| 6.15  | Bad and Doubtful Debt | 
  
    | 6.15.1 | NESCO has proposed Rs.13.54 crore as
    Bad & Doubtful Debt during 2001-02. In ARR filing 2002-03 it has also proposed an
    amount of Rs.13.59 crore for the year 2002-03. | 
  
    | 6.15.2 | NESCO has provided an age wise
    analysis of outstanding debts in F-25. As per the said analysis, NESCO has stated that
    Rs.123.02 crore are outstanding for more than 24 months as on 31 March 2002. | 
  
    | 6.15.3 | In its application, NESCO has
    proposed 1% of HT billing and 6% of LT billing to be kept for Bad and Doubtful Debt for
    the year 2001-02 and 1% of HT billing and 9% of the LT billing for the year 2002-03. | 
  
    | 6.15.4 | Many objectors have questioned the
    provision of such a high amount towards Bad and Doubtful debt. They have urged to disallow
    the provision except a token amount so that the licensee is not allowed a premium on its
    inefficiency in collection. | 
  
    | 6.15.5 | The Commission examined the
    proposal submitted by the licensee and analysed the suggestions and objections raised by
    the objectors during the hearing. The Commission is also concerned at the inefficiency of
    the licensee in collecting the arrear dues. Considering the reality of the situation and
    approval of the Commission of the bad debt in tariff order for 2000-01 it decides to
    permit 2.5% of the gross sales as provision for such debt. On this basis, the Commission
    approves Rs.8.61 crore and Rs.9.53 crore for the year 2001-02 and 2002-03 respectively as
    Bad and Doubtful Debt for recovery through tariff. | 
  
    | 6.16 | Contribution to
    Contingency Reserve NESCO has proposed a statutory appropriation towards
    contribution to contingency reserve calculated at 0.375% on the opening gross block for
    the applicable year. This works out to Rs.1.13 crore and Rs.1.36 crore for the year
    2001-02 and 2002-03 respectively and the amounts are within the limit prescribed in the
    Sixth Schedule to the Act, 1948. Hence the Commission approves a sum of Rs.1.13 crore for
    the year 2001-02 and Rs.1.36 crore for the year 2002-03 towards contribution to
    contingency reserves under special appropriation.  | 
  
    | 6.17 | Capital Base | 
  
    | 6.17.1 | Original Cost of Fixed
    Assets NESCO has projected its original cost of fixed assets at Rs.363.80
    crore as on 31.03.2002 and Rs.413.91 crore as on 31.03.2003 as depicted in Form No.F-14
    and F-35. Fixed asset as on 31.3.2001 was Rs.302.21 crore (F-37). NESCO shows an asset
    addition of Rs.61.59 crore during 2001-02 and Rs.50.11 crore during 2002-03. | 
  
    | 6.17.2 | This has been examined with
    reference to the audited accounts for the year 2000-01 submitted by NESCO and information
    submitted in the format F-2 and F-35. | 
  
    | 6.17.3 | The Commission accepts Rs.363.80
    crore and Rs.413.91 crore as original cost of the fixed asset as on 31 March 2002 and 31
    March 2003 respectively for the purpose of calculation of capital base. | 
  
    | 6.18 | Receipts against
    Consumers Contribution Contribution from consumers of Rs.51.82 crore as on
    31.3.2002 and Rs.54.53 crore as on 31.03.2003 has been deducted by the licensee from fixed
    asset for calculation of capital base. Schedule 2 to the Annual Accounts of 2000-01 of
    NESCO duly audited by the tax auditors, shows a balance of Rs.49.12 crore under consumer
    contribution. Comparing the figure of consumer contribution for the year 2001-02 and
    2002-03 with that of FY 2000-01 the Commission considers it reasonable to accept the
    figure of Rs.51.82 crore and Rs.54.53 crore for the respective years to be deductible from
    the asset base for the purpose of calculation of capital base. | 
  
    | 6.19 | Original cost of work in
    progress | 
  
    | 6.19.1 | NESCO has projected Rs.23.91 crore
    and Rs.10.66 crore towards original cost of work in progress for the year 2001-02 and
    2002-03 respectively which form a part of asset base. The comparative position of capital
    expenditure during the year 2000-01, 2001-02 and 2002-03 as per tariff filing and ARR is
    given in Table-7. Table : 22(Rs. In crore)
 
      
        | Particulars | 2001-02 | 2002-03 |  
        | Opening balance of WIP | 52.55 | 23.91 |  
        | Expenditure during the year | 30.48 | 34.05 |  
        | Interest during construction | 1.96 | 2.21 |  
        | Other OH | 0.51 | 0 |  
        | Transfer to fixed asset | 61.59 | 50.11 |  
        | Clossing balance of WIP | 23.91 | 10.66 |  | 
  
    | 6.19.2 | As per the audited accounts of
    2000-01 prepared for the purpose of Tax Audit, the capital work in progress position as on
    31.3.2001 is Rs.52.55 crore which corresponds to the opening balance as proposed by the
    licensee. The Commission consider it reasonable to accept Rs.23.91 crore and Rs.10.66
    crore as balance of capital work in progress as on 31.3.2002 and 31.3.2003 respectively
    for the purpose of calculation of capital base. | 
  
    | 6.20 | Compulsory Investment
    under Para IV | 
  
    | 6.20.1 | In OERC Form No.F-14, NESCO has
    shown a balance of Rs.1.13 crore under 'contingency reserve' as on 01.04.2002 to form a
    part of asset base whereas nothing has been proposed for the year 2002-03. From form F-33
    of the tariff filing 2001-02, it is revealed that the balance in the contingency reserve
    as on 31.03.2001 has been Rs.3.05 crore. Thus, the balance at the end of 31.03.2001 i.e.
    Rs.3.05 crore should have been invested in accordance with para IV(2) of the Sixth
    Schedule of the Act, 1948 by 30th September 2001 for inclusion in the capital base. No
    document regarding this investment has been produced to the Commission. | 
  
    | 6.20.2 | As such the Commission does not
    consider it prudent to take this Rs.1.13 crore for the purpose of calculation of capital
    base FY 2001-02. | 
  
    | 6.21 | Working Capital | 
  
    | 6.21.1 | Average cost of stores | 
  
    | 6.21.1.1 | According to para XVII(e)(i) of the
    Sixth Schedule of the Act, 1948, a sum equal to one twelfth of the sum of book cost of
    stores, materials and supplies including fuel on hand at the end of each month of the year
    of account should be taken into account as working capital for calculating the capital
    base. NESCO has proposed Rs.16.62 crore for the year 2001-02 and Rs.12.40 crore for the
    year 2002-03 in their retail tariff filing 2001-02 and ARR 2002-03 respectively. | 
  
    | 6.21.1.2 | The Commission examined the
    proposal of NESCO and does not accept the amount as proposed. A stock of three months
    consumption of materials at any particular point of time can be considered reasonable.
    Accordingly the Commission approves one-forth of the total annual consumption of materials
    i.e. Rs.4.08 crore for the year 2001-02 and Rs.4.84 crore for the year 2002-03 as
    reasonable for the purpose of working capital for stores to be included in the capital
    base. | 
  
    | 6.22 | Average Cash and Bank
    Balance | 
  
    | 6.22.1 | NESCO has proposed Rs.11.91 crore
    and Rs.11.11 crore for the FY 2001-02 and 2002-03 respectively computed on the basis of
    the provisions laid down in Sixth Schedule of the Act, 1948. NESCO in form F-19 has given
    the provision of monthly cash balance from April 2001 to March 2002 and projection from
    April, 2002 to March, 2003. As stated in para XVII(1)(e)(ii) of the Sixth Schedule of the
    Act, 1948, an amount equal to 1/12 of the sum of cash & bank balances and call and
    short term deposits at the end of each month of the year of account, not exceeding the sum
    specified therein can be included in capital base. | 
  
    | 6.22.2 | The Commission feels that liquid
    funds are needed for the payment of Employees' Cost and Administrative & General
    Expenses pending collection of receivable from the consumers. The normative lead time
    between the supply of electricity to the consumers and collection of tariff is considered
    two months. Hence, the fund requirement for two months payment of Employees' Cost and
    Administrative & General Expenses would be appropriate for meeting working capital
    requirement in the form of cash and bank balance Calculated on the aforesaid basis, the
    amount works out to Rs.9.30 crore for the year 2001-02 and Rs.9.60 crore for the year
    2002-03. The Commission, therefore, approves a sum of Rs.9.30 crore for the year 2001-02
    and Rs.9.60 crore for the year 2002-03 towards cash and bank balance for meeting working
    capital requirements. | 
  
    | 6.23 | Accumulated Depreciation NESCO
    has proposed a sum of Rs.116.52 crore and Rs.144.77 crore towards amounts written off or
    set aside on account of depreciation as on 31.3.2002 and 31.3.2003 respectively. The
    audited accounts for the year 2000-01 shows an accumulated balance of Rs.93.31 crore. The
    licensee has calculated depreciation as per the rate prescribed in the latest GOI
    notification and claimed depreciation for the year 2001-02 for Rs.23.44 crore and Rs.28.26
    crore for the year 2002-03. The Commission, as mentioned in para 6.4.4 has calculated
    depreciation at pre-92 rates for the year 2001-02 and 2002-03 and accepted a figure of
    Rs.11.38 crore and Rs.13.72 crore for the respective years. Accordingly accumulated
    depreciation as on 31 March 2002 would be Rs.104.69 crore (Rs.93.31+Rs.11.38 crore) and
    Rs.118.41 crore (Rs.104.69+Rs.13.72) as on 31st March 2003. Hence, the Commission approves
    Rs.104.69 crore and Rs.118.41 crore as accumulated depreciation as on 31.3.2002 and
    31.3.2003 for the purpose of calculation of Capital Base. | 
  
    | 6.24 | Loans and Bonds | 
  
    | 6.24.1 | NESCO has proposed Rs.310.45 crore
    and Rs.344.45 crore as loan and bonds to be deducted from the asset base in order to
    arrive at the capital base for the year 2001-02 and 2002-03 respectively. For the year
    2001-2002, the total loan and bond constitute Rs.65.18 crore of loan advanced by GRIDCO,
    Rs.78.27 crore of loans given by World Bank and Rs.167 crore of power bond issued to
    GRIDCO. Similarly, as on 31 March 2003 the balance of loan advanced by GRIDCO would be
    Rs.65.18 crore, World Bank Loan Rs.112.27 crore and power bond would be Rs.167.00 crore.
    Information on receipt/repayment of loan as submitted by NESCO in OERC form No.F-3 is
    reproduced in Table : 23. Table : 23(Rs. in crore)
 
      
        | Source  | Opening balance as
        on 1.4.01 | Received during
        01-02 | Repayment during
        01-02 | Balance as on
        31.3.02 | Expected received
        during 02-03 | Expected repayment
        during 02-03 | Expected balance as
        on 31.3.03 |  
        | GRIDCO | 65.18 | 00 | 00 | 65.18 | 00 | 0 | 65.18 |  
        | World Bank | 48.13 | 30.14 | 00 | 78.27 | 34.00 | 00 | 112.27 |  
        | Power Bond | 167.00 | 0.00 | 00 | 167.00 | 00 | 0.00 | 167.00 |  
        | Total | 280.31 | 30.14 | 00 | 310.45 | 34.00 | 00 | 344.45 |  | 
  
    | 6.24.2 | The Commission approves an amount of
    Rs.310.45 crore and Rs.344.45 crore of loans and bonds to be deducted for the year 2001-02
    and 2002-03 respectively from the asset base for the purpose of calculation of capital
    base. | 
  
    | 6.25 | Consumers' Security
    Deposit | 
  
    | 6.25.1 | NESCO while calculating the capital
    base as on 31.3.2002 and as on 31.03.2003, has not deducted security deposits made by the
    consumers lying with the licensee as on respective dates. As reported by the licensee in
    F-37, balance of security deposits as on 31 March 2002 would be 40.61 crore and Rs.49.61
    crore as on 31 March 2003. | 
  
    | 6.25.2 | The amount deposited in cash with
    the Licensee by the consumers as security is clearly deductible for the purpose of
    determination of Capital Base as per provision of para XVII(1)(iii) of the Sixth Schedule
    of the Act, 1948. Accordingly, an amount of Rs.40.61 crore and Rs.49.61 crore has been
    deducted for the year 2001-02 and 2002-03 respectively in computation of Capital Base. | 
  
    | 6.25.3 | Based on the forgoing observations,
    the Commission finds that Capital Base for 2001-02 and 2002-03 would be Rs.(-) 106.48
    crore and Rs.(-) 127.97 crore respectively as against Rs.(-)61.42 crore and Rs.(-)95.67
    crore proposed by NESCO. | 
  
    | 6.26 | Reasonable Return As
    capital base of the licensee for the year 2001-02 and 2002-03 has become negative, the
    licensee has not claimed return as per the standard rate. Only 0.5% on the loan
    outstanding as on 31st March 2002 and 2003 has been taken as reasonable return for the
    year 2001-02 and 2002-03 amounting Rs.1.55 crore and Rs.1.72 crore respectively. This
    conforms to the provisions of schedule Sixth to the Electricity Supply Act, 1948 and
    hence, Commission approves a figure of Rs.1.55 crore and Rs.1.72 crore towards reasonable
    return for the year 2001-02 and 2002-03 respectively. | 
  
    | 6.27 | Miscellaneous Receipts | 
  
    | 6.27.1 | NESCO proposed Rs.2.60 crore towards
    miscellaneous receipt for FY 2001-02 and FY 2002-03. As per the audited accounts of NESCO
    for the year 2000-01. Miscellaneous receipt collected by the licensee is of the order of
    Rs.1.70 crore. Hence, the Commission considers it reasonable to accept Rs.2.60 crore
    towards miscellaneous receipts for the year 2001-02 and 2002-03. | 
  
    | 6.27.2  | Revenue Requirement,
    Reasonable Return and Clear Profit In the light of above decisions and
    calculation, the Commission approves expenditure for the purpose of revenue requirement an
    amount of Rs.433.89 crore for the year 2001-02 and Rs.419.90 crore for the year 2002-03
    after applying correctives. In case the correctives applied by the Commission do not
    materialise the expenditure would be Rs.442.42 crore for the year 2001-02 and Rs. 507.53
    crore for the year 2002-03. Commission approves a special appropriation of Rs.1.13 crore
    for the year 2001-02 and Rs.1.36 crore for the year 2002-03 towards contribution to
    contingency reserve. Reasonable returns has been approved in para 6.30 at Rs.1.55 crore
    for the year 2001-02 and Rs.1.72 crore for the year 2002-03. The calculation of
    expenditure for revenue requirement, reasonable return and clear profit as approved have
    been reflected in Annexe-A, B & C respectively. | 
  
    | 6.28 | TARIFF ISSUES | 
  
    | 6.28.1 | In addition to the above, the
    Commission would like to address the various issues raised during the course of public
    hearing on other commercial matters which are given hereafter. | 
  
    | 6.28.2 | We do not find it necessary to
    specifically comment on each one of the objections. The objections with regard to
    financial aspects and with regard to tariff design as well as various suggestions on these
    aspects shall be dealt in the later part of the order while dealing with the revenue
    requirement and determining tariff. However, we may record our observations specifically
    on a few issues which do not conveniently fit into the module of either revenue
    requirement or tariff. | 
  
    | 6.28.3 | In course of the hearing, consumers
    of different categories have highlighted the impact of tariff with reference to financial
    viability, commercial consideration and ability to pay. While we have taken into account
    the overall interest of the consumers, we have also given equal consideration to the
    financial viability of the Licensee and the necessity of the State for fostering a healthy
    electricity industry. Ability to pay, lack of funds or competitiveness of any particular
    industry either in the domestic or in international market cannot be the guiding
    consideration in designing tariff. The Commission does not find it desirable to go beyond
    the principles incorporated in Section 26(2) and Section 26(5) of the Reform Act. | 
  
    | 6.28.4 | The Reform Act, 1995 envisages a
    tariff structure that would bring about efficiency and economy in the supply and
    consumption of electricity. The Reform Act, 1995, also aims at a tariff that would reflect
    cost, would be linked to efficiency and would eliminate inter-class and intra-class
    subsidies. At the cost of repetition we would like to state some of the observations of
    the Commission in the previous tariff orders. | 
  
    | 6.28.5 | The Commission is also acutely aware
    of its role in balancing the conflicting interest of various stakeholders, bringing about
    efficiency and economy in the use of electricity and designing a tariff structure that
    should be just, fair and reasonable. The low voltage consumers expect a tariff that is
    affordable and the high and extra high voltage consumers are pleading for a tariff that
    should reduce their burden of cross-subsidy. While taking note of these factors, we have
    to go by the mandate in law to allow reasonable return to the investors in the electricity
    industry in the State. | 
  
    | 6.29 | Tariff Hike | 
  
    | 6.29.1 | It was discernible from the filings
    before OERC that the currently proposed tariff would have to be much higher as compared to
    those of the immediate previous years even after pruning all expenditure items by the
    Commission on the same lines as in the past. Many objectors had alleged that there should
    be no revision in tariff since licensees have not achieved desired improvements and had
    not been able to reduce the T&D loss substantially. We ourselves have been very much
    concerned with the performance of the licensees and have been suo motu monitoring in
    various ways. | 
  
    | 6.29.2 | Another recurring objection against
    tariff increase has been the constraint of affordability. The domestic consumers have
    urged to leave them out of tariff increase because they cannot afford and they cannot pass
    on the burden which the commercial and industrial consumers can do. On the other hand,
    commercial and industrial consumers have pleaded that their products cannot be competitive
    and therefore their tariff should be reduced rather than increased. Every category has
    pleaded that tariff, if increased, should be for other categories. We cannot fully ignore
    the affordability factor because safeguarding interest of consumers is one of the main
    parameters in tariff fixation. But affordability cannot be the prime consideration. Sec.
    11(1)(e) of Reform Act mandates that the supply and distribution industry cannot be
    maintained unless the charges for the electricity supplied are reasonably levied and
    collected. Licensees of electricity supply and distribution cannot be expected to forego
    their legitimate dues and charge low rate to any category of consumers or to make
    industrial consumers competitive in national and international market. | 
  
    | 6.29.3  | It is the duty of the Commission to
    scrutinize the claims of licensee with a fine tooth-comb and allow only useful assets for
    capital base and only properly/prudently incurred expenditure for revenue requirement. But
    after we do so, Revenue requirement finally determined has to be allowed to be raised
    through tariff. This is the position in Law and has to be appreciated by the consumers of
    all categories. Keeping the above objective in view, the Commission has gone ahead in
    deciding the various parameters regarding determination of revenue requirement and tariff
    of the licensee in an endeavour to strike a balance between the interests of end consumers
    on one hand and financially viability of licensee on the other. | 
  
    | 6.29.4 | The Commission's analysis of NESCO's
    proposal and its finding as to reasonableness of various items and determination of the
    extent to which the expenses projected shall be considered to be "properly
    incurred" in the context of the Sixth Schedule as well as other parameters stipulated
    in Section 26 of the Reform Act, 1995 need to be given at length. | 
  
    | 6.30 | Wheeling charges | 
  
    | 6.30.1 | It was opined by some objectors that
    law does not provide for fixation of tariff for transmission or wheeling charges
    separately. | 
  
    | 6.30.2 | It may be noted that the provision
    under section 26(7) of OER Act authorises the Commission to ensure that the licensees
    comply with the provisions of their licensees regarding their charges for the sale of
    electricity, both wholesale and retail, and for the connection to and use of their assets
    or system in accordance with the provisions of this Act. | 
  
    | 6.30.3 | Thus, the provision of transmission
    or wheeling charges are built under the scope of tariff setting. | 
  
    | 6.30.4 | The issue of fixation of wheeling
    charges for utilisation of the distribution system by small generators namely mini/ micro/
    small hydro generators and non-conventional sources of generation has been examined by the
    Commission. In this connection, the Commission would like to clarify that a policy paper
    prepared by GoO was sent to the Commission for its views which has been duly scrutinised
    and forwarded to the Government for issue of appropriate policy guideline in this matter. | 
  
    | 6.31 | Load factor billing As
    opined by some of the objectors, it is true that it is the statutory obligation on the
    part of the licensee to replace meters. Load factor billing has been prescribed for a
    limited period the meter remains defective/or the consumer goes without meter to serve as
    a disincentive for the consumer and help adoption of metering by consumers. Hence, the
    Commission directs that the load factor billing should continue as per the existing
    tariff. | 
  
    | 6.32 | Incentive for maintaining
    high power factor | 
  
    | 6.32.1 | For the first time, the Commission
    in its tariff order dt.30.12.99 introduced an incentive to encourage improvement in power
    factor above 90%. Subsequently, the limit was raised to 97% in the RST order
    dt.19.01.2001. NESCO estimates that the rebate alone on this account to HT/EHT consumers
    will be of the order of Rs.0.81 crore during the FY 2001-02. | 
  
    | 6.32.2 | Some objector opined that for the
    health of electrical machinery it is risky to maintain power factor between 97% and unity
    power factor lagging because there is every chance of high voltage when suddenly some load
    gets off from the circuit. | 
  
    | 6.32.3 | It should be kept in view that the
    industries for better protection of their installation should follow prudent operational
    practice installing protective devices, so as to isolate the equipment during abnormal
    transient condition arising out of sudden load throw off or tripping of meter or feeders. | 
  
    | 6.32.4 | Further, as indicated below the KVA
    demand of the industry decreases as the PF improves, thereby benefiting the consumer on
    account of higher demand charge.
 
      
        | PF | KVA  | Excess KVA |  
        | 201 | 1 | 0 |  
        | 0.99 | 1.01 | 0.01 |  
        | 0.98 | 1.02 | 0.02 |  
        | 0.97 | 1.031 | 0.031 |  
        | 0.96 | 1.042 | 0.042 |  | 
  
    | 6.32.5 | Similar provision of power factor
    incentive/rebate have been recommended by other State Regulatory Commissions such as
    Gujurat Electricity Regulatory Commission, U.P. Electricity Regulatory Commission,
    Maharashtra Electricity Regulatory Commission where incentive is allowed for maintaining
    PF above 95%. Hence, the Commission does not consider it necessary to make change in the
    existing provision with regard to power factor incentive. |