4.0
|
OBJECTIONS DURING HEARING The Commission admitted
fifteen objections for personal hearing. Some of the objections were of general nature and
others were specific to the tariff filing of 2000-01. Summary of these objections based on
issues raised are presented below. |
4.1
|
Effective date for implementation of the tariff proposal. Some
of the objectors, like Shri R.P. Mohapatra of Jayadev Vihar, have suggested that the
tariff proposal should be effective from 1st April 2001. This will have the following
advantages over the other timings followed by OERC :
Audited accounts of the previous year will be available before the
tariff for the ensuing year is determined.
The reservoir levels of the hydro power stations at the beginning of
the storage season (1st November) will be known enabling a more accurate prediction of
hydro power availability.
The tariff shall be available for a full financial year.
|
4.2
|
Necessity for a Pilot Study Pilot studies should be
undertaken in selected urban and rural feeders in each DISTCO to determine actual
technical and commercial losses. |
4.3
|
Cost of Employees, material cost, A&G expenses Many
of the objectors have pointed out that the cost of employees, material cost, A&G
expenses are quite high. They need to be pruned as per OERC norms and fixed at 6% higher
over the corresponding figures approved by OERC for 1999-2000. |
4.4
|
High Transmission and Distribution Losses Almost all
the objectors strongly objected to high T&D loss assumed by the NESCO for calculating
its revenue requirement. It was pointed out by the objectors that, the estimation of loss
is not accurate as most of the meters are either defective or non-existent. Therefore OERC
should not allow the total loss to exceed 32% out of which 3.5% should be EHT loss and
28.5% should be distribution loss. Unfortunately the quantum of T&D Loss has been kept
constant by the Commission in both its orders dated Nov, 1998 and Dec, 1999. |
4.5
|
Provision for bad debts Provisions of bad debts for
2000-2001, proposed by NESCO is too high an should not be accepted. The Commission should
only make a token provision for bad debt, as allowing 15% of incremental arrears as bad
debt will be a premium on inefficiency. |
4.6
|
Load Factor Billing The licensee has not followed the
directions of OERC like installation of meters. Therefore load factor billing should not
be allowed to continue or at least, load factor should be brought down. |
4.7
|
Multi Year Tariff Tariff for consumers should be
fixed for a period of 5 years and should not change every year at least for industrial
consumers for enabling them their future strategy. |
4.8
|
Calculation of Interest on loan Interest should not
be charged on expenses which do not result in addition of assets. Penal interest on loan
and interest on loan for working capital should not be allowed because they have become
necessary due to NESCOs inefficiency in collecting dues. |
4.9
|
Calculation of Reasonable Return Reasonable return
should be recalculated after debiting consumer's contribution and following GOI circular
of May, 1999. Reasonable return for investments made upto 15.10.91 should be calculated
separately and not at 13%. The later rate is applicable to investments made after 16th
October, 1991 and till 31st March, 1999. |
4.10
|
Contingency Reserve Contingency
Reserve should be kept at 1999-2000 approved level. |
4.11
|
Calculation of Depreciation Depreciation for each
block of assets should be exhibited in a register by the licensees within a time frame
fixed by OERC. It should be calculated on the basis of relevant GOI notification of 1994. |
4.12
|
Special appropriation for previous losses Special
appropriation for previous losses should not be allowed as the licensee has not kept
within maximum limit permitted by OERC with regard to reduction of T&D loss and
directions to improvement of efficiency. |
4.13
|
Penalty for excess drawal DISTCOS should sign
agreement with GRIDCO for monthly demand and annual energy. Excess drawal over demand
booked should attract penalty and excess annual drawal of energy should be paid for at the
highest marginal rate. |
4.14
|
Export Oriented Units
|
4.14.1
|
Some of the EOUs suggested that OERC may create a sub category
of consumers namely, Export Oriented Power Intensive Unit. The total tariff including
demand and Energy Charges for EOUs should not exceed 200 paise/units.
|
4.14.2
|
Some of the objectors pointed out that NESCO is trying to give
a subsidised tariff to the EOUs to make additional profits out of it. The present proposal
for special tariff for EOUs should be rejected as a better incentive tariff is already in
operation.
|
4.15
|
Simultaneous Maximum Demand for Railways
|
4.15.1
|
The South Eastern Railway, Garden Reach, Calcutta has
represented that while the proposed BST of GRIDCO allows the benefit of simultaneous
maximum demand to NESCO, the latter does not pass on the benefit to Railways. Further the
integration period for recording of maximum demand should be restored to 30 minutes from
the existing 15 minutes as per General Conditions of Supply, 1995 of OSEB.
|
4.15.2
|
It was also argued that Railways load fluctuation is due to
extraneous factors like accidents and public agitation etc. and hence the proposed penalty
on over-drawal may be withdrawn.
|
4.16
|
Interruption, Low Voltage and Unreliable Supply Due
to power interruption, low voltage and unreliable supply, consumers are put to unnecessary
harassment. Sometimes, costly machines are damaged due to low voltage. Consumer standard
as prescribed by OERC should be strictly adhered to. |
4.17
|
Unauthorised and illegal abstraction of Electricity Despite
persistent objection by genuine consumers unauthorised and illegal abstraction of
electricity has not stopped. This has resulted in higher tariff for the honest consumers. |
4.18
|
Non payment of Bulk Supply bills by DISTCOs Despite
regular energy bills raised to DISTCOs, they are not making payment of the Bulk Supply
bills in full. This has resulted in huge arrears against DISTCOs, due to which GRIDCO is
unable to make payment to Generators and financing Institutions and paying a large amount
towards DPS and interest. |
4.19
|
Excess drawal of power by DISTCOs DISTCOs are drawing
power in excess of the projected schedule by GRIDCO, thereby GRIDCO is being compelled to
procure costlier power and hence loosing a large amount on this account. |
4.20
|
CLARIFICATIONS SOUGHT BY DIRECTOR (TARIFF), OERC During
Hearing Director (Tariff), OERC sought certain clarifications from NESCO on the following
issues. |
4.20.1
|
NESCO has estimated a sale of 1483.689 MU during the year
2000-01. The voltage wise sale figures are given as:-
LT
|
583.90
|
HT
|
396.04
|
EHT
|
503.74
|
Total :
|
1483.68
|
NESCO has proposed distribution loss at 38%. The total power to be purchased from
GRIDCO = 1483.689/(1-0.38) = 2393.04 MU
Loss at EHT is taken as zero by NESCO.
So power available for sale at HT = 2393.04 503.74 = 1889.3 MU
Sale at HT & LT = 396.03 + 583.90 = 979.94 MU
So the T&D loss = 48.13%
Similarly, it can be shown that the T&D loss level varies from
licensee to licensee. But strangely all the three licensee of BSES group have proposed
same level of T&D loss for the year 2000-01. |
4.20.2
|
None of the licensee has carried out any study till date to
differentiate and separately quantify commercial and technical loss by installation of
meters at distribution transformer end including 100% metering for consumers connected to
those transformers.
|
4.20.3
|
NESCO proposes a special rate for the power intensive industry
engaged in export and wants a relief of Rs.16.60 crores. Justification for this huge
rebate which would be otherwise loaded to other classes of consumers is not furnished.
|
4.20.4
|
No interest is paid to the consumers on security deposit and
security deposit has not been deducted while calculating capital base. The same may be
justified.
|
4.20.5
|
Interest on loan includes penal interest of Rs.9.24 crores
towards subsidiary loan and Rs.1.46 crores towards World Bank loan. This is due to
non-payment of installments in time. NESCO has to clarify why it should be included in
revenue requirement.
|
4.20.6
|
NESCO proposed to avail long-term loan from IFC amounting to
Rs.58 crores for meeting long-term working capital need. Interest burden has been
estimated at Rs.3.06 crores. Why interest on working capital loan should be considered for
the purpose of revenue requirement in addition to the provisions of Sixth Schedule.
|
4.20.7
|
NESCO has claimed an amount of Rs.15.98 crores as DPS to
GRIDCO. This amount is payable to GRIDCO due to non-payment of dues in time. NESCO has to
clarify why consumers should be burdened for its inefficiency in collection of dues
resulting in failure to pay GRIDCO.
|
4.20.8
|
NESCO proposed to incur capital expenditure amounting Rs.55.86
crores (52.05 + 3.81 IDC) only in the year 2000-01. The break up of the expenditure is
given below :
Name of the work |
Tariff filing 99-00 |
1999-00 (Actual) |
2000-01 |
PMU work |
23.76 |
8.03 |
37.48 |
R.E. work |
20.73 |
6.44 |
2.07 |
Metering |
10.36 |
3.15 |
10.00 |
Others |
3.17 |
1.53 |
2.50 |
Total
|
58.02 |
19.15 |
52.05 |
It is seen from the above that there is a big gap
between the figures proposed during 99-00 tariff filing and 2000-00 filing. Although
Commission in their last order has excluded RE works for the purpose of calculation of
capital base, still the expenditure approved by the Commission is much higher than the
actual achievement during 1999-00.
NESCO may explain the reason for not reducing the capital expenditure
to a comparative level as per the actual expenditure last year. |
4.20.9
|
NESCOs proposal of carry forward of past losses of 7.26
crores in the year 2000-01 needs clarification.
|