
Average Cash and Bank Balance
|
7.20.2.1
|
CESCO has proposed Rs.23.96 crores for the FY 2000-01
computed on the basis of the provisions laid down in Sixth Schedule of
the Act, 1948. CESCO in form F-19 has given the provision of monthly
cash balance from April, 99 to March, 2000 and projection from April,
2000 to March, 01. As stated in para XVII(1)(e)(ii) of the Sixth
Schedule of the Act, 1948, an amount equal to 1/12 of the sum of cash
& bank balances and call and short term deposits at the end of each
month of the year of account, not exceeding the sum specified therein
can be included in capital base.
|
7.20.2.2
|
The Commission feels that liquid funds are needed for the
payment of Employees' Cost and Administrative & General Expenses
pending collection of receivables from the consumers. The normative lead
time between the supply of electricity to the consumers and collection
of tariff is considered two months. Hence, the fund requirement for two
months payment of Employees’ Cost and Administrative & General
Expenses would be appropriate for meeting working capital requirement in
the form of cash and bank balance. Calculated on the aforesaid basis,
the amount works out to Rs.16.19 crores. The Commission, therefore,
approves a sum of Rs.16.19 crores as cash and bank balance for meeting
working capital requirements.
|
7.21
|
Accumulated Depreciation
|
7.21.1
|
CESCO had proposed a sum of Rs.104.87 crores towards
amounts written off or set aside on account of depreciation in their
original application and revised the amount to Rs.102.60 crores in the
sequel to clarification to queries on 02.11.2000. The amount is reduced
due to withdrawal of assets damaged on account of super-cyclone. The
Commission accepts the amount as proposed by CESCO with a minor
variation and approves Rs.102.15 crores towards accumulated depreciation
to be deducted for the purpose of calculation of capital base.
|
7.22
|
Loans and Bonds
|
7.22.1
|
CESCO has deducted Rs.282.01 crores towards loans and
bonds in computation of capital base. CESCO has stated that the loans
and bonds for its distribution and retail supply business as per the
transfer scheme notification for the period ending 31.3.99 amounted to
Rs.216.57 crores (Form No. F-3). Loan received during 1999-00 and the
projection to be received during 2000-01 are Rs.158.52 crores and
Rs.188.42 crores respectively. Information on receipt/repayment of loan
as submitted by CESCO in OERC form No. F-3 is reproduced in Table-16.
Table : 16
(Rs. in Crores)
Source |
Opening balance as on 1.4.99 |
Received during 99-00 |
Repayment during 99-00 |
Balance as on 31.3.00 |
Expected received during 00-01 |
Expected repayment during 00-01 |
Expected balance as on 31.3.01 |
Gridco |
161.26 |
0.00 |
17.80 |
143.46 |
1.00 |
39.70 |
103.76 |
World Bank(PMU) |
55.31 |
11.04 |
0.00 |
66.35 |
40.12 |
0.00 |
106.47 |
W.B. (Metering) |
|
|
|
|
3.78 |
|
3.78 |
W.B. (Cyclone) |
|
|
|
|
38.00 |
|
38.00 |
PFC (Cycone) |
|
|
|
|
30.00 |
|
30.00 |
Gridco (Power purchase) |
|
147.48 |
|
147.48 |
26.52 |
|
174.00 |
VRS Loan |
0.00 |
0.00 |
0.00 |
0.00 |
50.00 |
0.00 |
50.00 |
Total |
216.57 |
158.52 |
17.80 |
357.29 |
188.42 |
39.70 |
506.00 |
|
7.22.2
|
The Commission examined the loans and bonds statement as
submitted in Forms F-3 and and F-27. As stated in para 7.9.6 IBRD loan
for system improvement has been limited to Rs.11.13 crores based on last
year’s performance. Similarly, loans proposed for restoration of
cyclone damage has been limited to Rs.51.35 crores. Regarding working
capital loan of Rs.174 crores CESCO clarified that according to bulk
supply agreement with GRIDCO this amount shall be repaid in twelve equal
quarterly instalment with interest at such rates as is approved and
allowed by the Commission. The licensee has not claimed any interest in
the current application. Hence this loan should not be considered for
the purpose of calculation of capital base. The licensee also has not
claimed the interest of VRS loan in the revenue requirement for the year
2000-01.
|
7.22.3
|
As the interest on working capital loan of Rs.174 crores
and VRS loan of Rs.50 crores has not been included in the revenue
requirement and these loans are not utilised for the purpose of creation
of capital assets, the Commission does not find it prudent and
reasonable to include in the loans and bonds to be deducted for the
purpose of calculation of capital base. The loans and bonds to be
deducted from the capital base is approved for Rs.236.27 crores as
detailed in Table-17.
Table : 17
Loans approved by the Commission
(Rs. in crores)
Source |
Balance |
GRIDCO |
103.76 |
IBRD System Improvement |
77.38 |
IBRD Metering |
3.78 |
IBRD Cyclone |
38.00 |
PFC Cyclone |
13.35 |
Total |
236.27 |
|
7.23
|
Consumers’ Security Deposit
|
7.23.1
|
CESCO while calculating the capital base as on 31.3.2001
has deducted a sum of Rs.28.83 crores deposited with the licensee by way
of security as required under para XVII(1)(iii) Sixth Schedule to the
Act, 1948. The amount is accepted as deduction for calculation of
capital base.
|
7.23.2
|
Based on the forgoing observations, the Commission finds
that Capital Base for 2000-01 for the purpose of Sixth Schedule has to
be taken at Rs.22.70 crores (vide Annex to this order) as against
Rs.113.53 crores proposed by CESCO.
|
7.24
|
Reasonable Return
|
7.24.1
|
CESCO has calculated the reasonable return by multiplying
the standard rate of 16% to the Capital Base of Rs.113.53 crores to the
tune of Rs.18.17 crores. We are unable to accept this figure as we have
not approved the base figure of capital base. As the capital base of the
licensee has changed to Rs.22.70 crores reasonable return by applying
standard rate of 13% is calculated at Rs.2.95 crores. In addition to
above 0.5% on the approved loans of Rs.236.17 crores amounting Rs.1.18
crores is approved as per the provisions of the Act, 1948. The
calculation of reasonable return is given in Table-18.
Table : 18
(Rs. in crores)
Source |
Proposed by CESCO |
Commission’s Calculation |
Capital base |
113.53 |
22.70 |
Reasonable return 16% on investment made after
31.3.2000 Reasonable return @ 13% |
18.17 |
0.00
2.95 |
0.5% of loan outstanding as at the end of year
2000-01 |
0.00 |
1.18 |
Total |
8.17 |
4.13 |
|
7.25
|
Miscellaneous Receipt
The licensee has proposed an amount of Rs.18.89 crores receivable
towards miscellaneous receipt for the year 2000-01. This amount is
considered reasonable and accepted.
|
7.26
|
Revenue
Requirement, Reasonable Return and Clear Profit
|
7.26.1
|
In the light of above decisions and calculation, the
Commission approves expenditure for the purpose of revenue requirement
for the year 2000-01 at Rs.635.42 crores as against Rs.759.47 crores
proposed by CESCO. Commission has disallowed previous losses of Rs.13.77
crores and other special appropriation of Rs.1.41 crores claimed by
CESCO under special appropriation. Reasonable return has been approved
in para 7.24.1 at Rs.4.13 crores against Rs.18.17 crores proposed by
CESCO. The calculation of expenditure for revenue requirement,
reasonable return and clear profit as approved have been reflected in
Annexe A, B &
C respectively.
|
7.26.2
|
The total revenue requirement of CESCO including special
appropriation and reasonable return has been reduced by Rs.153.27 crores
from Rs.792.82 crores proposed by the Licensee, to Rs.639.55 crores.
|
7.26.3
|
The licensee will end up with an excess of clear profit
over reasonable return by Rs.2.92 crores, if the tariff would have been
in operation for a period of twelve months. As the tariff will be
effective for a period of two months only during the current financial
year, the deficit at the assumed level of Transmission and Distribution
loss will be Rs.51.04 crores which will be allowed as a pass through in
the tariff for the FY 2001-02.
|