6.33
|
Incentive for prompt
payment
|
6.33.1
|
Some objectors suggested for
relaxation of the rebate period of 48 hours . NESCO in its RST application for the year
2001-02 has estimated that the rebate on account of prompt payment within 48 hours of
presentation of bill during the FY 2001-02 will be order of Rs.0.37 crore in addition to
an amount of Rs.0.73 crore on account of rebate of 10 paise/unit. Hence, it is expected
that to avail such heavy amount of rebate, consumers should put extra efforts and make
payment of bills in time.
|
6.33.2
|
As per Commission's order, certain
categories of consumers are entitled to a rebate of 1% of the amount of the monthly bill
(excluding arrears and electricity duty) if payment is made within 48 hours of the
presentation of the bill. When a cash discount is allowed for payment within a specified
period, the cost of credit can be computed. For instance, if 15 days credit is offered
with a stipulation of 1% cash discount for payment within 48 hours (two days), excluding
the day for service of the bills, it means that the cost of deferment of payment by 12
days is 1%. If payment is made 12 days earlier than the due date, 1% of the amount can be
saved, which amounts to an annual attractive saving rate of 30%.
|
6.33.3
|
If cash discount is not availed, the
effective rate of interest will work out to 30.3%. The rational for availing trade credit
should be it's saving in cost over the form of short term financing, its flexibility and
convenience. Stretching trade credits or accounts payable results in cash discount
foregone.
|
6.33.4
|
As an example, Mahanadi Coal Field
with a monthly bill of Rs.8 crore gets a rebate of Rs.8 lakh per month or nearly a crore
of rupees over a period of one year. It is in the interest of the consumer to avail the
cash benefit or pay the normal charges i.e. within 15 days from the date of bill..
|
6.33.5
|
This practice of prompt payment is
followed by the generators for raising bills against GRIDCO and by GRIDCO to DISTCOs also.
In this age of SATCOM, FAX, Internet and STD commercial benefits must dictate and guide
not only the functioning of the licensee but those of the consumers also.
|
6.33.6
|
It has been reported by the
licensees that a number of consumers are availing this prompt payment rebate. The
objections have come mostly from the various Departments of the Government for fear of
audit objections for not availing the rebate due to their cumbersome official procedure
within their organization before releasing payment for consumption of electricity. For
them 48 hours may not be adequate and they may not be able to avail the prompt payment
rebate. In that case, they can pay the normal charges within the due date of 15 days and
convince the audit about their difficulty of not availing the rebate or alternatively
streamline the procedure to avail the rebate as a commercial incentive for the Government
|
6.33.7
|
In view of this, the Commission does
not consider it necessary to depart from its past order regarding incentive on prompt
payment.
|
6.34
|
Metering of street lights
|
6.34.1
|
Issues that street light metering
has not been done and billing is done on load factor basis was raised during the course of
the hearing. In this regard, Commission would like to convey that meetings were taken by
this Commission with Director, Municipal Administration, Government of Orissa, Chief
Executives of Municipalities and Managing Directors of DISTCOs on 11.04.2001 and
19.04.2001 to resolve the issues on metering of street lights.
-
It was agreed in the meeting that inspection to assess the connected load would be taken
up by Municipality and DISTCOs.
-
A single agreement for street lighting will be executed for a municipal area.
-
Wherever metering is in place, the rates applicable for street lighting category should
be implemented.
-
Until metering is in place, calculation of consumption for the purpose of billing will
have to be mutually worked out by the municipalities and DISTCOs considering the connected
load and the number of burning hours for street lighting. Preferably average 11 hours
burning of the lamps may be adopted due to seasonal variation. No maintenance should be
carried out during day time which requies avoidable consumption of electricity.
-
The switching ON and OFF of street lights will be done by the staff of the licensee.
Replacement of bulbs, fittings and maintenance thereof shall be carried out by the
municipal staff.
|
6.34.2
|
The licensees should take adequate
steps to comply with the decisions taken in the joint meeting with the Director, Muncipal
Administration, Government of Orissa and Chief Executives of Muncipalties, as stated
above.
|
6.35
|
Industrial policy framed
by Government of Orissa An issue was raised by the Orissa Small Scale
Industries Association that the proposed amendment in tariff by the licensee is directly
against the Industrial Policy Resolution (IPR) of Government of Orissa. This is clarified
that Industrial policy differentiating categories and conferring benefits change from time
to time on various considerations. Electricity charges are to be non-discriminatory from
economic point of view and it is neither desirable nor possible to synchronize the pricing
in keeping with changes from industrial and financial angle. However, if the State
Government desires to extent any benefit to a class or group of consumers, they can do so
under Section 12(3) of OER Act, 1995 by providing subsidy. |
6.36
|
Salt Production
Industries
|
6.36.1
|
The Commission carefully examined
the submission made by the M/s Humma and Binchanpali Salt Production and Sales Cooperative
Society Ltd., Ganjam requesting treatment of salt industry at par with Irrigation pumping
& Agriculture and not under general category. They submitted that electricity is used
only for pumping of brine to the salt field for manufacture of salt during production
season i.e. normally from January to June every year. There is no use of electricity
during off-season. They have also stated that this industry also employs a large number of
seasonal labours and the process of production of salt is very similar to agricultural
production for which they should be treated at par with Irrigation pumping &
Agriculture and not under general industry category. We would like to observe that the
salt industry does not fit into the present classification of agricultural irrigation
pumping category as defined in OERC Distribution (Condition of Supply) Code, 1998.
Further, the classification of Irrigation pumping & Agriculture with lower tariff is a
historical legacy targeted to promote agricultural production. We would like to clarify
that if the nature of their operation is seasonal they will not be paying any energy
charges during the off-season period when no energy is consumed. Hence, we are unable to
accede to the request.
|
6.36.2
|
The objection raised by some
objectors (OCA) that bi-monthly domestic bills are increasing loss to the licensee is not
correct as the licensee is already retaining charges of supply of two months against
security deposit which can be utilized as working capital.
|
6.37
|
Multi-year Tariff
|
6.37.1
|
In course of the hearings, the
utilities as well as some of the respondents spoke about the element of uncertainty and
risk inherent in an annual tariff setting exercise and they pleaded for introduction of a
multi-year tariff regime which would reduce such uncertainty and bring in predictability.
We, too are conscious of the need for greater certainty in the regulatory treatment of a
host of issues having direct impact on tariff setting. It shall be our endeavor to set in
motion a multi-year tariff regime effective from April, 2003 for FY 2003-04 after wide
publicity and valued consultation with all the stakeholders. We have, in fact, initiated
preparation of a five-year sectoral plan covering generation, transmission and
distribution which will provide key inputs to this exercise. The draft consultation
document which is currently under finalisation will also be brought out to facilitate the
process of such consultation and obtain comments from the various stakeholders.
|
6.37.2
|
The utilities have to improve upon
their own performance within a stipulated time frame by upgrading their managerial skills
and efficiency by scrupulously adhering to certain operational norms like reduction in the
level of loss, attaining certain level of billing and collection efficiency, setting a
target for investment and avoiding time and cost overruns in execution of projects, etc.
This calls for fixing a target to be achieved over a "Control period" than a
target confining to a single year to provide a kind of predictability to the consumers,
their own shareholders and to the Regulatory Commission. The Commission considers it
prudent and desirable to go for a multi-year tariff regime for which the utilities should
conform themselves to a multi-year target setting in the areas stated above. We also feel
that the FY 2001-02 should be considered as the base year for all calculations as
suggested by the Kanungo Committee.
|
6.37.3
|
Some objectors raised the issue that
the licensee should accept the payment by account payee cheque instead of demand draft.
|
6.37.4
|
As per the existing provision in
OERC Distribution Code, 1998 (Regulation 1993), the bill amount shall be paid by the
consumer either in cash or by bank draft or by banker's cheque or where specifically
allowed by the licensee by account payee cheque or credit cards. Hence, the facilities are
already available in the OERC Regulation.
|
6.37.5
|
Some of the objectors advocated in
favour of uniform retail tariff throughout the state. Historically, uniform tariffs have
been used in Orissa, and indeed in all states of India, in spite of significant cost
differences to serve different geographic areas. Prices that differ in relation to
differences in cost generally make better use of society's resources than uniform tariffs.
|
6.37.6
|
Some objectors suggested for
reduction of cross subsidies. As has already been dealt in the Retail Supply Tariff order
of the Commission dated 19.01.2001, the tariff structure that this Commission inherited
was a highly distorted one. In the past years by rationalising the tariff structure it has
been ensured that there is a progressive increase in the rate of tariff for those who are
paying less than the average cost of supply. The Commission in future tariff revisions
will take steps for rationalization of tariff i.e. gradually adopting a uniform rate for
all consumer categories using electricity on the same voltage of supply which is a good
measure of the cost of supply or thereby reduce the cross subsidy between groups of
consumers.
|
6.37.7
|
The question of a reasonable railway
traction tariff raised by the S.E. Railway so as to maintain a railway traction tariff,
not exceeding that of HT industrial consumer was also highlighted for consideration by
OERC. The Commission would like to clarify that the railway traction tariff in Orissa is
at par with that of HT or EHT consumers depending upon the voltage of supply as the tariff
structure has been totally linked to the voltage of supply. Railway traction tariff is
lower in Orissa. Therefore railways should have no grouse on this account.
|
6.37.8
|
The railways had also raised the
issue of a single part tariff which is today applicable only to very large industries with
a guaranteed off-take to which category the railways does not belong.
|
6.37.9
|
The second issue relates to the
prevalent maximum demand charge in Orissa. It needs to be clarified that the Commission
does not propose to make any change to the current maximum demand charge in force. Railway
further concern about recording and charging of maximum demand for individual supply
points as per the existing system turned out to be totally unrealistic as the railways
were moving loads for all substations along this track. In this connection, the Railways
quoted the letter of Ministry of Energy CEA, New Delhi dated 21.10.1988 proposing billing
on the basis of simultaneous maximum demand recorded in contiguous substation of the SEBs.
It may be mentioned here that the railway traction supply is from the EHT network of the
GRIDCO and the billing is done by the various supply companies to the railways in their
area of license. Therefore, the Commission is of opinion that the issue should be mutually
discussed by the railways with the four distribution companies and their views on the
matter may be placed before the Commission for taking a holistic view.
|
6.37.10
|
The railways also proposed that the
integration period of 30 minutes for measurement of maximum demand in respect of railway
traction has been changed to 15 minutes. The railways requested that the OERC may consider
restoration of integration period 30 minutes as per the earlier method which is also in
confirmity with the clause No.2(8) of Electricity Supply Act, 1948.
|
6.37.11
|
The Commission deliberated on this
issue and observed that 30 minute integration period for all categories has been provided
in the Regulation of ASEB, Ahmedabad Electricity Company, MPSEB, HSEB, DVP, Gujurat,
Maharashtra, Tamil Nadu. Fifteen minute integration period has been provided by UPERC,
APERC for loads more than 4000 KVA, and for railway traction by WBSEB. There are SEBs with
one hour integration period also.
|
6.37.12
|
The railways earlier have made a
case that there can be growth of traction only if the cost of tariff matches the cost of
diesel locomotion. Keeping this fact in view, the Commission will consider favourably the
adoption of 30 minute integration period which can reduce the overall tariff for railways.
It will be, therefore, desirable to discuss the issue along with the issue of simultaneous
maximum demand due to feed extension for meeting the demand of the rolling stocks after
discussion with the various supply companies of the state. The railways and DISTCOs may
mutually discuss and come up with a proposal for consideration of the Commission. This
will require amendment of the supply regulation OERC Distribution (Condition of Supply)
Code, 1998. Till such time the present arrangement shall continue.
|
6.38
|
Consumer Service
|
6.38.1
|
Construction Power Objection
was raised by M/s. Aditya Aluminium that the industries under construction may be
classified separately and no demand charge should be levied on construction power. There
seems to have no logic behind the objection as the licensee is to arrange/book, the
quantum of power as per the contract demand and pay fixed charge against the said quantum
of power which he has to recover from the consumer. |
6.38.2
|
Observations for
overdrawal penalty clause For the purpose of calculation of minimum demand
there should not be any differentiation between peak or off peak hours. As such we do not
accept the proposal of the objector for any change in existing tariff order. |
6.38.3
|
Observation for incentive
higher consumption Some objectors such as M/s. Mahanadi Coal fields Ltd.
pleaded that load factor as per standard nomenclature should be based on Maximum Demand
and should have no relation with Contract Demand. |
6.38.3.1
|
It is clarified that, for the
purpose of calculation of incentive energy, the standard terminology of Load Factor has
not been used, rather it is only the ratio of the total number of units consumed during a
given period to the total number of units that would have been consumed had the contract
demand or the maximum demand whichever is higher was maintained through out the same
period.
|
6.38.3.2
|
It may be noted that the incentive
tariff for HT/EHT category of consumers was introduced in the OERC RST order dt. 30.12.99
where incentive energy was considered above the load factor of 50% of contract demand.
Further as mentioned in the OERC RST order dt. 19.01.2001 "Some objectors objected to
recording of load factor during the FY 1999-00 in excess of 100% in the filing made by the
licensee on the ground that it had an element of absurdity. As prescribed in OERC
Condition of Supply Regulation, 1998 load factor of a consumer under no circumstances can
exceed 100%" Therefore consumption ratio was adopted in place of load factor for
determination of incentive energy. It is further clarified that for the purpose of
calculation of incentive energy, power factor should be taken as 0.9 for conversion from
KVA to KW or MVA to MW.
|
6.38.4
|
Treatment of Past Losses With
regard to the treatment of past losses, the Commission would like to clarify that in the
absence of audited accounts of the licensees, it is difficult to determine the extent of
loss that could have been admissible within the provisions of the Sixth Schedule to the
Supply Act, 1948. A decision on this issue can be taken only when the accounts are
compiled and audited in accordance with the relevant regulations of OERC. |
6.38.4.1
|
The Commission observes with
displeasure about non-maintenance of the asset register by licensees inspite of its
earlier direction. The Commission directs that maintenance of asset register must be
completed latest by 31 August and compliance reported.
|
6.38.5
|
Demand charges during
statutory power cut The levy of demand charge during the period of
statutory power cut has to be dealt in accordance with he relevant conditions of OERC
(condition of supply) Code,1998. |
6.38.6
|
Meter Rent The
Commission examined the issue of rents chargeable for the meters supplied by the licensee
and does not consider it necessary to make any change the rate already fixed by the
Commission in its order dtd.19.01.2001. |
6.38.7
|
Quality of Supply &
Service Interruption, low voltage and unreliable supply is a matter of
serious concern to the Commission which is taking appropriate steps to verify the data
furnished by the licensee in this regard through an affidavit to the Commission. The
Commission also is taking effective steps for monitoring of these parameters for meeting
the supply standards as prescribed by it. |
6.38.8
|
Unauthorised and Illegal
abstraction of electricity The issue of unauthorised abstraction of
electricity is one of the principal causes of high commercial losses in the licensee's
system which is being monitored every month at the Directors' Level Meeting. The licensees
must take the help of law and order authorities and the Commission is committed to allow
any additional expenditure on account of curbing the theft and unauthorised abstraction of
electricity which must be taken up vigorously and it shall continue to be monitored at the
Commission's level. |
6.39
|
Rural Electrification The
rural electrification work to be taken up by the licensee as a capital grant. In this
connection, the Kanungo Committee have suggested for setting up of Rural Engineering,
Planning Organisation (REPO) and Rural Electrification Planning Units (REPU) under
Government of Orissa to monitor R.E. and L.I. works. As and when REPO AND REPU start
functioning it is believed R.E. & L.I. works will be expedited. |
6.40
|
Special Tariff for Power
Intensive Industries
|
6.40.1
|
The Commission has taken a decision
to continue with the tariff structure approved vide its tariff order dtd.19.01.2001 in
respect of all categories of consumers supplied by the distribution and retail supply
licensee. In this connection, the Commission also examined the issues regarding a special
tariff of the power intensive categories of industries. Some of the objectors also
submitted that a preferential treatment to the EOUs was a burden to a licensee and the
general consumer, as costly power has to be procured to meet such demand. The Commission
reiterate its commitment for rationalisation of the tariff structure linked to the voltage
of supply. Keeping the above objective in view, incentive tariff has already been
introduced for consumers of contract demand of 110 KVA and above available power supply at
HT or EHT in the previous tariff orders. That automatically reduces the per unit cost of
electricity with a higher level of consumption as the fixed cost in the form of maximum
charge gets distributed over a larger number of units.
|
6.40.2
|
The Commission however, has taken
note of very special nature of some of the industries who provide continuous high load
factor to the system and in the process provides a support during the off-peak hours as
base loads besides dissuading such units from setting up CPPs. On the other hand this
helps in getting cross subsidy from such classes of consumers to other classes of
consumers who are charged below the level of cost of supply. This has also to be weighed
against the option of having an industry within its fold of supply of a licensee with a
lower profit margin and the option of not having the industry at all. The Commission has
favourably considered in the past the above option and have allowed signing of special
agreement with a proposal of guaranteed off-take at a rate lower than the normal rate
applicable to similar class of industries.
|
6.40.3
|
The Commission in its past orders
had approved tariff for consumers with a contract demand with 100 MVA and above with a
guaranteed load factor of 80% @ 200 paise/unit without levy of any demand charge. The
Commission has approved a rate of 182 paise/unit with a guaranteed load factor of 90% and
a contract demand of 50 MW in respect of INDAL by approving for entry into special
agreement between INDAL and WESCO. This rate is linked to the Bulk supply Tariff approved
in the Commission's order dtd.19.01.2001. This rate will undergo a change on account of
revision in Bulk Supply Tariff.
|
6.40.4
|
The Commission will examine such
special agreements for approval as and when it is placed before the Commission provided
the rates are within the parameters indicated above.
|
6.40.5
|
Any licensee willing to enter into
special agreement with a rate other than that for a particular category can do so provided
the licensee undertakes to absorb the difference between the revenue at the approved rate
and the rate at which it proposes to enter into a special agreement with any industry.
However, entry into special agreement should be non-discriminatory in nature i.e.
consumers falling into same category should be offered similar rates.
|
6.41
|
Emergency power supply to
CPPs The Commission examined the request for raising the level of emergency
power availability to 75% of the capacity/co-generation plants to reduce the burden on the
smaller industries. The Commission would like to clarify that in the tariff order
dtd.19.01.2001, a rate of 380 paise/unit has been fixed for emergency power supply to CPP.
The order does not stipulate levy of any demand charge for emergency power supply to CPPs.
|
6.42
|
The revenue requirement estimated by
NESCO has been duly examined at the Commission's end.
|
6.43
|
Corrective measures and
alternative calculation of revenue requirement
|
6.43.1
|
During the tariff hearing the State
Government did not appear and participate despite due services of notice. It even failed
to attend the Commission Advisory Committee Meeting in this connection. The Commission has
received no assistance or commitment from the State Government and has had to proceed in
the absence of Government's participation. It may be mentioned that during the Workshop on
09.01.2000, organized by the Department of Energy, Government of Orissa, the Commission
made a presentation elaborating the various corrections as outlined in para 6.43.6 (A)
below. In the circumstances, the Commission has been constrained to recommend several
measures as listed below for approval by the Government of Orissa w.e.f. 01.04.2001 to
bring down the cost of power, cost of transmission of GRIDCO and cost of distribution. In
view of the urgency and importance of the measures for consumers of the State and for the
electricity industry and success of the State policy of reforms, it is absolutely
essential that the State Government should communicate their decision on the
recommendations without delay, in order that the Commission may give effect to the
alternative calculation of revenue requirement. Everyday of delay causes huge avoidable
cost to the consumers and the revenue gap of the licensees will go on snowballing beyond
control.
|
6.43.2
|
The terms and conditions for
purchase of power from OHPC by GRIDCO is governed by the power purchase agreement between
OHPC and GRIDCO. The interim PPA between OHPC and GRIDCO for purchase of power from OHPC
old stations upto 31 March 2001 has been approved by OERC with certain observations. Both
OHPC and GRIDCO have been directed to submit the PPA to OERC for approval. The new PPA in
respect of these stations effective from 01.04.2001 has not yet been received till date.
Based on the latest commercial practice OERC directs that parameters like O&M
escalation, return on equity and depreciation in respect of these stations will be
calculated in accordance with the norms given in this order. The Commission also decides
to apply lower rate of depreciation (pre-92 rates) for transmission and distribution
assets to bring down the cost of supply to the consumer.
|
6.43.3
|
Similarly the Commission would like
to depart with respect to the O&M escalation, ROE and depreciation norms in respect of
UIHEP to bring down the input cost of power.
|
6.43.4
|
(a) OHPC old stations
-
O&M escalation taken as per the weighted average of growth of Wholesale Price Index
and Consumer Price Index for FY 2001-02 which works out to 2.5%. The same rate has been
adopted for FY 2002-03.
-
Return on Equity is calculated @ 12% on OHPC's own investment of Rs 22.56 crore.
-
Depreciation has been allowed to the extent of loan repayment during the year.
(b) UIHEP
-
O&M escalation taken as per the weighted average of growth of WPI and CPI for FY
2001-02 which works out to 2.5%. The same rate has been assumed for FY 2002-03.
-
ROE has been calculated @12% on equity of Rs.298.70 crore.
-
Depreciation has been allowed to the extent of loan repayment during the year.
(c) GRIDCO & DISTCOs
Depreciation has been calculated at pre-92 rate for years 2001-02 and 2002-03 both in
respect of transmission and distribution business. |
6.43.5
|
The Commission is entrusted with
heavy responsibility as per Section 11 of the OER Act, 1995 under the head "Functions
of the Commission". It would be appropriate to quote the relevant portion of the
above section. "11(1) Subject to the provisions of this Act, the Commission shall
be responsible to discharge, amongst others, the following functions, namely-
-
to aid and advise, in matters concerning generation, transmission, distribution and
supply of electricity in the State ;
-
to regulate the working of licensees and to promote their working in an efficient,
economical and equitable manner;
.
|
6.43.6
|
(A) In view of the above provisions,
the Commission would be failing in discharging its responsibilities without giving proper
advice to the State Govt. for adopting the corrective steps to bring the reforms back to
rails. Commission has applied the following correctives in determining the revenue
requirement for FY 2001-02 and 2002-03:-
-
Interest on GRIDCO bond issued by DISTCOs for the power purchase loan liabilities has
been calculated @8.5% for FY 2001-02 and FY 2002-03
-
Interest on World Bank loan has been calculated in terms of its original sanction
treating 70% as loan and 30% as grant for FY 2002-03
-
Interest on all existing bonds issued by GRIDCO have been calculated @8.5% for FY
2001-02 and FY 2002-03 assuming resecuritisation of the same.
-
New bonds of Rs.638 crore to be issued against power purchase liabilities of CPSU's as
on 28.02.2001 have been calculated @8.5% for FY 2002-03.
-
Impact of zero coupon bonds of Rs.400 crore issued by GRIDCO to Government of Orissa
against upvaluation of assets has not been considered for FY 2001-02 and FY 2002-03.
-
Outstanding loans from REC and PFC have been assumed for resecuritisation with a tax
free rate of 8.5%.
-
In view of swapping of Government and GRIDCO dues, interest on Government loan of
Rs.168.71 crore has not been allowed as a pass through for FY 2002-03.
-
Interest on GOO loans has not been allowed arising out of upvaluation of OHPC assets.
-
GOO loan of Rs.576.57 crore has been treated as loan on perpetuity.
(B) The Commission therefore advises Government of Orissa under section 11(1)(a) of the
OER Act, 1995 to approve the correctives w.e.f. 01.04.2001 as outlined in this para from
(i) to (ix) above to bring down the cost of power for the year 2001-02 and 2002-03. |
6.43.7
|
In this context the Commission deems
it fit and proper to review the whole question of revaluation of the assets of the
erstwhile OSEB and Government of Orissa, at the time of revesting of the same with GRIDCO
and OHPC and the impact of the revaluation on the tariff to be fixed now and in future. At
the time of revesting GRIDCO and OHPC were wholly owned Government companies. Section
23(4) of the OER Act, 1995 did not require any such revaluation. When the assets of the
OSEB vested in the State Government, the State Government paid nothing for it and did not
incur any expenses. The revaluation seems to have been purely notional, agreed to between
State Government on the one hand and GRIDCO and OHPC on the other hand, the latter being
Government companies at that time. Clause 2 of the statutory orders dated 01.04.1996
vesting assets with GRIDCO and OHPC runs as follows. "In accordance with section
24 of the Act, the fair value shall be duly determined of the property or rights in the
undertaking involved at the time of transfer to or involvement of any person or body other
than the wholy owned Government company or companies."
No such fresh and due determination of fair value appears ever to have been done - not
even at the time of involvement of DISTCOs operating under the aegis of private investor.
There may have been some reason (like credit worthiness of GRIDCO and OHPC), at the
material time, for state and GRIDCO/OHPC agreeing to some notional revaluation, but the
Commission does not think any such reason to be relevant for the purpose of tariff
setting, involving rights of consumers and third parties or useful in the context of
present realities in the industry. The Commission therefore in the public interest has
attempted to nullify the effects of revaluation in the present tariff setting. |
6.43.8
|
Based on the observations of the
preceding paragraphs of this order and prudent commercial consideration relying on the
existing purchase power agreements, relevant rules, orders and evidential documents placed
before the Commission. The Commission determine the revenue requirement for the FY 2001-02
as well as for the year 2002-03. Accordingly the revenue requirement as estimated in two
scenarios (i) with correctives (ii) without correctives for 2001-02 is given in Table :
24. Details of calculation of revenue requirement is given in Annex-A1. Table : 24
(Rs. in Crore)
Name of the licensee |
2001-02
(With correctives) |
2001-02
(Without correctives) |
Proposed sale in MU |
CESCO |
775.00 |
777.83 |
2461.48 |
NESCO |
435.44 |
444.00 |
1194.87 |
WESCO |
556.08 |
562.09 |
1756.19 |
SOUTHCO |
316.60 |
323.52 |
901.47 |
Additional RR on account of change in cost
of power and transmission by GRIDCO |
|
301.28 |
|
Total for DISTCOs |
2083.12 |
2394.34 |
6314.02 |
|
6.43.9
|
The revenue requirement for FY
2002-03 in both the scenarios (i) with correctives and (ii) without correctives as per our
recommendation regarding cost of power and cost of transmission based on the principles
enunciated in the earlier paragraphs of this order is given in Table : 25. Details of
calculation of revenue requirement is given in Annex-A2. Table : 25
(Rs. in Crore)
Name of the licensee |
2002-03
(With correctives) |
2002-03
(Without correctives) |
Difference |
Proposed sale in MU |
CESCO |
767.34 |
918.85 |
151.51 |
2768.03 |
NESCO |
421.62 |
509.25 |
87.63 |
1329.36 |
WESCO |
559.43 |
670.63 |
111.02 |
1980.13 |
SOUTHCO |
327.51 |
393.81 |
66.30 |
1078.58 |
Total for DISTCOs |
2075.90 |
2492.54 |
416.64 |
7136.10 |
|
6.43.10
|
It is evident from the calculations
given in Table above that it will require a very stiff upward revision in Retail Supply
Tariff in respect of all consumers of the State if the correctives proposed by the
Commission is not accepted by the government for immediate implementation. Incidentally,
the correctives applied by the Commission are, by and large, in line with those of Kanungo
Committee recommendation with minor modifications and few additional measures.
|
6.43.11
|
In this connection, the
recommendation of the Kanungo Committee is very pertinent wherein they had advised an
external financial support other than debts to the tune of Rs.3240 crore during a
transition period of 4 years from 2001-02 to 2004-05 to keep the tariff structure static
at the current level and proposing to raise it by about 18% in the year 2005-06. It is
expected that the Government will consider the advice of the Commission in this regard and
take immediate steps so as to avoid a stiff rise of tariff to all classes of consumers
particularly when State Government may not be in a position to provide financial support
as contemplated in the Kanungo Committee report.
|
6.43.12
|
However, if the decision of the
Govt. of Orissa goes contrary to the advice tendered by the Commission, the revenue
requirement for the FY 2001-02 and 2002-03 as determined without applying the correctives
shall be due for recovery from the consumers.
|
6.44
|
Expected revenue from
charges The expected revenue from charges in respect of all the DISTCOs
have been determined by the Commission as explained in para 6.9.5.2 of this order in Table
15 & 16. |
6.45
|
For the purpose of RST 2001-02, the
licensee has given a proposal which is given in annex to this order.
|
6.45.1
|
In para 6.43.8 and 6.43.9 the
revenue requirement has been calculated by applying necessary correctives to power and
transmission cost payable to GRIDCO and distribution cost.
|
6.45.2
|
Any revision of tariff in accordance
with the OER Act, 1995 can be applied prospectively. The reason is that a clear seven
day's notice before its implementation is necessary under Sec. 26(5) of the OER Act, 1995.
Revision of tariff cannot be done in case of the FY 2001-02, which is already over. This
situation arose because of deficiencies on the part of the licensees to submit the revenue
requirement and tariff application in complete shape in time. As such, the tariff revision
proposal for the year 2001-02 submitted by the licensee is rejected.
|
6.45.3
|
As observed in para 6.43.12 if the
decision of the Govt. of Orissa goes contrary to the recommendations made by Commission
the revenue requirement for the year 2001-02 as determined in this order without applying
the correctives shall be due for recovery. Since the FY 2002 is already over and no
fixation of tariff is possible with retrospective effect, the Commission will treat the
gap between the revenue requirement and expected revenue for the FY 2001-02 as a
regulatory gap for recovery at a future date.
|
6.45.4
|
In as much as tariff proposals for
FY 2001-02 have been rendered infructuous, GRIDCO and DISTCOs propose that the Commission
proceed under Section 26 (6) of the OER Act, 1995 to determine tariff for FY 2002-03 on
the basis of revenue requirement for that year as approved by the Commission. Hence the
Commission has proceeded under section 26(6) to determine tariff under section 26(6) of
the OER Act, 1995 for the FY 2002-03.
|
6.45.4.1
|
The Commission have made several
recommendations to the Government of Orissa for their implementation w.e.f. 01.04.2001.
Accordingly the Commission have determined the Retail Supply Tariff applying all
correctives based on its recommendations to the Government. If a decision to the contrary
is taken by the Government the revenue requirement for the FY 2002-03 as determined
without applying the correctives shall be due for recovery from the consumers. It will
raise the revenue requirement by Rs.416.64 crore on the basis of our present estimate. A
tariff schedule is given in the Annex-D3.
|
6.45.5
|
This is based on the assumption that
the existing retail supply tariff as approved by OERC in order dated 19.01.2001 shall
continue upto 31.07.2002 and the rates indicated in Annex-D3 shall be valid from 01.08.2002 to 31.03.2003 provided the
recommendation as indicated earlier are not accepted by the Government latest by 15 July
2002.
|
6.45.6
|
This tariff effective from
01.08.2002 shall be subject to such proportionate reduction as may be necessary to the
extent the Government accepts the recommendation made by the Commission. The reductions
being purely arithmatical in nature shall take effect without any further proceeding for
amendment under section 26(6) of the OER Act 1995. However it is made clear that in case
of such reduction a fresh notification under section 26(5) of the OER Act will be made by
the licensees with the approval of OERC.
|
6.45.7
|
Finally, the Commission orders as
follows with reference to the prayers of the applicant. The Commission does not approve
the retail supply tariff as proposed by NESCO for 2001-02 and rejects the tariff revision
proposal.
|
6.45.8
|
The Commission also does not approve
the revenue requirement for the FY 2002-03 as proposed by NESCO and directs for
implementation of Retail Supply Tariff as determined by the Commission in this order to be
effective after expiry of seven days of the publication by the licensee under section
26(5) of the OER Act 1995.
|
6.45.9
|
In case the recommendations made by
the Commission for necessary correctives for determination of revenue requirement are
accepted in toto by the Government, the retail supply tariff as approved by OERC in order
dated.19.01.2001 shall continue unchanged after 31.07.2002.
|
6.45.10
|
Pursuant to order dated 19.04.2002
of the Hon'ble High Court of Orissa the order is not being notified to NESCO in terms of
section 26(6) but is filed in sealed cover in the Hon'ble High Court of Orissa. The
application of M/s NESCO is disposed off accordingly.
Sd/-
(B.C. JENA)
MEMBER
|
Sd/-
(H. SAHU)
MEMBER
|
Sd/-
(D. C. SAHOO)
CHAIRMAN
|
|