5.0
|
NESCOS REPLY TO THE OBJECTIONS Shri S. K Anand,
Executive Director of NESCO, replied to the various issues raised by the objectors. |
5.1
|
NESCO stated that the proposed increase in tariff was based on
a reasonably accurate estimate of the revenue requirement for the year 2000-01.
Additionally the proposed tariff would be applicable for only a part of the year resulting
in huge losses for the company. In order to ensure the viability of the power sector in
the state of Orissa, it was necessary to balance the interests of the licensee and those
of the consumers.
|
5.2
|
The retail tariff application of NESCO was well within the
provisions of the Reform Act, 1995 and Sixth Schedule of the Act, 1948. The distribution
and retail supply licence also required the licensee to submit its revenue requirement
annually. NESCO has submitted the revenue requirement for 2000-01 and has requested for an
adjustment in tariff to meet the revenue requirement. This is in accordance with
regulatory framework prevailing in the State of Orissa.
|
5.3
|
A large number of LT consumers continued to pay tariffs much
lower than their cost of supply. The process of cross-subsidisation has to be tapered off
gradually due to socio-economic reasons. OERC recognises the need for cost based tariff.
This process would be completed over time and cross subsidies would continue till such
time.
|
5.4
|
Responding to the general objection of all objectors regarding
high distribution losses, NESCO stated that it had already embarked on a massive metering
plan and other projects which would strengthen the distribution system. The benefit of all
these would accrue over a period of time. The targeted loss of 38% for the year 2000-01
was a stiff target and formed a reasonable basis for the tariff proposal.
|
5.5
|
Distribution loss during the last year was 43%. NESCO was
taking a number of steps to reduce the system loss. Some of the measures were providing
meter to new consumers, replacement of defective meters, strengthening distribution
network, installation of 11 KV capacitors, commissioning of substations with small LT less
transformers, strengthening vigilance activities etc.
|
5.6
|
Regarding EOUs request for creation of a sub-category of Power
Intensive Industries to give benefit of competitive tariff NESCO had stated that similar
proposal was placed before the Commission in its tariff application of 1999-00. But the
same was not accepted by the Commission.
|
5.7
|
Replying to the objection raised by EOUs for continuation of
provision of Demand Charge, NESCO stated that it was not possible to waive the same as the
Bulk Supply Tariff prevailing is of two-part type. Even for those consumers having CD
higher than 25 MVA the licensee is charged Demand Charges by GRIDCO.
|
5.8
|
The proposed colony consumption tariff was still lower than
the proposed tariff charges for consumption by the EOUs.
|
5.9
|
Reacting to the suggestion for dispensing with the provision
of DPS, NESCO clarified that the Commission might consider dispensing this provision if
the same provision was dispensed with Bulk Supply dues.
|
5.10
|
Responding to the proposal made by EOUs for calculation of
load factor on an annual basis, NESCO had given a negative reply. NESCOs proposal
envisaged calculation of load factor on monthly basis as the basis of billing should
logically relate exactly to the billing period.
|
5.11
|
NESCO has not proposed any changes in the billing practice of
charging monthly fixed charges.
|
5.12
|
Distribution Loss at 43% last year was calculated based on
actual data. The reported loss of 43% was based on records and therefore the charges that
the figures were manipulated stood refuted. All records of the Company might be verified
to assess the actual level of loss suffered by the Company.
|
5.13
|
Computation of Employees expenses and A&G expenses was
made after taking into consideration the details on expenses already incurred by NESCO.
Fifth Pay Commission recommendations were already implemented before the business of
transfer of distribution of electricity was made to NESCO.
|
5.14
|
The State Govt. has not paid any subsidy for supply made to
Kutir Jyoti and irrigation categories so far.
|
5.15
|
Regarding revenue collection, NESCO was able to increase LT
collection by about 26% during the last year over previous year. Further up to the month
of November 2000 the LT collection in the current financial year had increased by about
37% over the same period in the last year.
|
5.16
|
Regarding creation of a special category of consumers NESCO
clarified that there was no proposal for a special tariff separately for Power Intensive
Industries. NESCOs offer of special tariff as per clause 9.3 of Retail Supply Tariff
Application was for all industrial consumers having contract demand of 25 MVA or above if
they achieve load factor of 70% or above in any month. If these consumers failed to
achieve the load factor of 70% in any month, they would have to pay for that month the
normal retail supply tariff as applicable to the relevant consumer category.
|
5.17.1
|
Sincere efforts for improving consumer services and redressal
of consumer grievances were being made through NESCOs departmental network.
Effective steps had been taken to form village committees and hold Bijuli
Adalats.
Constant efforts were made for improvement of the supply conditions as well as providing
proper metering for the benefit and satisfaction of consumers. These are also periodically
reviewed by OERC.
|
5.18
|
NESCOs application was submitted basing on the present
BST tariff and the question of resorting to high cost power did not arise.
|
5.19
|
The matter regarding improvement of supply conditions was to
be considered separately from the tariff application.
|
5.20
|
Metering Project was being rigorously executed and monitored
for maximization of benefit. Emphasis was being given for procurement of best quality
meters.
|
5.21
|
The energy bills were being prepared and delivered as per the
regulations and tariff and license conditions were not being violated.
|
5.22
|
The inadequacy of cash inflows to meet the cash outflows
(expenses) had forced NESCO to delay payments to GRIDCO thereby creating liability of
Delayed Payment Surcharge.
|
5.23
|
The objectors comments on Managing
Directors/Executive Directors expenditure were unfortunate and not based on
facts. With regard to employees expenses and A&G expenses, computation of such
expenses have been made after taking into consideration the details of expenses already
incurred by NESCO and expenses incurred during 1999-00. It was further clarified that
A&G expenses incurred were as per actual requirement. Considering the size of turnover
of the organization, the number of field offices it maintained and the no of numbers it
services, the establishment and A&G expenses incurred by NESCO are quite reasonable.
|
5.24
|
The decision of removing LT lines by providing small
transformer is technically sound. The company is using standard materials of good quality
in the system. The work of providing LT switches for street light and common control for
the same is in progress.
|
5.25
|
Different states have different tariff for different types of
consumers. OERC is regulating tariff every year after elaborate scrutiny, public notice
public hearing and having due regard to the actual expenditure etc.
|
5.26
|
Responding to GRIDCOs objection NESCO has stated that
the relationship between GRIDCO and NESCO is covered by Bulk Supply Agreement. Any
disputes regarding payment are to be resolved as per the above agreement and the same may
not be considered with this tariff application.
|
5.27
|
It is clarified that all data pertaining to accounts for the
period 26.11.98 to 31.03.99 has been furnished by NESCO to GRIDCO. We would like to
confirm that NESCO has also submitted to OERC the audited accounts for the year 1999-00.
NESCO has already submitted data for energy requirement and load growth as requested by
GRIDCO and OERC for planning purposes. This matter is to be considered separately from
tariff application.
|
5.28
|
The methodology adopted by NESCO in submitting the tariff
proposal is as stipulated by OERC. The figures given for debts, bad debts, interest on
loan, interest on working capital are also as per requirements of OERC.
|
5.29
|
NESCOS RESPONSE TO ISSUES RAISED BY DIRECTOR (TARIFF)
|
5.29.1
|
Distribution Loss In earlier tariff orders OERC had
defined the difference between total purchase and total sale as distribution loss. NESCO
submitted that it had followed the same methodology for calculation of distribution loss
in tariff application. In the list of queries of Director (Tariff) to NESCO, the
distribution loss had been computed after removing the sale and purchase of EHT consumers.
This method of calculation was neither correct nor was in line with the method adopted by
OERC earlier.
The loss figures for the BSES companies for 1999-00 were ranging between 42-44% and the
companies have targetted to bring the same to 38%. This also implied each company would
achieve different rate of loss reduction with a common target. OERC might appreciate that
there was no inconsistency in setting the loss target of 38% for the distribution company. |
5.29.2
|
Pilot Study Regarding the suggestion
for pilot study to quantify T&D loss at different voltage of supply NESCO submitted
that to carry out such studies necessary meters, metering units, meter boxes needed to be
procured which would take at least 4 months. Besides all defective meters had to be
replaced, unmetered supply to be metered, consumer data to be sanitized and unauthorised
connections to be regularised prior to conducting such a study. NESCO therefore
anticipated that such a study could be started some time in April 2001 and the first set
of results would be available by September 2001. NESCO proposed to carry out a study in
one 11KV feeder covering about 25 to 30 distribution transformers in the initial stage. |
5.29.3
|
Special Tariff Referring to the proposed special
tariff NESCO pointed out that the total rebate on account of this tariff was Rs.17.17
crores out of which Rs 0.27 crores had been estimated towards rebate for timely payment.
The balance rebate of Rs.16.90 crores represented the difference between the total revenue
at proposed retail tariff and the revenue to be realised if special tariff was to be
offered. NESCOs proposed tariff for industries above 25 MVA was based on
considerations of capacity, load factor and power factor. If any consumer failed to
achieve in any month, the consumer should be charged at normal RST. The idea of a special
tariff was to encourage the consumers to opt for grid power instead of captive power
generation. Any increase in consumption by these industries would mean availability of
higher crosss-subsidy to LT consumers. This justified the rebate on account of special
tariff.
NESCO clarified that it did not have any special affinity towards EOUs. In fact EOUs
for NESCO were like any other consumer. Considering the poor industrial base of the State
of Orissa and the vast mineral resources that it was endowed with OERC in the last tariff
order had formulated a special tariff for consumers having contract demand of 100 MVA with
load factor 80% and above. NESCOs proposal was along that line of thinking of OERC
and had the objective of attracting new consumers with high load factor and demand. |
5.29.4
|
Security Deposit Following the Sixth Schedule
Capital Base meant the capital investment made for long term use by the
licensee for the creation of long term assets as well as funds committed for long term
working capital use. Thus licensee was eligible to get reasonable rate of return on its
long term capital investment.
Going by the current practice no part of the consumer security deposit was used for
long term investment. On the other hand when an agreement was terminated the consumer
security deposit was refunded/adjusted against the consumers Energy Charges. Hence
the consumer security deposit was not deducted from the asset base for calculation of
capital base. NESCO further pointed out that in the transfer document also the consumer
security deposit had not been shown under long term liability. |
5.29.5
|
Penal Interest NESCO submitted that it had not been
able to make timely payment of loan installments due to poor cash inflows and the earlier
deficit tariff order. The payment of penal interest was therefore not due to the
inefficiency of NESCO. The licensee requested OERC to approve penal interest on loan. |
5.29.6
|
Working Capital Interest NESCO could
not avail of working capital assistance from any financial institution due to its poor
financial condition. That is why the licensee was unable to pay the power purchase bills
of GRIDCO in time. The inadequacy of cash inflows to meet the cash outflows had forced
NESCO to delay its payment to GRIDCO. This had resulted in accumulating arrears and
delayed payment surcharge.
NESCO had applied to IFC for long term loan to meet long term working
capital needs which would reduce its DPS liability. The licensee therefore requested to
allow working capital interest on long term working capital borrowed. |
5.29.7
|
DPS to GRIDCO As pointed out above the inadequacy of
cash inflows to meet the cash outflows had forced NESCO to delay its payment to GRIDCO and
subsequently pay DPS. NESCO submitted that the previous tariff order was a deficit order
and revenues from tariff were not adequate to meet the expenses. The licensee requested
OERC to approve the DPS figures. |
5.29.8
|
Capital Expenditure As per the audited accounts of
the Company for 1999-00 the total capital expenditure incurred by NESCO was as follows
:
(in Rupees) |
PMU Works |
136722013 |
REC Works |
75167838 |
Others |
7901850 |
Interest During Construction |
13945535 |
Capital Stores Procured for PMU Works |
62870178 |
Total Capital Expenditure Incurred in
1999-00 |
296607414 |
|
5.29.9
|
Carry Forward of Past Losses Following the Sixth
Schedule special appropriation could be made sufficient to cover previous losses. The
losses incurred by NESCO during 1999-00 was of the order of Rs.74.74 crores. NESCO has
proposed to include an amount of Rs.7.26 crores only for recovery through tariff in the
ensuing year to avoid a sharp increase in tariff. The balance loss would be recovered
through tariffs in future years. The licensee confirmed that the loss had been due to
inadequate tariffs and the same needed to be recovered. |
5.29.10
|
Valuation of Assets NESCOs assets had been
acquired from GRIDCO as on 01.04.1999 and the value of the assets as on that date was the
purchase price for the licensee. NESCO treated the assets as new even if the assets were
second hand. NESCO had computed depreciation treating assets as new. |
5.29.11
|
Metering NESCO had installed 38935 meters and
replaced 14682 defective meters during 1999-00. The company had also installed 38767
single-phase meters during the period from April to October 2000 and arrangements had been
made to procure two lakh single phase meters. The Company took some time to arrange for
the procurement of meters and large proportion of these meters were installed in the later
part of the year. The company had already made detailed programme of procurement and
installation of meters. NESCO requested for continuation of the present load factor
percentage as an appropriate load factor which could provide a correct incentive for
adoption of metering by consumers. The licensee might otherwise face much more resistance
for meter installation in case the load factor was revised downward.
|